General Engineering Guide 2015
General Engineering Guide 2015
400)
MCWP 3-17.7
GENERAL ENGINEERING
February 2015
General Engineering
Contents
Page
PREFACE.............................................................................................................. iv
INTRODUCTION ................................................................................................... vi
Chapter 1 GENERAL ENGINEERING AS A DISCIPLINE AND FUNCTION .................... 1-1
Life Cycle Activities ............................................................................................. 1-1
Employment Considerations .............................................................................. 1-3
Chapter 2 GENERAL ENGINEERING SUPPORT TO OPERATIONS .............................. 2-1
Range of Military Operations .............................................................................. 2-1
Theater and Operational Levels ......................................................................... 2-1
Tactical Level ...................................................................................................... 2-6
Chapter 3 PLANNING AND DESIGN ................................................................................. 3-1
Joint General Engineering Planning ................................................................... 3-1
United States Army and United States Marine Corps General Engineering
Planning .............................................................................................................. 3-4
General Engineering Design ............................................................................ 3-15
Engineer Work Line .......................................................................................... 3-21
Unified Facilities Criteria ................................................................................... 3-23
Field Force Engineering ................................................................................... 3-24
Chapter 4 CONSTRUCTION............................................................................................... 4-1
Plans and Estimates ........................................................................................... 4-1
Project Management .......................................................................................... 4-3
Methods of Construction..................................................................................... 4-4
Construction Materials ........................................................................................ 4-6
Construction Techniques .................................................................................. 4-14
Chapter 5 SEAPORTS ........................................................................................................ 5-1
Figures
Figure 1-1. Contiguous, noncontiguous, and unassigned areas ............................................ 1-8
Figure 3-1. Division engineer work line in contiguous operations ........................................ 3-22
Figure 3-2. Division engineer work line in noncontiguous operations .................................. 3-23
Figure 4-1. Project management process .............................................................................. 4-3
Figure 6-1. Airfield damage categories ................................................................................ 6-16
Figure 9-1. Base camp development planning process ......................................................... 9-8
Figure 9-2. Southeast Asia hut company cluster.................................................................. 9-15
Figure 11-1. Power continuum ............................................................................................. 11-4
Tables
Introductory table-1. Modified U.S. Army term ......................................................................... vii
Table 3-1. General engineering in the military decisionmaking process .............................. 3-11
Table 4-1. Sample stockage level for engineer Class IV supply point ................................... 4-8
Table 9-1. Sample construction standards ............................................................................. 9-6
Table 9-2. Minimum distances between facilities ................................................................. 9-12
Table 10-1. Example of base camp estimated solid-waste disposal in tons per day ......... 10-12
Table 11-1. Example of estimated power plant sizes, in kilowatts ....................................... 11-8
Table A-1. Metric conversion chart .........................................................................................A-1
Table B-1. Summary table—base camp engineer construction effort....................................B-1
Table B-2. Summary table—base camp aggregate requirements .........................................B-2
Table B-3. Construction effort—site preparation requirements ..............................................B-2
Table B-4. Construction effort—facilities requirements (temporary to semipermanent
standard/temperate climate/wood frame) ...........................................................B-3
Table B-5. Motor park .............................................................................................................B-4
Table B-6. Soldier or Marine support facilities ........................................................................B-4
Table B-7. Covered/open storage requirements for 14 days of stockage ..............................B-4
Table B-8. Cold storage requirements for 14 days of stockage .............................................B-5
Table B-9. Fuel storage ..........................................................................................................B-5
Table B-10. Soldier or Marine housing ...................................................................................B-5
Table B-11. Quality-of-life standards for tentage....................................................................B-5
Table B-12. Selected tentage planning factors ......................................................................B-6
Table B-13. General planning factors for potable and nonpotable water requirements.........B-6
Table B-14. Selected transportation information ....................................................................B-7
The U.S. Army proponent of this publication is the U.S. Army Engineer School. The preparing agency is the
Maneuver Support Center of Excellence Capabilities Development and Integration Directorate; Concepts,
Organizations, and Doctrine Development Division; Doctrine Branch. Send comments and recommendations on
DA Form 2028 (Recommended Changes to Publications and Blank Forms) to Commander, U.S. Army
Maneuver Support Center of Excellence, ATTN: ATZT-CDC, 14000 MSCoE Loop, Suite 270, Fort Leonard
Wood, MO 65473-8929; e-mail the DA Form 2028 to <usarmy.leonardwood.mscoe.mbx.cdidcodddengdoc
@mail.mil>; or submit an electronic DA Form 2028.
Marine Corps personnel should submit suggestions and changes by e-mail to <[email protected]> or by mail
to Deputy Commandant for Combat Development and Integration, ATTN: C116, 3300 Russell Road, Suite 204,
Quantico, VA 22134-5021.
Chapter 11 discusses electrical power systems and design considerations for reliability, efficiency,
and scalability. It also discusses the emerging requirements to store electricity and incorporate
renewable sources of energy. It provides an overview of Service capabilities and electrical safety
requirements.
Chapter 12 discusses GE support to the sustainment/combat service support water functions of
production and distribution. The chapter discusses well drilling and includes water production and
distribution responsibilities, planning and design, Service capabilities, employment, and operations.
It expands discussion on water distribution within facilities as a plumbing task.
The GE doctrine provided in this manual presents an overview of a wide range of topics and allows the reader
to understand how the topics fit together. The engineer must refer to the referenced materials throughout the
manual to gain a complete understanding of the GE life cycle activities. This manual is not meant to be a
substitute for the creative thought, innovation, and initiative among engineer leaders, Soldiers, or Marines.
Rather, its intent is to build, enhance, and strengthen their present knowledge and understanding. General
engineers take their training, experience, capabilities, and understanding of doctrine and apply them to solve
and unravel unique and obscure challenges to meet operational needs. Based on current doctrinal changes, a
term for which this manual was the proponent has been modified for the purposes of this publication. (See
introductory table-1 for the specific term change.)
CONSTRUCTION
1-5. Construction is the art or process of building or assembling structures such as base camps, bed-down
facilities, or infrastructures. It consists of a wide range of activities, methods, and techniques used to
combine individual parts and to assemble resources together to create a greater whole. Construction is
performed by military units, contractor personnel authorized to accompany the force (CAAF), and non-
CAAF to accompany the force. Facilities and infrastructure are built using various methods that are
evaluated and determined during planning and design.
OPERATION
1-10. This manual discusses the operation of engineer-specific equipment and systems that produce
engineering effects. The operation of these systems usually requires specifically designed, equipped,
organized, and trained units or trained individuals. Some facility engineer organization examples include
facility engineer detachments and engineer utilities detachments. Some equipment or system examples are
power systems, waste treatment systems, and float bridges. The tasks of O&M are often grouped together
but are sometimes separated in this manual because the engineer may be required to maintain some things
that they are not required to operate, such as an airfield that is operated by a U.S. Army aviation unit.
1-11. Base camp operation is the O&M of the base camp physical plant and the provision of base camp
services and support measures that are needed to achieve the purpose of the base camp and to fulfill
functional requirements. The skills needed for operating and managing base camps do not reside in any
single branch or functional area. A grouping of capabilities is required to produce synergic effects within
the base camp. Success hinges on placing the right people with the right skill sets at the right time.
Shortfalls in skills or capabilities at base camps are filled through tenant units, augmentation reachback
measures, or contracted support methods. (See ATP 3-37.10/MCRP 3-17.7N for additional information on
base camp operations.)
MAINTENANCE
1-12. Maintenance is the process of keeping facilities and infrastructure in good working condition so that
they can continue functionality and good service for the community they support. Engineers review
maintenance service records, conduct physical inspections, order parts, request services, and schedule
repair or service maintenance of individual facilities or of the overall infrastructure.
1-13. Facility maintenance responsibility has always been a teamwork process for the following reasons:
The commander has the overall responsibility to ensure that maintenance gets the proper
attention it deserves and the adequate resources it requires. The commander leads the
maintenance efforts.
The using units or tenant units are responsible for properly maintaining their own facilities.
Because they use the facilities on a daily basis, they are responsible for performing routine
upkeep and for reporting facility maintenance issues beyond their repair capabilities.
Engineers are responsible for assisting in facility maintenance areas that are beyond the training
and expertise of tenant units. This includes providing engineer expertise and resources to resolve
facility maintenance issues and bringing in external specialized engineering services. Engineers
can conduct facility assessments, inspections, services, maintenance, and repair.
1-14. This manual discusses the maintenance of completed GE projects and engineer-specific equipment
and systems. Maintenance and repair tasks are also often grouped together but are sometimes separated in
this manual because engineers may be responsible for repairing some things that they are not responsible
for maintaining, such as a finished well that has been turned over to a logistics unit for O&M.
1-15. The life cycle activities of O&M are discussed within the chapters of this manual for each specific
area. This manual discusses specific O&M requirements for construction, seaports, airfields, heliports,
roads, railroads, bridges, base camps, real estate, power systems, and water production.
EMPLOYMENT CONSIDERATIONS
1-18. General engineering consists of those engineering capabilities and activities, other than combat
engineering, that modify, maintain, or protect the physical environment (JP 3-34). GE encompasses the
engineer tasks that establish and maintain the infrastructure required to conduct and sustain military
operations. Examples include the construction, repair, maintenance, and operation of infrastructure,
facilities, line of communications (LOC), bases, terrain modification and repair, and selected explosive
hazard activities. (See JP 3-34.)
1-19. This manual serves as the primary reference for planning and executing GE as an engineer function
at the U.S. Marine Corps level and as an engineer discipline at the U.S. Army level. It is directly linked to
ADRP 3-0, FM 3-34, and JP 3-34.
1-20. GE is the most diverse of the three interrelated engineer functions and is usually the largest
percentage of all engineer support provided to an operation. GE missions are typically performed in a joint,
interagency, and multinational environment. Besides occurring throughout the AOs at all levels of war and
aside from being executed during every type of military operation, GE may employ many of the engineer
military occupational specialties within the U.S. Army and U.S. Marine Corps.
1-21. GE units are organized and equipped to respond to requirements across the range of military
operations. Engineer units with a GE mission must be trained and prepared to integrate engineer disciplines
or functions to support the maneuver commander. They must also be able to use and integrate geospatial
products into their operations and be capable of conducting limited combat engineering functions to
facilitate the construction mission. General engineers must be technically and tactically proficient to
conduct tasks across the range of military operations. They must also be well trained in small-unit tactics,
including convoy security, work site security, and limited offensive operations.
1-22. GE includes—
Constructing or repairing existing logistics support facilities, supply and LOC routes (including
bridges and roads), airfields, ports, water wells, power systems, water and fuel pipelines, base
camps, and force bed-down facilities. (Firefighting and engineer dive operations may be critical
enablers to these tasks.)
Conducting engineer tasks through a modified table of organization and equipment or through
the United States Army Corps of Engineers (USACE).
Conducting engineer tasks by using a combination of joint engineer units, civilian contractors,
HN forces, or allied engineer capabilities. (As the AO matures, the GE effort may transfer to
civilian contractors, such as to those who operate under the logistics civil augmentation
program).
Incorporating field force engineering (FFE) to leverage capabilities throughout the Engineer
Regiment. (This includes linkages that facilitate engineer reachback.)
Requiring various engineer reconnaissance measures and assessments to be performed before, or
early on in, a particular mission. (See FM 3-34.170/MCWP 3-17.4.)
Supporting disaster preparedness planning, response, and defense support of civil authorities
(DSCA). (See ADP 3-28.)
Acquiring and disposing of real estate and real property.
Supporting the engineer protection planning and construction tasks that are not considered
survivability tasks under combat engineering.
Conducting camouflage, concealment, and deception tasks. (See ATP 3-37.34/MCWP 3-17.6.)
Performing environmental support engineering missions.
Conducting base or area denial missions.
Obtaining large quantities of construction materials, which must be planned and provided for in
a timely manner.
Producing construction materials.
Integrating environmental considerations.
Clearing areas of unexploded ordnance and mines before job tasks are executed if combat
engineers are not available.
Reducing obstacles in an unopposed or nonhostile environment.
1-25. GE support to combat engineering efforts is not limited to countermobility. If combat engineering
assets are completely committed or if they exceed combat engineering capabilities and the situation
requires augmentation or greater engineer support, general engineers may be tasked to assist mobility units
or be assigned other tasks. However, the primary focus of GE is to develop infrastructure to support
mobility, force projection, logistics, base camps, force bed-down facilities, stability operations, and DSCA.
FORCE PROTECTION
1-26. GE enhances protection areas through the planning, design, construction, maintenance, and
hardening of facilities, including—
Operational area security.
Antiterrorism measures.
Survivability.
Detainee and resettlement operations.
FORCE PROJECTION
1-27. GE enables force projection by the planning, design, and construction to deploy forces. This includes
peacetime locations, intermediate staging bases, support accesses, and force bed-down facilities.
LOGISTICS
1-28. GE enables logistics by the planning, design, construction, maintenance, and repair of LOC, base
camps, and bed-down facilities. LOCs support logistics but are not incorporated into this consideration area
of logistics.
PARTNER CAPACITY
1-29. GE builds partner capacity by training and developing local leaders and engineer assets and by
involving the local community. General engineers develop partner infrastructure and perform tasks
alongside partner engineers to develop physical and engineer capacities.
1-30. Engineer partnerships can be local, national, joint, interagency, or multinational, based on the mutual
cooperation to achieve common engineering goals and purposes. Partnerships can be beneficial in sharing
construction efforts, ideas, or techniques, which leads to overall improvements. An example of building
capacity is the USACE assistance with a water resource study and engineer unit completion of water
infrastructure projects with HN involvement.
1-31. General engineers may be involved in building partner capacity in the development of infrastructure.
Engineers combine the capabilities of all three disciplines to build partner capacity and develop
infrastructure, which is vital to stability and counterinsurgency tasks that yield the greatest return. Partner
capacity building is not exclusively limited to only performing GE tasks; it can also include other tasks to
achieve the overall purpose and desired effect. (For example, performing GE tasks that enable force
projection and logistics that change the manner in which the task is executed.)
1-32. The overall purpose of building partner capacity is to support the commander in improving the
conditions of HN leaders, institutions, and infrastructure development capabilities and influencing them to
achieve military objectives for self–defense. (See FM 3-34 for more information on building partner
capacity.)
1-33. In support of building partner capacity, GE tasks may include—
Building, repairing, and maintaining various infrastructure facilities.
Providing essential services.
Building roads to improve economic conditions using local labor resources.
Assisting the local population in improving the quality of drinking water systems.
Training, educating, and developing local leaders and engineers in public works projects,
including exchange programs and conferences to build stronger relations and bonds.
Developing local engineer projects that involve the community to a greater degree, such as parks
and recreational centers that improve the quality of life.
Using geospatial engineers and USACE resources to assist in locating and mapping local water
sources.
Improving local water distribution systems, such as adding pumping stations or constructing new
water wells.
INFRASTRUCTURE
1-34. GE develops infrastructure to support mobility, force projection, logistics, base camps, force bed-
down facilities, stability operations, and DSCA. Infrastructure support includes construction, rehabilitation,
repair, maintenance, and modification to landing strips, airfields, check points, main supply routes (MSRs),
LOC, supply installations, building structures, bridges, and other related aspects.
1-35. General engineer units (in support of infrastructure development) may also perform repair and
limited reconstruction of railroads or water and waste facilities. The basic capabilities of general engineer
units can be expanded by augmenting them with additional personnel, equipment, and training from
specialized engineer units or other sources. Such augmentation can expand general engineer capabilities to
conduct bituminous mixing and paving, quarrying and crushing, pipeline support construction, and dive
support to complete major construction projects (highways, storage facilities, seaports, airfields).
1-36. Specialized engineer units also support infrastructure efforts. GE infrastructure capabilities can be
expanded with assistance from—
Forward engineer support teams who are subordinate to FFE.
Laboratories and research centers, such as the USACE Reachback Operations Center.
Centers of expertise (USACE, Naval Facilities Engineering Command [NAVFAC], U.S. Army
Engineer School).
FFE.
Search and rescue companies.
Technical rescue teams.
1-40. Conduct general engineer life cycle activities tasks, which include—
Perform GE planning.
Perform GE design.
Perform GE construction.
Perform GE operation.
Perform GE maintenance.
1-44. Construct and maintain base camp and force bed-down facilities tasks, which include—
Perform bed-down development planning.
Perform base camp development planning.
Perform planning and facilities design.
Perform existing facilities conversion.
Conduct site selection and layout.
Construct base camps.
Provide force bed-down facilities.
Perform facilities O&M.
1-45. Perform real estate and real property maintenance activities tasks, which include—
Acquire real estate.
Manage real estate.
Manage utilities.
Transfer real estate and real property.
Legend:
AO area of operations
BCT brigade combat team
1-49. The concept of contiguous and noncontiguous operations includes the following:
A contiguous area of operations is where all of a commander’s subordinate forces’ areas of
operations share one or more common boundaries (FM 3-90-1). Because they share some
boundaries, units can more easily pool resources together and plan a common defense.
A noncontiguous area of operations is where one or more of the commander’s subordinate
force’s areas of operation do not share a common boundary (FM 3-90-1). This makes it difficult
to share resources and plan a common defense due to geographic distance or separation.
1-50. The combination of contiguous and noncontiguous operations that the commander selects impacts
the planning and execution of GE tasks for the following reasons:
In a contiguous AO, GE tasks are typically performed to the rear of division boundaries by
engineer units assigned to higher echelon headquarters.
In a less contiguous AO, GE tasks are required in forward areas in proximity to combat units.
Because GE assets are not organic to the brigade combat team (BCT), the BCT is normally
augmented with the necessary engineer assets to perform GE tasks within the BCT AO. The
types of GE assets that will augment the BCT depend on the types of missions to be
accomplished and the availability of engineers. Selected GE tasks may need to be performed by
combat engineers. (See FM 3-90-1, JP 3-0, and JP 3-34 for additional information on contiguous
and noncontiguous operations.)
1-51. The impact of the noncontiguous battlefield on GE tasks is numerous and includes increased—
Work site security. Because units perform GE near forward elements, contact with the enemy is
much more likely. Units conducting GE tasks must be proficient in combat operations to provide
for their own defense against such threats. Commanders directing the performance of GE
missions must treat these missions like any combat operation and protect personnel. General
engineers who focus on combat operations cannot focus on performing GE missions and tasks. It
benefits the maneuver commander to keep general engineers out of close combat operations and
focused on GE missions and tasks.
General and local work site security. During contiguous operations, units receive general
security from forward maneuver units. Local security is performed by internal assets. On the
noncontiguous battlefield, units face the same threat level as maneuver units operating in the
AO. In addition, there is the loss of ability to mass when attached or placed in direct support.
Numbers and lengths of LOCs and MSRs. With construction and maintenance of these assets
critical to sustainment/combat service support operations, the noncontiguous battlefield greatly
increases the GE effort required. Engineer planners can expect smaller-sized units to be spread
over greater geographic distances than during contiguous operations. Increased personnel
security along those routes is needed, and greater convoy security measures are required.
Facility construction efforts. Units operate with more autonomy within their own AO and
require facilities for deployment, supply, maintenance, and other sustainment/combat service
support activities.
Possibility of combat engineer units conducting additional GE tasks. Maneuver commanders
at BCT, regimental combat team, and higher levels must be able to task organic or assigned
combat engineer elements to conduct selected GE tasks. However, Marine engineers are task-
organized and can have different command relationships than other services. Regimental combat
teams do not have organic engineer units but can be designated engineer units in direct and
general support relationships, unless otherwise directed. Some tasks can be performed without
augmentation. A conscious trade-off of potential combat engineering tasks possibly being
performed must precede a commander’s decision to have these tasks executed. Selected
additional GE can be performed by combat engineer units when they receive additional
specialized equipment and expertise. However, combat engineers cannot perform all GE tasks.
Likelihood of GE assets being task-organized to a much lower level. Because of the great
distances involved in a noncontiguous AO and the impact on the geographical span of control,
engineer commanders may not effectively provide GE efforts in a manner that is responsive to
maneuver commander needs without a decentralization of authority. These assets can be placed
in direct support or attached to BCTs to provide timely and responsive GE support.
conduct of operations. Principles are considerations that should guide the employment of an organization or
function.
1-53. GE is guided by—
Sustainability.
Scalability.
Modularity.
Standardization.
Sustainability
1-54. GE solutions should be sustainable. The solutions may be a facility, a service, a technique, or a
procedure. There are many elements of sustainability that GE applies to achieve greater efficiencies for
increased effectiveness. Sustainability helps achieve increased effectiveness through increased operational
efficiencies, reduced logistics requirements, and reduced costs.
1-55. GE pursues the goal of delivering effective, resilient, sustainable, and efficient solutions. There is a
balance between efficiency and effectiveness. Sometimes operational requirements allow the balance to
shift to increased efficiency. At other times, operational requirements shift the balance toward increased
effectiveness, regardless of efficiency. When conditions permit, sustainable design and construction
practices should be considered during the development of GE solutions.
1-56. GE integrates and supports sustainability by—
Applying sustainable design, construction, and O&M practices.
Developing cost-effective solutions by using available resources to produce desired results.
Developing more efficient solutions that reduce the consumption of resources (energy, water,
labor, equipment, time, materials, money).
Reducing demands on sustainment/combat service support systems.
Reducing energy consumption by reducing demand, enhancing efficiencies, and using renewable
energy sources.
Developing sustainable facilities and infrastructures. (Reduce, recycle, and reuse waste with
solutions that are simple and inexpensive to operate, maintain, and repair.)
Developing initial life cycle planning cost estimates and economic analysis.
Notes.
2. See ATP 3-37.10/MCRP 3-17.7N for more information on sustainable base camps.
Scalability
1-57. GE solutions should be scalable. Scalable solutions can be easily expanded or contracted to meet
changing requirements without the need to redesign. Scalable solutions remain efficient and practical when
applied to a larger or smaller requirement.
1-58. The use of modular and multifunctional designs and systems contribute to scalability. Some
comprehensive, scalable GE solutions are integrated and developed at the joint and Service level.
Modularity
1-59. GE solutions should be modular. GE modular solutions contribute to scalability, but solutions may be
scalable without being modular. Modularity is the degree to which system components may be separated or
recombined. For example, standard military bridges are modular. A large project or system combines
smaller subprojects or systems. The use of modular systems and prefabricated or preengineered
components is maximized to facilitate rapid development and achieve scalability.
1-60. Modular construction techniques use standard materials and component sizes to build a single
structure or mass-produce components of the structure for quicker assembly. The use of modular
construction techniques does not ensure that the design is scalable.
Standardization
1-61. GE solutions should be standardized. Standardizing plans, designs, and construction methods or
techniques simplifies maintenance and repair. Standardization—
Reduces uncertainty in meeting mandatory requirements and provides for more accurate
estimates of materials, schedules, and costs.
Helps to improve and sustain proficiency and readiness through the universal application of
approved practices and procedures.
Reduces the adverse effects of personnel turbulence associated with reassignments and
facilitates interoperability between different organizations.
Uses standardized, scalable, and adaptable designs and construction methods.
Simplifies construction programming activities, improves early planning techniques, and
provides consistency in solution deliveries.
Uses standard solutions for one set of requirements that can be modified or adapted to meet
similar requirements.
Reduces costs and inventory requirements without having to maintain large inventories of
diverse parts or equipment.
Increases sustainability.
Seeks to standardize Service construction standards to provide commanders with consistent
expectations and the use of proven best practices and tactics, techniques, and procedures. (A
standard solution may not always be the best solution to meet unique requirements.)
1-62. An example of standardization is the development of the Unified Facilities Criteria. This is a
Department of Defense (DOD)-developed standardized facility planning, design, construction, and O&M
criteria system for use by all Service components. The Theater Construction Management System (TCMS)
contains standardized data that engineers can use to construct a variety of buildings.
1-64. Effective proactive planning and engineer initiative combine to accomplish challenges inherent in
each of the considerations discussed in the following paragraphs.
Speed
1-65. Speed is fundamental to all activities in an AO. Given the tendency for GE tasks to be resource-
intensive in time, materials, manpower, and equipment, speed is often most critical. Proper planning and
prioritization are essential to achieve the desired GE effect. Key practices that best support speed include—
Proper prior planning. Speed is a relative term if the planning before the operation did not set
the conditions for facilitating real speed in terms of mission accomplishment. Speed requires
effective, broad, inclusive, proactive, and synchronized planning across all staff sections and
engineer capabilities.
Existing facility use. Engineer units must rapidly provide facilities that enable forces to deliver
maximum combat power. The use of existing facilities greatly contributes to achieving speed by
eliminating unnecessary construction support. The use of existing ports, pipelines, warehouses,
airfields, and roads during operations is critical. Commanders and staffs must be capable of
planning and conducting real estate and real property acquisition to facilitate this effort. Often,
the joint force commander (JFC) must effectively negotiate with the host government for HN
support to use existing facilities. In mature theaters, such as the Republic of Korea, status of
forces agreements may dictate procedures for using existing facilities.
Standardization. Standard materials and plans save time and construction efforts and permit the
streamlining of production line methods, including the prefabrication of structural members.
Standardized assembly and erecting procedures increase work crew efficiency by reducing the
number of methods and techniques required. This supports simplicity. Standardization between
Service engineers is essential for success.
Simplification. The simplicity of design and construction reduces requirements when faced with
limited manpower resources, materials, and time allowances. When scarce resources are
available, simple methods and materials allow installation in a minimum amount of time. This
may also allow HN labor use to support construction.
Bare-bones construction. Military construction in an AO is characterized by using the
minimum necessities when possible. The theater commander must make the decision on
construction standards early in the planning process.
Phased construction. Phased construction allows for the rapid completion of critical
components of buildings or installations and uses these components for their intended purpose.
Engineers primarily use the Gantt chart as a tool to plan and track progress.
Economy
1-66. GE in an AO requires the efficient use of personnel, equipment, and materials. To most effectively
accomplish the tasks assigned to engineers, it is necessary for commanders to carefully consider
augmentation requirements. General engineer units are very capable of accomplishing their assigned tasks;
however, they are designed to accomplish specific types of tasks. Therefore, it is imperative that the proper
assets be allocated from the engineer force pool when task-organizing engineers. Proper proactive planning
is the first step in the application of economy. Other considerations include—
Conserving manpower. Construction tasks are time-consuming, and engineer commanders
must deal with engineer and construction worker shortages. Labor must be conserved, and every
engineer must function at the peak of efficiency for long hours to accomplish the GE mission.
Careful planning and coordination of personnel are necessary. Missions must be well organized
and supervised, and personnel must be carefully allocated for the task. Selected GE tasks can be
performed by combat engineers but require a conscious decision by the commander to trade off
one set of engineer capabilities to further GE tasks.
Conserving equipment. Military construction equipment might be in short supply, particularly
at the beginning of a contingency operation. The operational capability of equipment may be
impaired by shortages in repair parts and maintenance personnel. A possible solution is to
contract for local equipment and repair parts to alleviate shortages. The preventive maintenance
of equipment is essential to ensure the availability of long-term use. Commanders must ensure
that time is allocated for scheduled services to optimize equipment capabilities.
Conserving materials. The critical aspect of completing a GE task is often the availability of
appropriate materials. Although planners should maximize the use of local resources in their area
of responsibility, these resources may not be available or may be in short supply. Planners must
anticipate shipping materials from outside the AO, which may require longer transit times. The
conservation of materials while executing GE tasks is a critical consideration.
Evaluating environmental factors. Apply environmental considerations early in the process.
While some situations require putting aside risk associated with environmental considerations,
the earlier the risk is mitigated, the easier and less complex mitigation procedures will need to be
to be employed later. As the staff proponent for environmental issues, engineers must analyze
environmental considerations and recommend appropriate courses of action (COAs) to the
Flexibility
1-67. Rapidly changing situations during operations require that GE tasks in all stages be adaptable to new
conditions. Units must rapidly transition from all types of operations, and engineers must be agile in
applying the GE principle of flexibility to facilitate this transition. To meet this requirement, use standard
plans that allow for adjustment, expansion, and contraction whenever possible. For example, a standard
building plan may be easily adapted for use as an office, barracks, hospital ward, or dining facility. Forward
airfields should be designed and located so that they can later be expanded into more robust facilities that
are capable of handling larger aircraft and a larger maximum (aircraft) on ground (MOG) capacity.
Standardization enhances flexibility.
1-68. Flexibility facilitates versatility between Service engineers and within engineer organizations to
accomplish GE tasks. This includes providing selected technical expertise and equipment to a variety of
engineer organizations to perform GE missions that they are not specifically designed for or organized to
perform. Engineer units must display a multifunctional ability to perform engineer tasks outside their
mission-essential task list. An example is using combat engineers to perform selected GE tasks. However,
such a decision requires a risk analysis and higher echelon commander approval. This ensures that the
engineers are not removed from performing other, more critical missions in supporting movement and
maneuver for BCTs and other combat forces.
1-69. The basic deployability of engineer organizations and their designed modularity are enablers of
flexibility. Engineers must be ready to send only those assets specifically required to perform a mission.
They must establish functional, high-performing teams from a variety of U.S. Army engineer units while
maximizing capabilities from multi-Service engineer organizations. The integration of commercial engineer
equipment and the flexibility of engineer mission command or command and control must be able to
support the decentralization of authority.
Authority Decentralization
1-70. The wide dispersion of forces in the AO requires decentralizing engineer authority as much as
possible. The engineer commander or engineer staff officer in charge of operations at a particular location
must be granted authority that is consistent with responsibilities. As previously noted, this is particularly
essential on the noncontiguous battlefield.
1-71. The decentralization of authority requires effective mission command or command and control and
flexibility of its application to integrate the variety of engineer capabilities and accomplish selected GE
tasks or missions. Service engineers must strive for seamless integration between units and capabilities to
meet joint or component commander needs.
Priority Establishment
1-72. A lack of resources (planning and design capability and capacity, funding, equipment, personnel,
systems, logistics) severely impedes the commander from executing necessary GE tasks concurrently.
Therefore, careful prioritization must occur. It is essential to establish priorities to determine how much
general engineer effort must be devoted to a single task. While detailed priority systems are usually the
concern of lower echelon commands, all levels (beginning with the JFC and Army Service component
command [ASCC]) must issue directives that establish broad priority systems to serve as guides for
detailed systems. Resources are initially assigned only to the highest-priority tasks. Low-priority tasks are
left undone, while recognizing and assessing the risk of doing so. At the theater level, planners can assume
general priorities for initial phases of an operation and refine the priorities as the planning effort matures.
Project approval processes and acquisition review boards ensure an equitable distribution of resources
according to established priorities.
1-73. Engineer-prioritized project lists are developed by systems at each level, from brigade or regimental
combat team through theater. The priority system may include the procedures to process and review
requests, cost-benefit analyses, risk assessments, resource commitment approval steps, and prioritization
procedures.
2-7. General and combat engineers perform engineering tasks at different levels. For example, general
engineers typically perform mobility operations at the operational level, while combat engineers focus on
mobility at the tactical level. Likewise, ATP 3-37.34/MCWP 3-17.6 are supported by general engineers at
the operational level, while combat engineers support survivability at the tactical level.
2-8. The GE effort at theater and operational levels is coordinated and synchronized with tactical combat
operations. At the operational level, general engineer activities may not be conducted as part of a combined
arms mission, but they are fully coordinated with the maneuver commander responsible for the AO.
2-9. General engineer units may follow and support combat engineers as they transfer bridges, roads,
bypasses, or forward tactical airfields to allow forward movement with maneuver units. These tactical
efforts may then become operational efforts that have to be maintained or upgraded. For example, in some
situations, tactical trails may become roads and those roads may be upgraded to MSRs. To reduce the
construction effort, it is more likely that existing roads would be upgraded.
2-11. General engineer units support offensive, defensive, stability, and DSCA operations at theater and
operational levels. Combat engineer units may provide support at theater and operational levels if it is
available or if the condition requires close support to maneuver forces that are in close combat.
2-12. General engineers may also be involved in countermobility operations intended to achieve
operational or strategic effects. (See ADRP 3-90.) These engineering efforts focus on denying the
adversary the freedom of movement and maneuver by slowing or diverting the enemy to increase target
acquisition and increase weapons effectiveness.
2-13. Although primarily a combat engineer task, general engineers may be required to supplement combat
engineer efforts with the development of a system of barriers and obstacles with the integration of fires to
increase maximum effect. (See ADRP 3-90, ATP 3-90.8/MCWP 3-17.5, FM 3-34, JP 3-34, and TM 3-
34.85/MCRP 3-17A for additional information.)
Force Projection
2-14. General engineers may be required to support force projection efforts. (See ADRP 4-0.) Force
projection is the ability to project the military instrument of national power from the United States or
another theater, in response to requirements for military operations (JP 3-0).
2-15. Force projection includes GE tasks that enhance movement from the strategic to the operational level
and from peacetime locations to assembly areas or base camps. Tasks that support force projection may
simultaneously support logistics.
Access
2-16. General engineers contend with the following access types:
Informational access to USACE resources and higher-level engineering expertise to support
engagement strategies and wartime operations.
Physical access, such as forcible entry into a theater.
2-17. General engineers may be required to support efforts to gain access into a theater. Engineer efforts
ensure the mobility and flow of forces by establishing and securing an initial foothold, beachhead, or entry
point into the theater to enable follow-on forces to continue onward penetration to the objective. Like
forcible-entry operations, access efforts by friendly forces may be stopped and repelled by the adversary
use of counterattacks, coordinated and synchronized weaponry systems, and layered obstacle systems. (See
ATTP 3-90.4/MCWP 3-17.8, TM 3-34.85/MCRP 3-17A, FM 3-34, JP 3-18, and JP 3-34 for additional
information.)
2-18. The support to early-entry includes reconnaissance that mitigates antiaccess and area-denial
mechanisms to clear and open aerial ports of debarkation and seaports of debarkation. These tasks are often
considered combat engineering tasks, even though general engineer units can perform them when
conditions allow (See FM 3-34). Geospatial engineers can provide high-resolution mapping to clarify
situational understanding of early-entry and initial AOs at landing sites.
2-19. During access, combat engineers usually support forcible entry and the seizure and establishment of
lodgments. General engineers normally support the establishment and expansion of lodgments and bed-
down facilities.
2-20. GE tasks in support of access may be required to augment combat engineers to—
Clear beaches and remove antiaccess systems (such as barriers and obstacles) from roads,
airfields, and ports.
Construct initial combat trails and roads, gap crossings, LOCs, MSRs, mobility bridges,
airfields, base camps, and ammunition and supply depots.
Support countermobility and survivability efforts earlier in the insertion to repel enemy
counterattacks to recover lost land.
Assured Mobility
2-21. Assured mobility is a framework—of processes, actions, and capabilities—that assures the ability of
a force to deploy, move, and maneuver where and when desired, without interruption or delay, to achieve
the mission (ATTP 3-90.4/MCWP 3-17.8). Assured mobility is applied at strategic, operational, and
tactical levels of war to facilitate the commander’s freedom to move and maneuver. Combat engineering
assures tactical mobility, while GE assures operational mobility and supports strategic mobility. The GE
effort is directed at providing the assured mobility of forces, from ports of debarkation to forward AOs.
2-22. The fundamentals of assured mobility and the specific linkages to GE are as follows:
Predict. Engineers and other planners must accurately predict potential enemy impediments to
joint force mobility by analyzing enemy tactics, techniques, procedures, capabilities, and
evolutions. Prediction requires an updated understanding and awareness of the operational
environment. When applying GE, planners must predict the impact of enemy and military
operations on the infrastructure required to maintain mobility and momentum. For example, they
must predict the damage to a MSR caused by the movement of a large mechanized force over a
single route.
Detect. Using information collection assets, engineers and other planners identify early
indicators for the location of natural and man-made obstacles, make preparations to create or
emplace obstacles, and determine potential means for obstacle creation. They also identify actual
and potential obstacles and propose solutions and alternate COAs to minimize or eliminate
potential effects. For the GE function, planners must be aware of the effects to strategic,
operational, and tactical mobility impacted by engineering solutions.
Prevent. Engineers and other planners apply this fundamental by denying the enemy the ability
to influence mobility. This is accomplished by forces acting proactively before obstacles are
emplaced or activated, including executing aggressive action to destroy enemy assets and
capabilities before they can be used to create obstacles. Political considerations and the rules of
engagement may hinder the ability to apply this fundamental early in a contingency.
Commanders apply necessary GE assets in a timely manner to prevent mobility impediments to
the force. An example of a GE task to support this fundamental is constructing a bridge bypass
before a bridge becomes unusable.
Avoid. If prevention fails, the commander maneuvers forces to avoid impediments to mobility if
it is viable within the scheme of maneuver. GE is an integral part of the maneuver force ability
to avoid such impediments. Examples of GE tasks that support this fundamental are building
roads around natural or man-made obstacles, constructing alternate airfields, and implementing
other actions that allow maneuver elements to operate effectively.
Neutralize. Engineers and other planners plan to neutralize, reduce, or overcome obstacles and
impediments as soon as possible to allow the unrestricted movement of forces. The breaching
tenants and fundamentals apply to the fundamental of neutralize. An example of a GE task to
support this fundamental is building a tactical or LOC bridge that neutralizes a river obstacle.
Protect. Engineers and other elements plan and implement survivability and other protection
measures that deny the enemy the ability to inflict damage as joint forces maneuver. This
includes executing countermobility missions to deny the enemy the ability to maneuver and
providing protection to friendly maneuvering forces. Commanders can ensure that GE efforts
focus on survivability support (berms, bunkers, hardened facilities), which is primarily centered
on the hardening aspect of survivability as described in ATP 3-37.34/MCWP 3-17.6.
2-23. The assured mobility construct enables a joint force to achieve the commander’s intent. Assured
mobility emphasizes proactive mobility and countermobility, supports survivability, and integrates engineer
functions to accomplish this. Assured mobility is broader than mobility and should not be confused with the
limited application of mobility operations as described in ATTP 3-90.4/MCWP 3-17.8. Assured mobility
focuses on supporting the maneuver commander’s ability to gain a position of advantage in relation to the
enemy. This can be accomplished by conducting mobility operations to negate the impact of enemy
obstacles, conducting countermobility operations to impact and shape enemy maneuver, or conducting a
combination of mobility and countermobility operations.
2-24. Assured mobility is an integrating process related to each U.S. Army warfighting function and is
similar to targeting, risk management, and intelligence preparation of the battlefield. As an integrating
process, assured mobility provides linkage between the tasks associated with mobility, countermobility, and
survivability and their roles across the six warfighting functions. Assured mobility applies in all operations
and across the range of military operations. While it is an enabler of warfighting functions and other
integrating processes, assured mobility is also enabled by other integrating processes. The purpose of
assured mobility is to ensure the freedom of maneuver, preserve combat power throughout the AO, and
exploit superior situational understanding.
Infrastructure Development
2-25. General engineers may be required to support infrastructure development in support of force
projection, theater opening, and sustainment. (See ADRP 4-0.) Theater opening is the ability to establish
and operate ports of debarkation (air, sea, and rail) to establish a distribution system and
sustainment/combat service support bases. It also facilitates port throughput for the reception staging,
onward movement, and integration of forces within the theater of operations (TO). (See ADRP 4-0.)
Engineer efforts are focused on ensuring that the structural framework is in place to support a network of
bases, a logistics network, a transportation network, and interconnecting service facilities to sustain forces.
2-26. GE tasks in support of infrastructure development may include—
Establishing and maintaining the infrastructure necessary for supporting early-entry and follow-
on forces in support of force projection and for sustaining military operations.
Conducting master planning and design, construction, and real estate actions.
Coordinating for environmental and geospatial support, O&M, and assessment.
Continuing to improve, upgrade, and expand infrastructure as the TO matures and requirements
increase.
Constructing seaports, airfields, bases, and mass logistics storage facilities.
Developing water, power, and waste systems. (See ADRP 4-0 and JP 3-34.)
Protection
2-27. U.S. Army and U.S. Marine Corps forces face hybrid threats, which are described as the diverse and
dynamic combination of regular forces, irregular forces, terrorist forces, and/or criminal elements unified to
achieve mutually benefitting effects (ADRP 3-0). These forces and elements can employ hostile actions to
inflict serious damage on personnel, physical assets, or information. Such hostile actions pose threats to
survivability requiring adequate protection of personnel and physical assets.
2-28. Survivability has two aspects: avoiding and withstanding. Avoiding can include concealment,
camouflage, and disbursement. Withstanding can include construction or the hardening of protective
positions. There are a variety of protective measures that can be employed. These measures are discussed in
the following paragraphs.
2-29. Hostile actions usually involve the employment of weapons. ATP 3-37.34/MCWP 3-17.6 addresses
various types of weapons effects and the design considerations to mitigate them.
2-30. Adversaries use sensors to increase the effectiveness of weapons. Sensor systems are categorized
based on the component of the electromagnetic spectrum in which they operate. ATP 3-37.34/MCWP 3-
17.6 addresses sensor systems and the principles and techniques for using camouflage and concealment to
defeat them.
2-31. Concealment protective measures include the use of weather effects, battlefield dust, debris, smoke
munitions, or other potential obscurants to hamper observation and target acquisition capability or to
conceal activities or movement. Battlefield obscuration is typically provided by specialized chemical,
biological, radiological, and nuclear (CBRN) elements or fires, which can conceal friendly positions and
screen maneuvering forces from enemy observation. (See ATP 3-11.50 for additional information on the
employment of obscurants. See ATP 3-37.34/MCWP 3-17.6 for more information on camouflage,
concealment, and decoys.)
2-32. Hazards associated with the surrounding environment also pose threats. Weather conditions, natural
disasters, diseases, and terrain-related hazards are common examples. (Environmental hazards are
addressed in FM 3-34.5/MCRP 4-11B)
2-33. Although it is often considered to be a part of countermobility operations, another protective measure
is the use of obstacles, which is a key enabler to ATP 3-37.34/MCWP 3-17.6. Obstacles provide friendly
forces with close-in protection, which enhances the effectiveness of survivability positions. (See ATP 3-
90.8/MCWP 3-17.5, for additional information on protective obstacles.)
2-34. Military forces are composed of personnel and physical assets, each having their own inherent
survivability qualities or capabilities that can be enhanced through various means and methods. Although
units conduct ATP 3-37.34/MCWP 3-17.6 within the limits of their capabilities, the U.S. Army and U.S.
Marine Corps have a broad range of diverse engineer capabilities that can enhance unit survivability, which
is discussed in this chapter.
2-35. GE may be required to support the preservation of the force so that the commander can apply
maximum combat power. (See ADRP 3-37.) Engineers possess unique equipment and personnel
capabilities that can be used directly to support survivability and related protection efforts. General
engineer support to protection and survivability continues as improvements are continuously reassessed and
additional assets are made available. (See ADRP 3-37, TM 3-34.85/MCRP 3-17A, FM 3-34, FM 5-415,
ATP 3-90.8/MCWP 3-17.5, JP 3-15, JP 3-34, and ATP 3-37.34/MCWP 3-17.6.)
2-36. At the operational level, general engineer support will be continuously conducted to harden and
prepare positions for facilities and installations. Engineers possess unique equipment and personnel
capabilities that can be used directly to support survivability and related protection efforts.
2-37. GE tasks in support of protection may include—
Logistics
2-39. GE may be required to support logistics. (See ADRP 4-0.) Engineer efforts help ensure the
continuous and uninterrupted flow of material, equipment, and supplies to the force. Engineers can
combine all three disciplines (combat, general, and geospatial engineering) to establish and maintain the
infrastructure necessary for sustaining logistics operations in the AO.
2-40. GE tasks in support of logistics may include—
Building, repairing, and maintaining roads, bridges, airfields, ammunition supply points,
warehouses, supply points, maintenance facilities, waste management facilities, and open
structures for aerial ports of debarkation, seaports of debarkation, MSRs, and base camps.
Expanding the infrastructure base to accommodate increased logistics demands. Such tasks can
include constructing larger storage facilities, enlarging seaports and airfields, and upgrading the
transportation network (such as strengthening and widening roads and improving bridges) to
accommodate increased volume and logistics traffic flow.
Planning, acquiring, managing, and remediating real estate.
Providing power system support, waste management support, environmental support, and
firefighting support.
Supporting joint logistics over-the-shore (JLOTS), force projection, or access. (See FM 3-34 and
JP 3-34.)
TACTICAL LEVEL
2-41. GE supports unified land operations. GE does not normally provide close support to maneuver forces
that are in close combat and provides less direct support to offensive and defensive operations. General
engineer support tasks to the offense and defense are mostly at the operational level, but they can
accomplish tactical-level tasks that exceed the combat engineer force capability. GE may provide more
support to defense in the support area and provide significant support to stability and DSCA. GE also
supports protection and logistics at the tactical level. (See ADRP 3-0, ADRP 3-07, ADRP 3-90, FM 3-34,
and JP 3-34 for additional information.)
OFFENSIVE
2-42. The main offensive focus is using engineer support for movement and maneuver. GE support is
primarily focused on the tasks that support mobility. The general engineer function reinforces combat
engineering, enables logistics, and develops infrastructure. Enabling sustainment/combat service support
includes the creation and sustainment of LOCs and bed-down facilities. GE assets may be task-organized to
augment combat engineer units.
2-43. General engineer tasks that support the offense include—
Supporting theater access (seaports, airfields, bed-down facilities).
Supporting mobility.
Constructing and repairing bridges.
Constructing and repairing roads, airfields, and heliports that support the mobility of the
maneuver force.
Conducting earthmoving operations.
DEFENSIVE
2-45. The primary defensive focus is using engineer support for movement, maneuver, and protection. GE
support to defense is primarily focused on tasks that assure mobility and enhance protection. The GE
function reinforces combat engineering and enables protection. Countermobility operations are dominant,
but some support to mobility operations may be provided to ensure the ability of forces to freely move and
maneuver. The engineer primary protection task is support to survivability. (Countermobility and combined
arms obstacle integration are discussed in detail in ATP 3-90.8/MCWP 3-17.5, and JP 3-15. Protection is
discussed in ADRP 3-37. Survivability is discussed in ATP 3-37.34/MCWP 3-17.6.)
2-46. General engineer tasks that support the defense include—
Constructing entry control points.
Erecting barriers to deny access to fixed sites.
Providing area damage control and assessments.
Supporting survivability.
Hardening facilities.
Constructing sustainment sites.
Constructing decontamination sites.
2-47. GE units may conduct combat engineering tasks to support the defense if tactical conditions do not
exceed their capability to protect themselves and defend against expected threats. (See ADRP 3-90 and FM
3-90-1.)
2-48. Engineers must carefully analyze the threat to adequately predict and carefully plan the GE
requirements for an operational mission. Changes in the threat status may affect how units designed to
perform GE missions are equipped and trained.
2-49. General engineer planners should use their knowledge of the conditions in a specific AO to predict
and estimate the level of GE effort by examining the state of the infrastructure (ports, roads, bridges,
airfields, utilities). An examination of the physical environment (including environmental considerations
affecting the mission) will assist in determining the scope, level, and type of GE requirements.
STABILITY
2-50. General engineers may be required to support stability operations. (See ADRP 3-07, JP 3-07, and
MCIP 3-33.02/NWP 3-07/COMDTINST M3120.11.) Stability tasks are conducted as part of operations
outside the continental United States (OCONUS) in coordination with other instruments of national power
to maintain or reestablish a safe and secure environment and to provide essential government services,
emergency infrastructure reconstruction, and humanitarian relief.
2-51. The primary stability focus is using engineer support to stabilize a region by improving the
infrastructure and integrating with and supporting other forces in their missions. Maritime force engineers
(Marines and Seabees) are capable of performing emergency repair of maritime infrastructure under
varying conditions of instability. These engineers may embark in amphibious ships or be airlifted to
locations. (See MCIP 3-33.02/NWP 3-07/COMDTINST M3120.11.) Most overall engineer effort during a
stability operation is likely to be through the GE function.
2-52. GE may support all primary stability tasks. No GE task only supports stability. The purpose, desired
effect, and conditions for the task may differ in stability, which may affect how the task is accomplished.
For example, a task to support stability may be accomplished with the involvement of more HN
participation.
2-53. In addition to their normal support of U.S. forces, GE tasks primarily focus on the reconstruction or
establishment of services that support the population in conjunction with civilian agencies. Engineers
conducting missions provide resources to assist in disaster or theater response in areas outside U.S.
territory. Rapid and effectively emplaced sustainment/combat service support operations can reduce human
injuries and fatalities and harden infrastructure.
2-54. General engineer support for the restoration of essential services and infrastructure development is
the primary engineer focus in stability operations. Essential services for engineer considerations include
food and water, emergency shelter, and basic sanitation (sewage and waste disposal). GE may support the
mobility of the population.
2-55. General engineer support may be necessary for the sustainment/combat service support and
protection requirements of the force or for others conducting stability operations. Stability operations tend
to have a longer duration than offensive and defensive operations. (See ADRP 3-07 and FM 3-07 for
additional information on stability.) As such, the GE level of effort is very high at the onset and gradually
decreases as the TO matures. As the AO matures, the GE effort may transfer to civilian contractors, such as
to those who operate under the logistics civil augmentation program. Given the nature of stability, the risks
associated with environmental hazards may have greater importance and impact in stability than in
offensive or defensive operations.
2-56. GE support to stability is primarily focused on tasks to build partner capacity; build infrastructure;
and assure mobility, sustainment/combat service support, and protection. Countermobility operations are
dominant, but some support to mobility operations may be provided to ensure the ability of forces to freely
move and maneuver.
2-57. General engineer tasks that support stability may include—
Conducting infrastructure reconnaissance (survey and assessment).
Providing infrastructure development (reconstructing or establishing infrastructure to provide
essential services that support the population, developing HN capability and capacity, providing
water resources).
Constructing base camps and force bed-down facilities.
Constructing survivability and other force protection support.
Constructing support area facilities.
Providing infrastructure support, including utilities and other essential services.
Providing reliable electrical power.
Providing LOC construction, maintenance, and repair.
2-58. GE may include conducting countermobility tasks to control traffic or the population. Entry control
facilities may be required at base camps or support facilities.
2-59. Stability operations may include humanitarian and civic assistance. U.S. Army and Marine forces act
as part of a joint force with the U.S. country team and the U.S. Agency for International Development.
2-60. General engineers may be required to provide support to special forces operations. (See FM 3-34,
JP 3-0, and JP 3-34.) Such tasks could be diverse and range from small- to large-scale operations. They
could also include training others in demining techniques, providing technical capabilities to restore
essential services, and providing infrastructure reconstruction and humanitarian relief to demonstrate U.S.
commitment.
HOMELAND DEFENSE
2-61. The military will continue to play a vital role in securing the homeland through the execution of
homeland defense. General engineers must be prepared to provide the required effort and resources when
necessary.
2-62. Homeland defense is the protection of United States sovereignty, territory, domestic population, and
critical infrastructure against external threats and aggression or other threats as directed by the President
(JP 3-27). DOD is the lead for these missions.
2-63. The strategy for homeland defense necessitates securing the United States from attack through an
active, layered defense. DOD engineering capabilities, coupled with the commercial sector or with
contractor capabilities, can provide extensive, in-depth engineering for homeland defense. (See JP 3-27.)
Massive national general engineer support may be garnered from local, state, and federal resources via a
multitude of avenues or agreements.
2-64. General engineers may be required to augment national efforts in homeland defense. Engineer
support could be directed toward offensive and defensive operations if supporting homeland defense. (See
JP 3-27 for additional information on homeland security. See JP 3-26 for more information on the
overarching homeland security framework.)
2-65. Homeland defense and DSCA are separate mission sets with different leads. (See JP 3-28 for a
review of the relationship between homeland defense, homeland security, and DSCA.)
2-70. GE support to DSCA is primarily focused on tasks that enable sustainment/combat service support
and enhance protection. GE tasks to DCSA include—
Focusing on first responder and population mobility.
Reinforcing civil authorities.
Supporting military forces by enabling logistics, repairing infrastructures, and restoring critical
services.
Repairing or restoring selected civil and commercial infrastructure that provides water, power,
communication, transportation, and other essential utilities that military forces and DOD support
organizations depend on to meet operational needs.
2-71. There are few unique GE tasks performed in DSCA that are not performed during other operations.
The difference is the context in which they are performed. (See ADRP 3-28.) Because of the unique nature
of the hazard or threat, planning for DSCA is significantly different than planning for offense, defense, or
stability tasks, although the basic missions may be similar to those of stability tasks. For example, the
hazard or threat will most likely be a natural or man-made disaster with unpredictable consequences. The
military will assume a support role to DSCA operations.
Notes.
1. See ATTP 3-34.23 for a discussion of engineer capabilities that could be applied to support
DSCA requirements.
2. See ATP 3-28.1/MCWP 3-36.2/NTTP 3-57.2/AFTTP 3-2.67 for more information on specific
DSCA tasks and planning considerations.
3. See ATP 3-37.34/MCWP 3-17.6 for information on considerations for stability or DSCA
tasks.
2-72. General engineer support for the restoration of essential services after an incident is the primary
engineer focus in DSCA. Engineer support may also be required for forces providing DSCA command to
government agencies at all levels until they can function normally.
2-73. There are 15 national emergency support functions used by the federal government and states as the
primary means to organize and provide assistance. General engineers may be tasked to support some of
them. Each emergency support function is identified and discussed in detail in ADP 3-28, ADRP 3-28,
JP 3-28, and ATP 3-28.1/MCWP 3-36.2/NTTP 3-57.2/AFTTP 3-2.67.
2-74. For engineers, the most applicable function is the Emergency Support Function #3–Public Works and
Engineering Annex. USACE is the primary coordinating agency for this emergency support function that is
responsible for providing technical advice and evaluations, engineering systems, construction management
and inspection procedures, emergency contracting procedures, emergency wastewater and solid waste
facility repair, debris handling and removal, and roadway maintenance and openings following presidential
disaster declarations. (See ADP 3-28.)
2-75. The overall scope of Emergency Support Function #3–Public Works and Engineering Annex includes
infrastructure protection and emergency repair, infrastructure restoration, engineering service and
construction management, and emergency contracting support for lifesaving and life-sustaining services.
Some examples of GE support to providing or restoring essential services may include—
Supporting urban search and rescue.
Providing food and water.
Conducting emergency shelter and base camp construction.
Providing emergency transportation.
Providing boats during flooding.
Providing trucks for hauling critical supplies and equipment.
Providing hauling assets for population movement.
Providing public works and other engineering support.
Providing firefighting support.
Providing deployable prime power systems.
2-77. GE support may be required for force sustainment/combat service support and protection
requirements and may be extended to support other agencies during DSCA. Likely missions include—
Debris removal.
Route clearing operations.
Expedient (temporary) road and trail construction and repair.
Forward aviation combat engineering (including the repair of paved, asphalt, and concrete
runways and airfields).
Device installation that prevents foreign object damage to rotary-wing aircraft.
Temporary bridging construction.
Port, airfield, reception, staging, forward movement, and integration facility upgrades and
construction.
3-5. GE planning and design (along with preparation, execution, and assessment) are often collaborative
efforts between higher headquarters, constructing units, facility commanders, and users or tenants. (See
JP 1 and JP 3-0 for a discussion of the joint operations planning process. See JP 3-34 for engineer
contributions in operation plans [OPLANs] and operation orders [OPORDs].)
3-6. Careful consideration during planning and execution must be made for command relationships to
effectively achieve seamless integration of GE support throughout the TO or JOA. The overarching
doctrine for command is contained in capstone doctrine such as ADRP 3-0, ADRP 5-0, ADRP 6-0,
FM 3-34, JP 3-0, and JP 3-34 and in U.S. Army engineer implementing manuals such as ATTP 3-34.23.
3-7. GE involves the application of technical knowledge and judgment to make trade-offs among
competing requirements and to recommend solutions to difficult problems. Construction OCONUS may
also be governed by DOD guidance, status of forces agreements, HN-funded construction agreements and,
in some instances, bilateral infrastructure agreements. Planners and designers must ensure compliance with
the more stringent standards as applicable.
3-9. General engineers assigned as joint engineer staff officers must be well trained to effectively plan
and synchronize joint GE operations as members of a JFC staff. Action officers must be well versed in the
complex mission command or command and control of the joint force and be knowledgeable in the
capabilities of all Service engineer forces to maximize the use of their capabilities.
3-10. U.S. Army and U.S. Marine Corps engineers must recognize that other Service engineer forces
organize and equip their engineer forces for different functions and adapt their capabilities to meet specific
needs. This is particularly critical for GE, where each Service has capabilities and limitations that must be
properly understood to effectively employ them. JP 3-34 provides the necessary baseline planning
information for all Service engineer capabilities.
Planning
3-28. Planning follows these general steps:
Determine operational requirements.
Conduct site selection and reconnaissance.
Conduct initial engineering reconnaissance.
Analyze existing infrastructure.
Develop repair, upgrade, or modification plans.
Determine new construction requirements.
Determine O&M requirements.
Coordinate planning with concept or initial designs.
3-29. MDMP helps engineers apply thoroughness, clarity, sound judgment, logic, and professional
knowledge to understand situations, develop options to solve problems, and reach decisions. It helps
facilitate collaboration and parallel planning and seeks the optimal solution. The MDMP process outlined
in ADRP 5-0 is used for GE. There are particular considerations and tools for planning GE missions that
must be understood and integrated into the process to make them an effective portion of the planning
process.
3-30. Planning and design are continuous interactive and iterative processes throughout the military
operation and the life cycle of the facility or infrastructure. Planning and design can be conceptual or
detailed and highly structured or less structured. Plans and designs may be initial or final-approved and are
often documented in master plans.
3-31. Planning affects design, and design affects planning. Each may provide information to, and constrain
or restrict, the options of the other. Planning and design are interdependent efforts that are combined to help
facilitate a desired outcome. Effective design hinges on the accuracy and completion of the information
generated during planning, particularly information related to facility and infrastructure requirements,
available resources, construction means, and site location. Automated planning and design tools are
available to assist general engineers in expediting the process.
3-32. Critical information resulting from design that is integrated into planning includes construction
estimates (bill of materials, equipment, personnel, cost, and time) that the commander needs to know in
establishing priorities of support, priorities of effort, timelines associated with movement, the basing of
forces, and the flow of the operation.
3-33. Failure to remain continuously linked and updated with mission planning as it progresses can result
in design solutions that are unsustainable based on the concept of operations and are inadequate in meeting
the commander’s needs. Planners and design engineers develop an integrated collection plan for engineer
reconnaissance to support planning and design.
3-34. Planners may use basic periods of time (such as the two-shift, 20-hour working day) or the days in a
month to prepare estimated labor needs extending over a period of time. However, adverse physical
conditions peculiar to the location must be considered. For example, severe icing conditions during the
winter months, periods of extreme tide range, or severe seasonal winds may have a direct bearing on
construction or rehabilitation work. When heavy seasonal rains, snowfall, icing, seasonal winds of unusual
severity, frequent or seasonal fogs, or exceptionally high or low temperatures are typical to a coastal area,
work time estimates should be modified accordingly to allow for such conditions. When operating in other
countries, planners need to consider holidays and their impact on local contractor work schedules. For
example, Muslims observe Ramadan as a month of fasting and do not go to work for a few weeks.
Design
3-35. The design of structures in TO construction is specified in the authorizing or construction directive.
Normally, engineers build one of two structures in the TO—initial or temporary. Initial design life is up to
6 months; temporary design life is up to 2 years. The use and actual life of the structure may exceed the
design life.
3-36. When possible, standard designs are used to save time in design, construction, and maintenance.
Using standard designs and their accompanying bill of materials allows for the advance procurement of
construction materials and equipment. The engineer must fit these designs to the site and adapt them to the
existing conditions. Reconnaissance, construction surveys, soil bearing tests, test piles, and, perhaps, a
sieve analysis of local sands and gravels are thus prerequisites to the preparation of final design drawings
and bill of materials.
3-37. The design of nonstandard structures is usually carried out only if standard designs cannot be adapted
or modified accordingly.
Constraints
3-43. A constraint dictates an action or inaction, thus restricting how something can be done. Planning and
design are constrained by—
Base camp standards (facility allowances and construction standards).
Construction resources availability (labor, equipment, materials, money).
Terrain and climate conditions.
Weather effects.
Available and usable vacant land areas.
Funding limits.
Force protection requirements.
HN agreements.
Environmental considerations and impacts.
Operational timelines.
Civil considerations and impacts.
Locally available commercial power characteristics.
Standards
3-44. General engineer planners and designers consider all standards established by the CCDRs or higher
level headquarters for their area of responsibility. Some CDDRs publish guidebooks with rules of
allocation and planning or construction standards. CCDRs often establish standards in orders that may take
precedent over guidebooks.
3-45. Standards may be established in a number of areas that affect GE, to include design, construction,
materials, O&M, quality of life, and environmental considerations. Some are in Unified Facilities Criteria,
technical manuals, or other publications or are provided by commanders. Standards help provide effective,
efficient, and sustainable solutions. These are not to be confused with task standards that are used to assess
individual or unit performance.
3-46. Standards can be viewed as a continuum with a wide range of professionally recognized
specifications and expectations, from minimum to highly restrictive. Standards can have steps with
different names and various levels of complexity and technical details. For example, airfield standards are
initial or temporary contingency operations standards. The general engineer must be aware of these
standards, whether they are Service-oriented, state, national, or international in nature.
3-47. The CCDR specifies the facility allowances and construction standards for the theater to minimize
the engineer effort expended on any given facility while assuring that the facilities are adequate for health,
safety, and mission accomplishment. Typically, the CCDR will develop the base camp construction
standards for use within the theater utilizing the guidelines provided in JP 3-34. There can be construction
quality standards and material property standards that must be checked using quality assurance and quality
control activities. (See EP 415-1-261 series for information on quality assurance representative activities.
See NTRP
4-04.2.5/TM 3-34.42/AFPAM 32-1020/MCRP 3-17.7F for information on project quality control plans.)
3-48. The engineer must recommend the most feasible solutions to meet each requirement based on
construction guidelines and other planning factors. Standards documents that provide specific construction
examples are in ATP 3-37.10/MCRP 3-17.7N. The commander may also establish standards in specific
OPLANs, OPORDs, and directives. These standards are used as initial guides, provide planning tools, and
may also provide priorities for construction within base camps.
Engineer Reconnaissance
3-52. Engineer reconnaissance enables GE planning and design by providing the information needed to
perform planning and design. Availability and assessment information requirements include infrastructure
(en route to and within the operational area), materials, LOC supportability, local labor, and contractor
capabilities. (See FM 3-34.170/MCWP 3-17.4 for more information.)
Site Reconnaissance
3-53. Each potential site should be reconnoitered to select the most economical use of available resources.
General locations and potential sites are determined by tactical requirements and initially analyzed by
preliminary studies (intelligence or technical), reports, and interviews with locals and remote
reconnaissance, such as a review of maps, aerial reconnaissance, aerial or space images, and databases. An
initial on-site reconnaissance may be made by the planning headquarters and later confirmed and expanded
by the constructing unit.
Site Selection
3-54. The exact site selection is normally made by the constructing unit after conducting a ground
reconnaissance that considers the selection factors for the specific project, such as access routes,
trafficability, soil characteristics, location, quality and quantity of materials, wind patterns, drainage,
bivouac sites, and security. Other factors, such as real estate acquisition and EBS, should be considered as
well.
Site Layout
3-55. The site layout considers the access, environmental conditions, clearance, drainage, visitor center,
parking area, break area, equipment staging area, equipment park, bivouac sites, borrow sites, quarries,
aggregate supplies, haul routes, material storage areas, facility locations, utilities, and security. A simple
site layout sketch for some projects may evolve to detailed plans in master planning documents. Site
preparation requirements are discussed in TM 5-301 series.
Economic Analysis
3-56. GE analyzes the projected life cycle cost and potential mission impact of GE solutions and makes
recommendations to the commander based on this analysis. The economic analysis looks at all resources to
include labor, materials, equipment, and funds. Economic analysis may affect the planning, design,
construction, O&M methods, materials, and procedures.
3-57. A detailed cost estimate is developed to allow a cost comparison of concept designs or to help
analyze the engineering trade-offs made to complete the detailed plans and designs. Economic analysis may
need to be made at specific intervals over the life of a program or project as new information that changes
initial conditions becomes available. For example, the use and upgrade of existing facilities can save
resources, but the risk may be significant due to the impacts of unknown or unforeseen conditions.
Priorities
3-58. GE priorities and resource allocation conflicts may be resolved by boards with the final resolution
subject to the approval of the commander. GE priorities are identified and set at all levels. The priorities
guide the application of scarce or limited resources. Priorities may be adjusted many times as operations
progress.
Master Planning
3-59. Master planning is an integrated strategy for the long-range approval, design, construction, and
maintenance of required facilities and infrastructure throughout their life cycle that integrates
improvements for protection, quality of life for residents, and efficiencies and effectiveness at their best
possible cost. Proper master planning enables scalable and sustainable facilities, conserves resources, and
prevents wasted construction. Early master planning facilitates the transition to improved facilities of the
right size, with the right capabilities, and at the right locations as the operation develops. At lower levels,
the master planning is linked to the scheme of base camps and is the responsibility of the commander. A
good master plan will also incorporate an EBS. EBSs are an important part of the initial survey,
development, and master planning for base camps.
3-60. Key features of master planning include—
Producing a documented initial plan and plans for changes of operational requirements, capacity
requirements, the purpose, construction standards, protection requirements, quality of life
standards, resources, contracted support, efficiencies, and effectiveness.
Seeking to attain cost-effective, scalable, and sustainable solutions.
Serving as the long-term blueprint for the implementation of future improvements or changes to
the service life of the base camp.
Starting early to help facilitate the transition to more permanent facilities on the base camp as an
operation develops. (See JP 3-34.)
Note. See TM 5-803-1 and TM 5-803-5/NAVFAC P-960/AFM 88-43 for more information on
installation master planning.
ENGINEER RECONNAISSANCE
3-74. Reconnaissance is a mission undertaken to obtain, by visual observation or other detection methods,
information about the activities and resources of an enemy or adversary, or to secure data concerning the
meteorological, hydrographic, or geographic characteristics of a particular area (JP 2-0).
3-75. Route classification is a classification assigned to a route using factors of minimum width, worst
route type, least bridge, raft, or culvert military load classification, and obstructions to traffic flow
(JP 3-34). Route classification results from collecting detailed technical information on various components
of a designated route, such as the road network, the bridges along a selected route, any underpasses and/or
overpasses, and so forth. Route classification provides a graphical display of the load-carrying capacity and
the rate-of-travel capacity of the selected route. (See FM 3-34.170/MCWP 3-17.4 and MCWP 3-17 for
additional information.)
3-76. The five forms of reconnaissance are zone, area, route, force, and special. See ADRP 3-90 for
additional information on the forms of reconnaissance.
3-77. Site reconnaissance includes obtaining information to plan security, site layout, and site drainage.
Survey and soils experts should participate in the site reconnaissance. Reconnaissance to support the
construction of a new road may be classified as area or route reconnaissance. (See FM 3-34.170/MCWP 3-
17.4 and FM 3-90-1.)
3-78. When available, an automated route reconnaissance kit can provide engineer units with an automated
reconnaissance package that allows the reconnaissance element to collect and process reconnaissance
information. An overlay is made with attachments that describe all pertinent terrain features in detail. This
overlay forms part of the mobility input to the common operational picture and is maintained by the
engineer unit tasked to perform the reconnaissance. (See FM 3-34.170/MCWP 3-17.4 and MCWP 3-17 for
more information on route reconnaissance.)
3-79. An air or map reconnaissance includes a general study of the topography, drainage pattern, and
vegetation. Construction problems, camouflage possibilities, and access routes should be identified. A route
reconnaissance plan is developed by selecting the areas to investigate and the questions to be answered
from the information available or, if time is available, to request and support the reconnaissance. Air and/or
map reconnaissance can be used to eliminate unsuitable sites, but cannot be relied on for site selection.
Digital imagery greatly enhances the usefulness of this method of reconnaissance.
3-80. While air and map reconnaissance can effectively minimize needed ground reconnaissance, it cannot
replace ground reconnaissance. It is on the ground that most questions must be answered or that most
observations tentatively made from available information are verified.
3-81. There are two types of engineer technical reconnaissance discussed in FM 3-34.170/MCWP 3-17.4
that may be performed as part of a reconnaissance or as a special task (route classification or an
assessment) or as a survey. Engineer assessments and surveys are typically conducted at the operational
level and in support of the GE function. Assessments and surveys include—
Bridge reconnaissance.
Gap crossings and choke points.
Engineer resource assessments.
Infrastructure reconnaissance.
Environmental reconnaissance.
Airfield assessments.
3-82. Engineer reconnaissance includes two levels of detail: assessment and survey. The comparison and
contrast is as follows:
Assessment. An assessment, in the context of engineer reconnaissance, is a judgment about
something based on a technical understanding of the situation. Within the range of technical
reconnaissance, an assessment takes less time and technical expertise to perform than a survey
but yields less technical detail than a survey. Reconnaissance elements do not require specialized
technical expertise to perform an assessment. They conduct assessments following the same
basic formats that a survey would use.
Survey. A survey, in the context of engineering reconnaissance, looks at or considers something
closely, especially to form a technical opinion. Within the range of technical reconnaissance, a
survey requires more time and technical expertise than an assessment to perform, but it
subsequently produces more technical detail. Specific technical expertise is required to conduct a
survey. The survey team is normally augmented by forward USACE personnel assigned to a
forward engineer support team, other technical specialties (such as medical, civil affairs, other
government agencies, contractors, and HN), and reachback as needed to enhance the survey
quality.
3-83. General engineers working at the operational level will conduct reconnaissance primarily to identify
requirements for operational level sustainment/combat service support. Technical reconnaissance
capabilities are typically conducted by a general engineer assessment team or survey team to gather the
technical information required for—
Maintenance and upgrades of ground LOCs.
Bridge construction and repair.
GE support of airfields and heliports.
GE support of seaports.
GE support of protection procedures.
Real estate and real property maintenance activities.
Procurement and production of construction materials.
GE support of bed-down facilities, base camps, and support areas.
Power systems.
Support to petroleum pipelines and storage facilities.
Water supplies and well drillings.
Underwater and other specialized construction support requirements.
Infrastructure surveys.
Environmental baseline assessments.
Environmental remediation surveys and assessments.
ROUTE CLASSIFICATION
3-84. The route classification is assigned to a route using factors of minimum width and worst route type;
least bridge, raft, or culvert military load classification; and obstructions to traffic flow. The military load
classification is a standard system in which a route, bridge, or raft is assigned class number(s) representing
the load it can carry. Vehicles are also assigned number(s) indicating the minimum class of route, bridge, or
raft they are authorized to use. (See FM 3-34.170/MCWP 3-17.4 for more information on route
classification.)
3-85. Route reconnaissance is normally a combat engineer task. Route classification is normally a GE task.
However, there is no clear dividing line from the technical effort required for the combat engineering task
of classifying a route for combat vehicle traffic to the GE task of conducting a road reconnaissance to
estimate the effort required for the design of an upgrade of a MSR.
3-86. The combat engineering task will effectively address classification of the route, but will also provide
information useful in the general engineer estimate. Similarly, the general engineer estimate will effectively
address the effort required for an upgrade and will provide the information required to properly classify the
route. The general engineer conducts reconnaissance to obtain information needed to classify and provide
designs for upgrades.
3-87. Route reconnaissance is conducted to evaluate the proposed routes, soil properties, terrain, borrow
sites, quarries, hydrology, and condition of existing roads. The information from route reconnaissance
supports route selection decisions; design of a new road; or the maintenance, repair, or upgrade of an
existing road needed before a route can carry the proposed traffic.
3-88. Route reconnaissance is classified as hasty or deliberate. The way in which route reconnaissance is
performed depends on the amount of detail required, the time available, the terrain problems encountered,
and the tactical situation.
3-89. Hasty route reconnaissance determines the immediate military trafficability of a specified route. It is
limited to critical terrain data necessary for route classification. The results are part of the mobility input to
the common operational picture. Information concerning the route is updated with additional reports as
required by the situation and/or the commander's guidance.
3-90. A deliberate route reconnaissance is conducted when sufficient time and qualified technical
personnel are available. Deliberate route reconnaissance is usually conducted when operational
requirements are anticipated to cause heavy, protracted use of the road and may be the first reconnaissance
conducted or follow the conduct of a hasty route reconnaissance.
ENVIRONMENTAL RECONNAISSANCE
3-95. Environmental reconnaissance is focused on collecting technical information on existing
environmental conditions and identifying areas that are environmentally sensitive or of relative
environmental concern. The information collected is used to assess the impact of military operations on the
environment and to identify potential environmental impacts on safety and protection.
3-96. Like infrastructure reconnaissance, environmental reconnaissance is a multidiscipline task conducted
by a base team augmented as necessary with additional expertise. An engineer reconnaissance team may
conduct the initial site assessment and gather information, which assists in determining whether a parcel of
land is acceptable for military use. This assessment is as detailed as the situation permits and is focused on
determining whether the site is healthy for Soldiers and Marines.
3-98. If the tactical situation permits, commanders conduct an EBS before occupying a site. An EBS
documents the original environmental condition of the land. An EBS is required if an area is to be occupied
by U.S. forces for more than 30 days. Linking an EBS to the signing of a lease whenever possible is an
excellent method of providing desired financial protection for the United States and its allies against unjust
and unreasonable claims and charges for using, renting, or leasing real or personal property.
3-99. An EBS identifies environmental hazards and issues that could impact area suitability for occupation
by U.S. forces. This document is also critical during base cleanup and closure, when the U.S. military
prepares to return the land back to the HN in its original condition. An EBS is also conducted to protect the
U.S. government from future claims or liability.
3-100. Ideally, the EBS is conducted in conjunction with an EHSA since the two documents support each
other. An EHSA is conducted by a medical base team augmented with other specialties (engineer, CBRN,
or others).
3-101. An EHSA is conducted to determine whether environmental contaminants from current or prior
land use, disease vectors, or other environmental health conditions that could pose health risks to deployed
personnel exist at the deployment sites. Additionally, an EHSA identifies industrial facility operations and
commodities near the site that could, if damaged or destroyed, release contaminants harmful to personnel.
While the EBS is generally more visual and engineer-related, the EHSA is more analytical (which includes
a greater variety and detail of sampling), with a greater focus on health hazards.
Note. See the Environmental Surveys Handbook: Contingency Operations (Overseas) and FM 3-
34.5/MCRP 4-11B for more information on conducting an EBS before the establishment of a
base camp.
UNCERTAINTY
3-102. Commanders and their staffs must have tolerance for the uncertainties (beyond their span of
control) associated with planning GE solutions, specifically base camps and bed-down facilities, and be
prepared to handle the inherent ambiguities and complexities through extensive planning and continuous
coordination that effectively mitigate risk. Two of the most demanding challenges are as follows:
Projected population. Accurately estimating the intended base camp population (personnel,
vehicles, and equipment that will be on the base camp or facility at any one time). This can be
difficult due to fluid changes in assigned units, transient personnel, contractors, and HN
personnel.
Projected service life-span. Accurately determining the expected service life-span of the base
camp or facility based on mission duration. The size and composition of the deployed force may
change between planning and construction and will almost certainly change over the life-span of
a base camp or facility. In addition, the actual mission support timeline may also change over
time and require adjustment as well.
3-103. These uncertainties force planners to plan and seek design GE solutions based on valid
assumptions, which if proven false can result in inadequate facilities and infrastructure or wasted
construction that cannot support the mission. With this in mind, engineers strive for planning and designing
scalable solutions, which will assist in mitigating the effects of uncertainty.
using computer- or application-aided design. Each method may be needed to site-adapt standard facility
designs. All methods of design require engineering judgment, the application of engineering principles,
mathematical problem solving, and engineering knowledge.
DESIGN CONSIDERATIONS
3-106. Key design considerations include—
Operational requirements.
Resource constraints.
Basing strategies.
Base camp schemes.
Master plans.
Design criteria.
Standards.
Design life expectancies.
Economic analysis.
Available materials.
Available units.
Intended purposes or functions.
3-107. Design produces efficient and effective solutions. Ideally, if a new design is necessary, it should be
simple and flexible and must reflect available materials and the level of training of construction personnel.
(See TM 3-34.51.)
3-108. During design, engineering principles, construction means, standards, site conditions, and
adaptable, scalable designs are matched against client facility and infrastructure requirements. The end
result is the production of detailed site designs, plans, drawings, specifications, and special instructions
needed for constructing facilities and infrastructure that meet requirements. Some higher headquarters
designs may be conceptual, preliminary, detailed, or final-approved designs. Some designs cannot be
finalized until the construction unit completes their engineering reconnaissance to obtain on-site
information. Other standard or detailed designs may be site-adapted with or without higher headquarters
approval.
and specifications and to design change directives required to accommodate the differing site conditions,
client-requested changes to the design, or problems encountered during construction.
3-112. The architect or engineer produces a set of plans and specifications (to include a submittal register
for materials, equipment, and systems requiring approval before use) based on the concepts and
requirements that define and meet the needs of the client. The architect and engineer may provide design
and engineering assistance and oversight during project construction.
Site-Adapted Designs
3-113. Site-adapted designs are generally approved by the headquarters that completed the concept
designs. The constructing unit may possess the necessary engineering expertise (or obtain it through
reachback), automated design tools, access to standard designs, and network capability to share, archive,
and print construction documents.
3-114. Planners and the constructing unit assess the progress and compare forecasted outcomes with
actual events to determine overall effectiveness. Based on this assessment, adjustments are made or new
options are developed to achieve the desired results. Lessons learned and recommended improvements to
standard designs and theater adaptations are captured to facilitate design modifications, and facility records
and as-built designs are updated and maintained to facilitate future construction and transfer or closure.
3-115. One of the possible options for base camp and bed-down facility design of new facilities should be
the use of standard AFCS designs. As plans are finalized, the standard designs are site-adapted accordingly.
If some or all existing facilities are used, the information from the AFCS can be used as planning factors to
help estimate and assess facility requirements and design upgrades. Standard facility designs should be
modular, scalable, sustainable, and energy-efficient. The AFCS and Service doctrinal design and
construction technical publications should provide metric designs and standards that can be used in regions
that use the metric system.
3-116. When possible, the construction unit should be included in the design effort. Since the construction
unit may not yet be identified during the initial design effort, an engineer with construction experience,
knowledge of construction techniques, and unit capabilities should be part of the design team. The
construction unit or its immediate higher headquarters should be included in the detailed design process if
they are not directly responsible for it.
3-119. In permanent, peacetime construction, underground drains are often used because the efficient use
of space, environmental considerations, and safety practices do not permit large, open ditches, particularly
for the disposal of collected runoff. In contrast, designs for road drainage in contingency operations use
surface ditching almost exclusively because of limited pipe supplies and the absence of storm sewer
systems to collect runoff. Design the drainage system to remove surface water effectively from operating
areas, to intercept and dispose of runoff from adjoining areas, to intercept and remove runoff expected due
to the selected design storm, and to minimize the effects of exceptionally adverse weather conditions.
3-120. The siting of base camps and individual facilities can have major effects on required drainage
structures and their associated cost in terms of materials and construction effort. Inadequate drainage is the
most common cause of road and airfield failure. Data on local drainage conditions for initial planning may
be obtained from maps and aerial reconnaissance and then confirmed with on-site ground reconnaissance
and information from local inhabitants. (See FM 5-430-00-1/AFJPAM 32-8013, Volume I, for a discussion
on drainage system designs.)
DESIGN VARIABLES
3-121. Some of the primary variables affecting design that must be resolved through planning and
reconnaissance include—
The availability of suitable existing facilities and infrastructure.
The availability of suitable construction materials and means for performing construction
(skilled labor and special equipment provided by troops and or contractors).
Facility allowances and construction standards.
The prescribed level of capabilities and linkages to other similar facilities.
Terrain and weather effects at selected facility locations.
Protection and security requirements (based on threat and vulnerability assessments).
Civil and environmental considerations.
Cost and time constraints.
Governing U.S. regulations and policies and HN laws and customs.
PROTECTION CONSIDERATIONS
3-122. Facilities should be designed to resist attack through selecting proper materials, limiting the
number of doors and windows, and orientating openings to minimize overall blast radius exposure.
Minimum contingency requirements normally are hardened walls and roof that protect occupants and that
are sized to adequately accommodate personnel.
3-123. Overhead blast protection designs can be incorporated into contingency construction facilities and
are available as a retrofit for existing structures (such as low-emissivity glass [commonly referred to as
e-glass]). The most common design is a layered structure with one layer used to detonate incoming
munitions and a second layer used to absorb the blast concussion and shrapnel.
3-124. The AFCS incorporates limited protection requirements into its designs. Protection designs fall
into two main categories: isolation and hardening. For facility protection, planners consider using facility
hardening, dispersion, standoff, and security. Some examples are as follows:
For facilities that must be isolated, most designs will need to be augmented. One means is the
use of soil-filled containers to create a system of barriers that surround and separate the facility.
The hardening of facilities is desirable when terrain constricts dispersion and the threat analysis
indicates that the facilities are likely possible targets for enemy weapons. Concrete masonry
walls can be hardened with reinforced concrete up to the blast height. The walls can also be
reinforced with blast mitigation products as outlined in GTA 90-01-011. Hardening techniques
are discussed in ATP 3-37.34/MCWP 3-17.6.
Widely dispensing facilities (where terrain conditions permit) should be established to prevent
the enemy from inflicting massive damage in a single strike; however, precautions must be made
to ensure that operations are not unduly hampered by ill-planned dispersion schemes.
Standoff distances that equate actual distance from force protection barriers, such as fences, to
the closest facility should also be considered. Avoid building facilities close to fences.
3-125. The force protection of a facility or installation may be accomplished by active and passive
security measures, including facility hardening and dispersion. (See ADRP 3-37 and ATP 3-37.34/MCWP
3-17.6.) The enemy situation must be evaluated as carefully and thoroughly as possible. Threats to supply
and maintenance facilities may include conventional and nonconventional ground forces, CBRN threats,
and attacks delivered by direct and indirect systems. The remote delivery of mines should also be
considered.
3-126. Insurgent activities may pose a threat to logistics assets. In determining how to best protect a
facility against interdictory attacks, the commander must take into account the surrounding terrain, local
weather and climate conditions, the availability of Class IV and V materials to support protective measures,
and the current enemy situation.
3-127. From the GE perspective, the protection areas that most affect base camp development (site
selection, layout, design, and construction) include base camp security and defense, antiterrorism measures,
survivability, facilities for force health protection, safety techniques (including fratricide avoidance),
physical security systems and, if assigned the task, detainee and resettlement facilities. The development of
the base camp layout will ensure the adequate protection of personnel and assets.
3-128. The key to the effective development of base camp protection is a working partnership between
those personnel focused on antiterrorism and other protection issues and the site engineers. This partnership
facilitates the development of integrated physical security protective measures and security procedures that
are consistent with base camp design.
3-129. The early identification of protection requirements is essential to base camp planning efforts.
Addressing the collective protection concerns early helps to ensure that site location and layout are
compatible with security operations and mission accomplishment.
Notes.
1. See ADRP 3-37, AFCS program guidelines, ATP 3-37.2, ATP 3-39.32, GTA 90-01-011, and
ATP 3-37.34/MCWP 3-17.6 for additional information on determining threats, assessing
vulnerabilities, and integrating antiterrorism and protection measures within operations.
2. See UFC 4-010-01 and UFC 4-010-02 (FOUO) for additional information on antiterrorism
standards.
3. See UFC 4-010-03, UFC 4-010-05, UFC 4-020-01, UFC 4-020-03FA (FOUO), UFC 4-021-
01,
UFC 4-021-02, UFC 4-022-01, UFC 4-022-02, UFC 4-023-03, UFC 4-023-07, UFC 4-024-01,
and UFC 4-025-01 for additional information on facility force protection planning, design, and
construction.
4. See UFC 1-201-01 for additional information on the criteria for life safety- and habitability-
related design requirements for nonpermanent facilities in support of military operations.
or storage areas containing more than 100,000 square feet of storage space are each allocated at least one
fire pumper truck team.
3-133. The commander has full responsibility for implementing fire prevention and protection. All U.S.
Army, command, and local fire regulations must be enforced. Programs of inspection must be established,
self-help and firefighting responsibilities identified, and equipment assigned. AR 420-1 provides further
information about fire prevention and protection.
3-134. Fire protection measures available to the commander include—
Enforcing the rule.
Setting up alarm and notification procedures.
Procuring and making available extinguishers and other firefighting equipment.
Training personnel in fire prevention and protection measures.
Locating water tanks and reservoirs in key centralized areas to properly support firefighting
activities.
Ensuring that installation or base camp facilities allow access for firefighting personnel and their
vehicles to move about freely to perform their duties unimpeded.
3-135. An additional requirement for the assets that provide fire protection is responding to hazmat spills.
This support is an important part of environmental considerations that may have a direct effect on force
health protection. (See UFC 3-601-02 for additional information on dry chemical suppression systems.)
Safety
3-136. Designers work together with safety specialists to mitigate hazards that are developed as part of
risk management, which is initiated during planning and continues throughout the base camp life cycle.
3-137. The design influences safety considerations during construction. Some designs and the associated
construction methods may be more difficult, especially when unskilled labor is used, and inherently more
dangerous. Designers must ensure that the complexity of designs is reasonable and justifiable based on the
construction means available and that the means for enforcing safety and mitigating risks during
construction is achievable. HN laborers and contractors may not adhere to expected construction and safety
standards.
3-138. Any specifications in component configurations, materials, and construction tasks that are essential
for achieving the quality and safety features of the design must be clearly articulated and communicated to
the constructing unit and become part of the overall quality assurance or quality control plan. Any incorrect
design decisions, changes desired by the facility user, or material substitutions based on availability may
require the reevaluation of designs.
3-139. One of the possible options for the base camp and bed-down facility design of new facilities
should be the use of standard AFCS designs. As plans are finalized, the standard designs are site-adapted
accordingly. If existing facilities are used, the information from the AFCS can be used as planning factors
to help estimate and assess facility requirements and design upgrades. Standard facility designs should be
modular, scalable, sustainable, and energy-efficient. The AFCS converts U.S. standard designs to metric
designs.
3-140. When possible, the construction unit should be included in the design effort. Since the construction
unit may not yet be identified during the initial design effort, an engineer with construction experience,
knowledge of construction techniques, and unit capabilities should be part of the design team. The
construction unit or its immediate higher headquarters should be included in the detailed design process if
they are not directly responsible for it.
Structural Integrity
3-141. The safety risks from structural collapse increase when existing buildings are used for a new
purpose with greater loads or when damaged. Although contingency construction standards are generally
conservative to address a wide range of loads in different environments, the structural integrity and
conditions of an existing structure can vary greatly based on HN construction standards, the quality of
construction, and the effects of battle damage. Existing structures may have little resistance to seismic
activity, abnormal weather, or impact loads.
3-142. The general engineer or other qualified engineer representative must oversee the allowable use of
existing structures. A proper structural analysis and materials evaluation must be completed before any
protection measures are affixed to an existing structure since they may increase the load-bearing structural
capacity.
3-143. A qualified engineer oversees the repair, modification, or expansion of any existing building to
ensure that it conforms to established policies and standards. Construction variances with structural
components that deviate from the Service standards require a structural assessment and compliance with
Unified Facilities Criteria. Material substitutions for structural members with standard designs require a
structural assessment and compliance with Unified Facilities Criteria. This necessitates completing a
structural assessment and repair before buildings can be occupied.
Legend:
AA assembly area
EWL engineer work line
3-148. Figure 3-2 depicts an example of multiple engineer work lines to depict responsibilities between
engineers (who are organic and who augment BCTs) and BCT and echelons-above-BCT engineer units. In
this case, engineers (who are organic and who augment BCTs) would focus primarily on engineering tasks
inside Engineer Work Lines Dog, Cat, and Lion, while echelon-above-BCT engineers are responsible for
GE tasks throughout the remainder of the division AO, including the intermediate staging bases. During the
offense and defense, the focus shifts to providing support to the BCTs and providing combat engineering
support to combat maneuver forces. However, during stability operations or DSCA, GE tasks will be
executed with echelons-above-BCT engineers operating throughout the AO.
Legend:
AO area of operations
EWL engineer work line
ISB intermediate staging base
MSR main supply route
3-149. At corps, theater, or joint levels, the engineer staff officer for that echelon may establish a corps
engineer work line or theater engineer work line in much the same manner as the division work line. The
theater engineer staff officer augments subordinate echelons by assuming responsibility for specific
support, on a task basis, forward to the appropriate engineer work line, thus releasing the direct
support/general support GE units to engage in activities as far forward as possible.
3-150. The engineer staff officer who assigns the engineer work line to a particular sector is responsible
for planning and advising the commander when the engineer work line shifts. This occurs after a careful
analysis of the ongoing operation, available GE assets, and future requirements. Early in a contingency, it
may be very difficult for the theater engineer staff officer to shift the theater engineer work line out of the
theater staging base because of shortages in GE assets.
3-154. Although Unified Facilities Criteria are written with long-term standards in mind, planners who
are executing under contingency and enduring standards for GE tasks will find them useful. Topics include
pavement structure design, water supply systems, military airfields, concrete design and repair, plumbing,
electrical systems, and many others. The Unified Facilities Criteria are distributed only in electronic media
and are effective immediately on issuance.
3-155. The Unified Facilities Criteria system provides planning, design, construction, operations, and
maintenance criteria and applies to all Service commands having military construction responsibilities.
Unified Facilities Criteria are living documents and will periodically be reviewed, updated, and made
available to users to provide technical criteria for military construction. Unified Facilities Criteria are
effective upon issuance and are distributed only in electronic media from—
The Unified Facilities Criteria index Web site.
The USACE Technical Information Web site.
The NAVFAC Engineering Criteria and Programs Office Web site.
The Construction Criteria Base Web site.
UFC 1-200-01.
The Whole Building Design Guide Web site.
FORWARD-PRESENCE CAPABILITY
3-158. FFE has the ability to form scalable modular teams that are capable of deploying into theater on
short notice to provide engineering support to the CCDR and fill gaps in capabilities and expertise.
Engineer planners must carefully analyze the mission to determine the required level of forward-presence
support and tailor its requests. Because these teams can be tailored, specificity of requests in terms of the
mission type is critical. To facilitate the engineer planning effort, USACE maintains established liaison
officer planners at the combatant command and ASCC levels.
3-159. Requests for USACE support should be channeled through the USACE liaison officer at the
combatant command or ASCC echelons. The USACE assistant chief of staff, operations (G-3) will respond
to requests for engineer support in the event that coordination through a liaison officer is not possible.
REACHBACK CAPABILITIES
3-161. Engineers have a variety of reachback capabilities at their disposal. These capabilities include
the—
U.S. Army Engineer School.
U.S. Marine Corps Engineer Center.
Engineer Infrastructure and Intelligence Reachback Center.
Base development team.
USACE Reachback Operations Center.
Reachback equipment.
Reachback Equipment
3-171. USACE and other engineer organizations use a variety of systems for facilitating reachback for
technical engineering support for problems requiring rapid solutions. Reachback equipment includes the
TeleEngineering Communication Equipment, geospatial assessment tool, automated route reconnaissance
kit, and TeleEngineering Toolkit software.
3-177. The response is sent back from the mission support element and is graphically displayed on the
TeleEngineering Toolkit software system. It also works with the automated route reconnaissance kit using a
global positioning system, a video camera, and a three-dimensional accelerometer to provide a mounted
vehicle or airborne automated reconnaissance capability.
DRAINAGE
4-12. The constructing unit establishes construction drainage on the construction site to prevent water from
interfering with the construction progress. Construction drainage may be temporary drainage structures or
part of the permanent drainage system constructed early.
PROTECTION
4-13. The constructing unit constructs protective structures using protection designs, construction
techniques, and methods discussed in ADRP 3-37, AFCS program guidelines, ATP 3-37.2, and ATP 3-
37.34/MCWP 3-17.6.
PROJECT MANAGEMENT
4-14. NTRP 4-04.2.5/TM 3-34.42/AFPAM 32-1020/MCRP 3-17.7F provides all Services with common
methods, procedures, and formats for construction project management at the operational unit level
required by military engineers to successfully plan, schedule, and execute GE and contingency construction
projects. The duration and amount of effort for each phase depends on mission variables (the scope and
complexity of the project involved, the time available for planning, and the operational environment).
Project management does not replace the military planning process used by each Service for contingency
and crisis action planning or troop leading procedures at the tactical level for conducting unit operations.
4-15. Program and project management are used for most GE management. The U.S. Army has designated
some duty positions that require program or project management professional certification. Planners use the
construction project management as a tool to assist them in their process of coordinating the skill and labor
of personnel using machines and materials to configure the materials into a desired structure.
4-16. Figure 4-1 shows the project management process that divides the effort into three parts, consisting
of preliminary planning, detailed planning, and project execution. Preliminary planning may include the
completion of detailed designs by the constructing unit or provide an adjustment to the designs as required
by information obtained from the site investigation.
4-17. General engineer planners and construction units rely extensively on the TCMS to produce the
products required by the project management system. Effective products produced during the planning
phases greatly assist during the construction phase. In addition to the TCMS, the engineer has various other
reachback tools or organizations that can exploit resources, capabilities, and expertise that is not organic to
the unit that requires them.
4-18. Digital, handheld devices can be used to document existing conditions, speed accurate reporting, and
provide timely information to the construction site. They can decrease idle time on the construction site due
to decreased wait time for information. They can also decrease the time spent by supervisors on nondirect
construction tasks, such as reports and requests for information on-site and to or from higher headquarters.
4-19. Based on careful analysis, construction assignments, required facilities, and scheduled target dates
for phased development as outlined in the OPORD, general engineers can formulate a construction
schedule. Construction schedules are prepared to show a detailed time plan for operations in proper
sequence. The equipment hours and man-hours required for each principal operation are then tabulated.
4-20. The construction schedule is based on the—
Time allowed for completion.
Available equipment and special assets required.
Type of labor available (regular troop units, reserve troop units, newly activated troop units,
local contractors, international contractors).
Delivery of construction materials.
Local sequence of operations.
Necessary delays between operations.
Projected weather and climate conditions.
Force protection, antiterrorism considerations, and threat assessments.
Environmental, health, and safety considerations.
JOBSITE SAFETY
4-21. Jobsite safety at the construction site is important in preventing injuries, avoiding accidents, and
preventing death. The following are some of the resources that are available to assist engineers in safety
considerations:
AR 385-10, ATP 5-19, DA Pamphlet 385-1, and DA Pamphlet 385-10.
Unit safety standard operating procedures.
Commander’s guidance and policies.
U.S. Army Safety Center. (See the U.S. Army Safety Center Web site for additional
information.)
Center for U.S. Army Lessons Learned. (See the U.S. Army Combined Arms Center Web site
for additional information.)
Engineer manual 385-1-1. (See the USACE Publications Web site for additional information.)
U.S. Department of Labor Occupational Safety and Health Administration. (See the U.S.
Department of Labor Occupational Safety and Health Administration Web site for additional
information.)
JOBSITE SECURITY
4-22. Jobsite security is of paramount importance in preserving the force. Engineers in a combat role may
have limited manpower to accomplish their construction mission, yet they may find themselves devoting
manpower assets to providing jobsite security in high-threat areas. Consider requesting external
augmentation from infantry or other combined arms units for jobsite security forces. This will allow the
engineer to devote manpower resources toward construction project completion.
METHODS OF CONSTRUCTION
4-23. The major construction methods used by military general engineers are on-site construction, design-
build construction, and modular construction. The on-site construction of buildings is also called stick-built
or stick frame if referring to carpentry. Larger post and beam or timber frames may be used for bunkers and
protective structures. Most military GE uses on-site construction.
4-24. Planners determine the major construction methods for various requirements based on operational
considerations and economic analysis. Standardizing the construction methods used throughout an
operational area simplifies estimating methods, safety requirements, training requirements, quality
assurance, quality control, and O&M. Each construction technique has various construction methods with
considerations, advantages, and disadvantages. The construction unit adjusts the construction methods
based on local conditions, material availability, local construction methods and labor skills, and the ability
of the HN to maintain facilities intended to be turned over to them when no longer needed.
4-25. Construction is a broad term that may include the following tasks:
Provide new construction.
Upgrade existing facilities.
Assemble or erect preengineered buildings or systems.
4-26. Deconstruction is done to scale down the size of a facility, structure, or building. During
deconstruction, many of the same construction techniques may be used if the materials are to be reused on
other projects. Deconstruction may simply be the reverse of a construction technique. Demolition may be
carefully performed to allow the reuse of some construction materials, or demolition may be completed to
prevent the enemy from reusing a facility.
4-27. Construction may be provided by—
Military units. Troop construction is economical because it eliminates labor cost and contractor
profit. Tactical considerations may create situations in which HN support contractors are
unwilling or unable to undertake construction projects. Troop construction is more flexible
because there are no contracts to negotiate for changes in plans, specifications, or required
available time allowances.
Contractors. Contractors bring laborers with specialized skill sets in the desired numbers with
specialized equipment and required resources. Contractors have greater flexibility, as opposed to
troop labor that is restricted by combat mission demands. Troop construction equipment may not
be as specialized as contractor equipment, because it must be rugged and flexible enough to meet
combat conditions. Contractors bring a dedicated pool of talent to focus exclusively on the
construction project, as opposed to troops who must focus on combat mission and other military
duties.
Local labor assets. Using local labor may be more economical than bringing in external
contractors from the continental United States (CONUS) or other countries.
HN labor assets. Like local labor, HN labor may provide the right skill sets and resources to
meet construction project needs within economical cost.
DESIGN BUILD
4-30. Design-build (also called design and build contracting process, or method of delivery) is a common
construction method used by industry and Service construction agents. Typically, most design is completed
by architectural engineer firms, who then go out for construction bids. Then, the project is built by
construction firms (a design-bid-build contracting process). Design-build combines these two processes
together by having a single organization perform them to achieve time and cost savings.
4-31. Concurrently, construction can begin based on some completed designs while other designs are
completed as construction progresses. As the project progresses, the constructing unit has the opportunity
to provide immediate input to the design based on site conditions, available materials, and preferred
construction methods. Most military unit construction is designed and then built, sometimes by the same
unit. However, on a larger, more complicated project without all requirements known at the start, design
and construction conducted concurrently as information becomes available is an effective construction
method.
MODULAR CONSTRUCTION
4-32. Modular construction is a method of construction, not a building type. Modular construction involves
procuring commercially prefabricated or military unit prefabricated buildings, components, or systems of
multiple sections (called modules) that are joined together on-site. Engineers provide the contracting office,
quality and construction standards, specifications, and codes that the contracted modules must meet.
4-33. The prefabricated sections are typically transported to the site by truck and then, depending on
weight, off-loaded and positioned with a crane or other material-handling equipment. The constructing unit
assembles the prefabricated sections with organic tools or special tools provided as part of the system. The
modules may require limited site preparation or a foundation that can be constructed simultaneously with
off-site module construction.
4-34. The modules may be prefabricated as a box that has more shipping volume or as flat panels or
components that have less shipping volume but require more assembly time on-site. Depending on
transportation restrictions, the modules may be up to 20 feet wide and 90 feet long. Precast or prefabricated
concrete panels, structural insulated panels, or other major building components may be produced on-site,
contracted for and shipped, or locally procured.
4-35. Modular construction may produce semipermanent facilities that may be disassembled and reused.
Another possibility is to design and procure relocatable buildings that are partially or completely
assembled. Relocatable modular buildings are designed to be reused multiple times and transported to
different sites.
4-36. Modular construction may offer several advantages to site-built facilities, such as—
Increased design time savings (comes predesigned).
Increased construction speed.
Fewer weather considerations.
Increased flexibility of configurations and module layouts (modules that may be disassembled,
refurbished, and reused).
CONSTRUCTION MATERIALS
4-37. Depending on the project type, required construction materials can be expensive, specialized, and
unique. There are a variety of different materials that can be used in construction, including steel, rock,
wood, and concrete. Class IV supplies include all construction materials and installed facility equipment.
4-38. Theater requisitions for engineer construction materials must take careful account of project
requirements for special, large-scale operations. Issues from stocks are based on the requirements for the
particular work on which the requisitioning unit is engaged. Critical items of Class IV supplies may be
issued under policies approved by the assistant chief of staff, logistics (G-4); uncontrolled items are issued
on-call.
4-39. The task of providing engineer construction supplies can be quite comprehensive and costly, and
every effort must be made to simplify it through the use of local procurement channels and standardized
designs. The unit supply officer maintains a local inventory of continuous stocks of construction materials
and equipment. Class IV supplies suitable for local procurement may include lumber, cement, structural
steel, sand, gravel, rock, plumbing and electrical supplies, hardware, and paint.
PROCUREMENT
4-40. Obtaining materials on time and in the quantity and quality needed must be coordinated and
synchronized to support the assembly of other resources (time, personnel, equipment) to complete the
project. Construction of any kind will fail if the required materials (or suitable substitutes) are not available
when needed. Efforts to obtain the proper material begin early during the planning phase (receipt of
mission or construction directive) and do not end until the project is completed and turned over.
4-41. For procurement, engineers have the option of obtaining materials from CONUS through the service
supply system, from countries as adjacent to the area of responsibility as possible, and from local suppliers.
Each method has inherent costs and benefits. Engineer units may be used, or a contractor hired, to produce
the necessary materials. Whatever the method, obtaining resources must be an integral part of planning and
executing tasks to properly accomplish the mission.
Class IV Materials
4-42. Units may obtain GE construction materials by using standard supply procedures that unify the way
in which they are requested, managed, and distributed. Most construction materials are Class IV materials
and are distributed according to unit standard operating procedures. Many Class IV materials are also used
for field fortifications, fighting positions, and other types of protection work, making it likely that they are
in high demand and necessitate engineer involvement in distribution decisions.
4-43. Class IV supplies are not maintained in significant quantities and are bulky. This makes handling
and transporting supplies over strategic distances difficult. Obtaining GE materials through normal supply
channels is considered the least efficient and desirable method for GE missions. Engineers should only use
this method after determining that the materials are unavailable locally, the proper quantity and quality
cannot be met locally, or the cost to obtain them is prohibitively high. Engineer logisticians must constantly
track the status of orders throughout the requisition process to ensure that they are filled.
4-44. Maintaining Class IV supply points is a logistics function that engineer units are not organized or
equipped to perform. Although engineer units should avoid operating Class IV supply points, recent and
repeated experience in contingency environments has shown that engineers are habitually forced to do so to
ensure the completion of GE missions, particularly when time constraints exist. Engineers should be
involved, but they should not be required to run Class IV supply points. Units may need to be creative in
the way they obtain Class IV supplies, such as using materials from base camps that are closing.
Considerations
4-46. Although obtaining materials for GE missions is often the most advantageous method of needed
requirements, engineers must consider the following factors:
Standard sizes of GE materials may be different in the AO. Dimensional lumber is often cut to
different standards in foreign countries. Voltage systems in overseas locations are also typically
different from CONUS.
The quality of different items may be considered substandard. Lumber, concrete, and asphalt are
three examples of construction materials that are typically not consistent with U.S. standards.
Language and cultural differences may make it difficult to communicate and obtain GE supplies.
In some situations, local vendors may feel that it is more important to try to please you in initial
discussions than to tell you the truth about whether they are capable of providing materials in the
quantity and quality needed.
Military operations may drive up prices. Shortages caused by multiple units competing for the
same resource may induce local suppliers to inflate prices and profiteer from ongoing operations.
4-47. Table 4-1 is a list of supplies that units might maintain in an engineer Class IV supply point during a
contingency. Note that it contains only very basic materials and supplies.
Table 4-1. Sample stockage level for engineer Class IV supply point
Table 4-1. Sample stockage level for engineer Class IV supply point (continued)
Table 4-1. Sample stockage level for engineer Class IV supply point (continued)
Table 4-1. Sample stockage level for engineer Class IV supply point (continued)
od olive drab
port portable
psi per square inch
pt pint
PVC polyvinyl chloride
recp receptacle
rect rectangle
ro roll
rs rustproof series
sch schedule
scr screwed
sfc surface
sol solid
st set
std standard
stl steel
str strand
sw solid wall
thds threads
thw thermoplastic vinyl-insulated building wire
v volt
w watt
wog water, oil, or gas
wp wall plug
wt weight
UI unit of issue
yd yard
PRODUCTION
4-48. Certain types of materials are typically needed in such large quantities and are of such great weight
that engineers must produce them locally (or contract a supplier). Soil for fill, sand, and gravel are
examples of materials that are typically obtained from local sources. Contracted construction and the
construction directive for engineer units should specify quality standards for the use of local materials that
are verified through inspections as part of the quality assurance or quality control plan.
4-49. To produce more refined products, engineers may need to further process materials to obtain required
construction materials, such as crushed rock, asphalt, and concrete. There are specialized engineer units
(quarry teams, asphalt teams, concrete sections) that handle production missions for most types of
construction materials. Significant environmental considerations may be placed on U.S. forces when
creating or operating construction sites.
and the evaluation of possible sites for underground installations. Military commanders should incorporate
geologic information with other pertinent information when planning military operations.
4-52. Material testing involves obtaining samples, performing engineering tests and calculations on soils,
bituminous paving mixtures, and concrete. These materials include aggregates, bituminous materials, and
stabilized soil, including stabilizing agents such as bitumens, cements, lime, fly ash, and chemical
modifiers. Material testing is conducted to achieve proper design with these materials and adequate control
over their use in construction. (See FM 5-472/NAVFAC MO 330/FAJMAN 32-1221(I) for a discussion on
material testing. See TM 5-818-1/AFM 88-3 for information on soils and geology.)
Crushed Rock
4-58. TM 3-34.65/NTRP 4-04.2.12/AFMAN 10-903 provides a discussion on aggregate production
through rock-crushing operations. Rock of specific size and gradation is required for asphalt and concrete
production. Crushed rock is used as the base course for roads and airfields. Rock from quarry operations
and borrow pits must be crushed, screened and, perhaps, washed to meet specific design standards. (See
Asphalt
4-64. TM 3-34.63 provides information on asphalt production. The specialized engineer unit that can assist
is the asphalt team. This team has the required trained personnel and equipment to support asphalt
operations The typical U.S. Army asphalt plant is a portable, drum type, electric motor-driven facility that
is capable of self-erection (major components) and satisfactory operation without permanent footings. It
consists of major units, components, and accessories as required to assemble a complete plant that is
capable of producing 150 tons per hour of graded asphalt paving mix.
4-65. The asphalt plant may be set up for batch and continuous mix. It is trailer-mounted and can be
interconnected mechanically and electrically and operated to the rated capacity. A good road network is
needed to avoid traffic jams and the resultant cooling of mixes. The planner must also consider the
potential environmental problems, including dust that is generated by the plant and potential soil
contamination from bitumen and fuel spills.
4-66. The construction paving unit will use some asphalt production equipment at the jobsite, to include an
asphalt melter and an oil heater. The following are key features of asphalt equipment:
The asphalt melter is a skid-mounted, 750-gallon-per-hour, dedrumming asphalt melter. The
dedrumming tunnel is capable of removing 85- to 100-penetration cement from twelve 55-gallon
drums at one time. The unit also contains a 3,000-gallon, hot-storage compartment for heating
the asphalt to pumping temperature (235°F). Melters can operate individually, in pairs, or in trios
and can operate in parallel from a single source of hot oil.
The oil heater is a trailer-mounted, heavy-duty, high-output capacity unit that is designed to
transfer oil and pump it through transmission lines to the asphalt melter and storage tank. It
requires fuel and external electric power for operation.
4-67. Asphalt as a construction material has advantages and disadvantages. As a surface covering for roads
and airfields, it provides a flexible and durable covering. However, it is impacted by extremes in climate
and weather conditions affecting its structure. It requires continuous maintenance to remain serviceable and
to extend its service life.
Concrete
4-68. TM 3-34.44/MCRP 3-17.7D provides planners, designers, and general engineers with information on
the production of concrete. Planners refer to it when determining the design mixtures, form design and
construction, concrete production, and testing required for a specific mission. The specialized engineer unit
that can assist in concrete production is the concrete section. This section has the required trained personnel
and equipment to support concrete operations.
4-69. Concrete is produced by mixing a paste of cement and water with various inert materials. The most
commonly used inert materials are sand and gravel or crushed stone. A chemical process begins as soon as
the cement and water are combined.
4-70. Concrete as a building material has advantages and disadvantages. Concrete is fireproof, watertight,
economical, easy to use, and available worldwide. However, concrete can crack and other structural
weakness can detract from its appearance, survivability, and useful life.
4-71. The U.S. Army has mobile mixers in its inventory for the mass production of concrete. They are
mobile and self-contained units, which can produce fresh quality concrete at the construction site. These
mobile mixers include—
16S concrete mixer. This mixer produces a 16-cubic-foot batch of concrete. It is ideal for small
missions and can be moved to remote locations. The hourly production rate varies between 10
and 15 cubic yards, and it can also mix mortar.
M5 engineer mission module concrete mobile mixer. This mixer is transported by an M1075
palletized load system and M1076 palletized load system trailer.
M919 concrete mobile mixer. This mixer is a concrete material transporter and mixing
machine. It has the capacity to carry the materials for 5 to 8 cubic yards of concrete, depending
on usage (mobile/stationary). The M919 has limited trafficability and must remain on firm
ground. It requires a scoop loader to support it while mixing.
CONSTRUCTION TECHNIQUES
4-75. Construction techniques are the result of time-proven best practices that are employed by general
engineers. These construction techniques may be used for initial construction or the maintenance, repair,
upgrade, or rehabilitation of existing facilities. They can also be used for some deconstruction.
Construction capabilities may be viewed as horizontal or vertical. The key features of each construction
technique are described as follows:
Horizontal construction. Horizontal construction is earthmoving efforts to bring about a
desired design of an earth foundation. It can involve cut and fill operations, the emplacement of
drainage to create a level foundation, or the moving and shaping of earth to create berms. It
involves the employment of heavy-equipment operators and a variety of heavy construction
equipment. It can set the stage for follow-on vertical construction if structures are to be built on a
foundation, or remain as a stand-alone project. Examples of horizontal construction projects are
parking lots, runways, and roads.
Vertical construction. Vertical construction involves efforts at building or assembling
structures upwards above the ground. It can also involve underground structures, like basements.
It usually involves the employment of masons, carpenters, plumbers, electricians, and other
skilled laborers to build floors, walls, windows, trusses, and roofs. It can involve heavy
equipment to help erect the building components and use pneumatic power equipment.
Examples of vertical construction projects are buildings, bunkers, and skyscrapers.
TOPOGRAPHIC SURVEYING
4-76. Topographic surveying is performed by a topographic surveyor. A geodetic survey considers the size
and curved surface shape of the earth. A geodetic survey report is used for the positioning of field artillery
units, air defense units, aviation units, intelligence units, communications, and construction control points.
Most construction projects use plane surveys that require less accuracy and ignore the curvature of the
earth. Survey classifications include—
Artillery.
Basic control.
Satellite.
Construction.
Airfield engineering and navigation aid.
Hydrographic.
Field classification and inspection.
Land.
Inertial.
CONSTRUCTION SURVEYING
4-77. TM 3-34.55 discusses the methods and techniques used by military construction surveyors.
Construction surveying supports planning with reconnaissance and preliminary data to aide in route and
site selection. During the construction phase, the surveyor may extend geodetic survey control from a
construction control point or use plane surveys to support the layout and quality control of the road,
airfield, bridge, facility, utility, or building. Survey types may be reconnaissance survey, preliminary
survey, final location survey, and construction layout survey. The accuracy of the survey is normally
determined by the project manager.
EARTHMOVING
4-78. TM 3-34.62/MCRP 3-17.7I discusses earthmoving. Earthmoving or horizontal construction is
required on most GE projects. Major horizontal construction projects are typically roads and airfields.
Depending on site conditions, earthmoving for site preparation may consume most of the construction
resources.
4-79. Earthmoving efforts may include site preparation; excavation; embankment; construction; backfill;
dredging; base course, subbase, and subgrade preparation; compaction; and road surface.
4-80. The phases of horizontal construction projects include—
Notes.
1. See TM 3-34.55 for information on the use of surveying to plan and estimate earthwork.
3. See EP 1110-1-8 series for information on cost estimates and the hourly usage cost for
construction equipment.
4-84. Concrete may be reinforced by adding steel or other materials. Precast concrete products may also be
procured. Precast concrete is a mixture of aggregates that are held together by a hardened paste, which is
typically made by combining Portland cement with water. There are five common types and several special
types of Portland cements, all with varying properties and uses. Admixtures can also be added to concrete
to modify properties.
4-85. Concrete has a great variety of applications. It meets structural demands and lends itself to
architectural treatment. In buildings, concrete is used in major building components (footings, foundations,
columns, beams, girders, wall slabs, roof units). Other important concrete applications are in road and
airfield pavements, bridges, dams, irrigation canals, water diversion structures, sewage treatment plants,
and water distribution pipelines. Asphalt cement is used to make asphalt cement concrete for paving.
4-86. Masonry materials usually include concrete blocks, bricks, and structural clay tiles and may also
include rubble stone masonry. Masons use specialized equipment to lay out and construct masonry walls
and other building features. Masons determine the correct mixing proportions for mortar to bond the
masonry units together and safely erect scaffolding.
4-87. Masonry construction procedures include—
Modular coordination and planning.
Rubble stone masonry.
Bricklaying.
CARPENTRY
4-89. TM 3-34.47/MCRP 3-17.7C discusses carpentry details; concrete forms (because concrete forms are
constructed from wood); nonstandard, fixed, wood construction bridges (timber trestle bridges); and timber
pile wharves. Carpentry is the skilled labor of making, finishing, and repairing wooden objects and
structures. Carpentry work includes light wood framing, heavy wood framing (timber construction), finish
carpentry, and roof construction. Carpenters use their skills to perform metal construction work and to erect
metal buildings from a complete set of construction drawings (a set of plans).
4-90. Carpentry routinely uses two methods for erecting buildings as follows:
The built-in-place method.
The panel method (or preassemble method).
4-91. Carpenters are issued hand tool kits, power tool kits, and other equipment (such as pneumatic
compressors and nail guns) to speed their work. Carpentry tools include saws, blades, hammers, sawhorses,
braces, and other specialized woodworking tools. Carpenters are assigned to vertical construction platoons
and can be organized into work teams to ensure speed and efficiency.
Notes.
WASTE MANAGEMENT
4-94. Waste management is the collection, transport, treatment, or disposal of waste materials in an effort
to ensure a healthy and sanitary environment. (For more information about waste management see FM
3-34.5/MCRP 4-11B.)
4-95. Integrated waste management is the management of the entire waste process, including generation,
storage, collection, transportation, resource recovery, treatment, and disposal. It employs several waste
control methods based on the waste hierarchy (avoidance, reduction, recycling, reuse, recovery, treatment,
and disposal) and is aimed at minimizing the environmental impact of waste. (For more information about
waste management see FM 3-34.5/MCRP 4-11B.)
4-96. Engineers have staff proponency for waste management. Waste is categorized as nonhazardous solid
waste, wastewater, hazardous and special waste, and medical waste. Waste management includes the
construction, operation, and maintenance of new (and the upgrade of existing) utilities (examples are
sewage collection and treatment or landfill construction) and the construction of facilities for the purpose of
waste management.
4-97. TCMS provides some options for collection, treatment, and disposal facilities. (See TM 3-
34.70/MCRP 3-17.7E and FM 3-34.5/MCRP 4-11B for a detailed discussion on waste management. See
UFC 3-240-01, UFC 3-240-02, and UFC 3-240-03N for information on wastewater treatment systems
operation and management.)
PAVING
4-98. To construct roads and airfields, the military typically conducts three types of paving and surfacing
operations: bituminous pavements and surfaces, concrete pavements, and expedient pavements. Bituminous
pavement (wearing surface) is a compacted mass of bitumen and aggregate.
4-99. Concrete pavements usually combine Portland cement, water, and aggregates with possible
admixtures. TM 3-34.63 discusses construction materials and equipment; mix design; and production,
placement, and repair of bituminous and concrete pavements. It also provides a detailed discussion of
expedient pavements and surfaces.
5-6. The ASCC Assistant Chief of Staff, Movements, is responsible for operating ports and furnishing
liaisons with the U.S. Navy, U.S. Coast Guard, and other interested military and authorized civilian
agencies of allied countries and the United States. The Assistant Chief of Staff, Movements, advises and
makes recommendations concerning the engineer troops employed and the work concerned. (See the annex
in the joint OPLAN or OPORD for environmental considerations.)
Diving Support
5-10. Building new ports and facilities requires extensive diving support. A dive detachment is normally
assigned to the ASCC to provide dive support in ports, harbors, and costal zones. Dive detachments are
assigned and attached to the theater engineer command, which allocates them according to mission
requirements. The detachment may be attached or assigned to a subordinate headquarters or task-organized
with supporting units to provide direct-support diving capabilities.
5-11. Dive detachment capabilities are tailored to the mission (allowing the use of surface-supplied diving
apparatus, scuba, and remotely operated vehicles), and they work closely with heavy equipment operators
for large-scale operations. Supporting diver assets range from a small scuba team to multiple larger teams
with a diverse range of capabilities. An engineer dive team has enough personnel and equipment to conduct
multiple diving operations currently. Divers can work up to a depth of 190 feet in support of GE.
Note. The U.S. Army does not have explosive ordnance disposal-trained diving teams.
5-13. Port opening, construction, and rehabilitation missions include planning and inspection, clearance,
repair, and quality assurance inspections. Salvage missions include refloating and rigs for towing. Ship
husbandry includes in-water hull inspections, in-water maintenance, and damage control and repair. JLOTS
support includes hydrographic surveys, mooring systems, and off shore petroleum systems. Diver civil
assistance and civil defense missions include humanitarian support, port rehabilitation, construction, and
peacetime missions.
5-14. Divers enhance force protection by conducting security swims and the emplacement or removal of
underwater obstacles and barriers. This includes installing underwater security systems. Divers also enable
expeditionary logistics by providing accurate waterway datum, surveys, and the repair of existing
waterfront facilities. Engineer dive missions assist in building capacity through infrastructure support and
sustainment operations.
5-15. Divers also provide technical assistance and staff planning support to the ASCC through brigade
commanders. (See ATTP 3-34.84/MCRP 3-35.9A/NTTP 3-07.7/AFTTP 3-2.75/CG COMDTINST
3150.1C, SS521-AG-PRO-010, TM 3-34.73, and TM 3-34.83 for additional information on dive teams,
diving support requests, and diving operations.)
Construction Support
5-16. Vertical and horizontal companies augmented with a concrete section, dive team, and other specialty
teams or sections accomplish most construction or salvage tasks. In performing their mission of
construction, expansion, rehabilitation, conversion, maintenance, and repair of a port, U.S. Army engineer
responsibilities include—
Construction and repair of breakwaters, docks, piers, wharves, quays, moles, and landing stages.
Construction and maintenance of port area roads.
Construction and major maintenance of railway facilities required by the port.
Construction of storage and marshaling areas required by the port.
Construction or reconstruction of port utilities (water supplies, electrical power systems,
sewerage).
Construction and major maintenance of tanker unloading facilities (mooring facilities;
submerged pipelines; surface pipelines; rigid petroleum, oils, and lubricant tank farms).
Maintenance and operation of port firefighting facilities.
TRANSPORTATION UNITS
5-20. U.S. Army transportation units are responsible for opening and operating the port and conducting
LOTS operations. (See TM 3-34.73.) U.S. Army equipment includes self-deploying watercraft, lighterage,
modular causeway systems, logistics support vessels, landing crafts, causeway ferries, floating piers,
Trident piers, small tugs, and barge derricks. (See JP 4-01.2.) The unit coordinates operational activities
with the completion of necessary projects and provides liaison with the U.S. Navy and U.S. Coast Guard.
5-21. The transportation unit also conducts a continuous study of port facility requirements to ensure the
smooth and orderly flow of personnel, supplies, and material through the port. The unit staff plans,
supervises, and controls freight movement from the port by rail, motor, inland water transportation and,
under special conditions, air transport.
5-22. Finally, the transportation unit is responsible for establishing engineer port construction priorities and
terminal operations. Transportation units have the capability of providing personnel and haul assets for the
movement of mass volumes of supplies and material. (See FM 4-01 for specific details on transportation
unit equipment and capabilities.)
QUARTERMASTER UNITS
5-23. U.S. Army quartermaster units are responsible for supplying potable water and operating petroleum
pipeline systems, including off-vessel discharging and loading. Their capabilities include providing
terminal service unit handling equipment, shore-based water storage systems, and inland petroleum
distribution systems. (See JP 4-01.2.)
5-24. Quartermaster units coordinate with naval units, engineer units, and transportation units in
determining the location of tanker unloading and vessel fueling facilities. Quartermaster units have the
capability of providing personnel and equipment assets to support logistics operations and services. (See
TM 3-34.73.)
5-39. Geospatial products may assist before, during, and after seaport reconnaissance.
Notes.
1. See ATP 4-13 for information on a marine beach profile diagram on sea, shore, and beach
slope construction requirements.
6. See TM 3-34.73 and TM 3-34.83 for information on dive team support planning.
5-40. There a variety of designs for different types of port facilities and structures, which include wharfs
(floating and stationary), piers, causeways, breakwaters, seawalls, landing ramps, anchorages, mooring, and
support facilities.
Notes.
5-41. ATP 4-0.1 gives planning factors for approximate materials and man-hour requirements for the
overall planning and estimating of general and break-bulk cargo port construction. TM 5-301-2,
TM 5-301-4, and TM 5-303 provide information on design, material, and labor requirements for port
structures.
5-42. After the port has been occupied, planners must carefully and critically examine previous plans in
view of the physical condition and structural integrity of the port. Any major proposed changes impacting
logistics and scheduling must be coordinated through engineer, transportation, and command channels.
Priorities established in the OPORD may have to be modified after construction is started based on current
conditions and on-site information. Planning and scheduling are based on meeting all immediate needs,
while ensuring that all work contributes toward successful project completion.
5-43. Comparative studies are made to determine the relative value of rehabilitation of the existing port
versus new port construction. These studies compare the benefits to be gained from specific facilities
within a port to the construction effort required. Among other factors, the selection of the best ports for
further development is determined by the need for dispersion, location of logistics requirements, time and
effort required to move construction units, local availability of materials, and civilian labor.
5-44. The U.S. Army theater sustainment command estimates port capacity requirements. The engineer
usually makes an independent estimate of the port capacity under various alternative methods of
construction, repair, or rehabilitation. This procedure serves as an aid in determining the most
advantageous, relative priorities of engineer projects. The capacity estimates of the sustainment brigade or
theater opening element, however, must govern with respect to military loads. Several software packages
exist that are helpful in determining port capacity and expansion requirements. Consult the reachback
capabilities available through the USACE Reachback Operations Center for information on such software
packages.
5-45. On the basis of port capacity estimates, the engineer recommends schedules for construction,
rehabilitation, and maintenance of port cranes and facilities; road and railroad construction within the port
area; preparation of storage and marshaling areas; and others. Port openings may require combat or GE
support to conduct reconnaissance, clear debris or obstacles, and provide facilities.
WHARF FACILITIES
5-48. Port capacity estimates are based on the discharge rates of ships at the wharf or in the stream, which
are associated with ships at anchor in connection with a JLOTS. Priority is given to methods that allow
ships to be discharged more quickly. Construction is scheduled in coordination with transportation
operations so that construction activities interfere as little as possible with the discharge of ships.
ANCHORAGE
5-49. When sheltered anchorage is available, lighterage operations provide a means of discharging cargo
while deepwater wharves are under construction or repair. By conducting lighterage operations while
construction and rehabilitation work go forward, continued unloading is possible through the use of the
following alternatives:
The continuous dredging of the deepwater wharf approach channel by using a shallow-draft
approach and discharge outside dredging work areas.
The use of shallow-draft parts of the wharf systems while some of the deepwater wharves are
under construction.
The unloading of shallow-draft vessels over deep-draft wharves during construction.
LOGISTICS OVER-THE-SHORE
5-50. At least 90 percent of the tonnage required to support deployed forces in the AO must be provided by
sea LOCs. Although air LOCs usually carry high-priority shipments and personnel, sea LOCs will likely
bear the main burden due to greater carrying capacities of strategic sealift vessels. The uninterrupted
delivery of materiel requires that vulnerable fixed port facilities be backed up by a flexible system, and
LOTS operations provide that system. LOTS is the process of loading and unloading ships without the
benefit of deep draft-capable, fixed port facilities or as a means of moving forces closer to tactical assembly
areas. The scope of LOTS operations depends on geographic, tactical, and time considerations.
5-51. JLOTS operations include U.S. Marine Corps forces and occur when the U.S. Navy and U.S. Army
LOTS forces conduct LOTS together under a JFC. Armed forces LOTS operations involve transferring,
marshaling, and dispersing materiel from a marine system to a land transport system. The rule of thumb for
planners is that 40 percent of all cargo entering contingency theaters by surface means will need to be
delivered through LOTS terminals. In some theaters, this proportion may be much greater. Beaches that are
distant from fixed port facilities serve as LOTS sites. The rapid establishment of a viable LOTS system
depends on engineer construction and maintenance support. (See JP 4-01.6, NWP 4-0M/MCWP 4-2, and
NTTP 3-02.1M/MCWP 3-31.5.)
5-52. Initial LOTS planning and site selection are coordinated between the theater opening element or
sustainment brigade commander (Transportation Corps) and the U.S. Navy/Military Sealift Command. The
initial site selection is based on map studies, hydrographic charts, and aerial reconnaissance.
RESPONSIBILITIES
5-53. Proper logistics planning to support deployed forces on a foreign shore always begins with an
evaluation of in-place, fixed port facilities and capacities. These, combined with connecting railway,
highway, and inland waterway networks, are the major logistics systems required for military operations.
When a reckoning of available resources is complete, planners determine the need for LOTS terminals to
supplement and back up the transportation network. (See ATP 4-13 for information on LOTS layouts. See
ATP 4-13 and JP 4-01.6 for information on JLOTS.)
5-54. The overall responsibility for LOTS operations lies with the U.S. Army Transportation Corps for the
U.S. Army and with the U.S. Navy for the U.S. Marines Corps. Each LOTS terminal acts under the direct
control of a transportation terminal battalion that comprises two service companies and appropriate
lighterage units. The CCDR may assign construction responsibilities to U.S. Army, U.S. Navy, and/or U.S.
Marine Corps engineer units, depending on their availability and the overall situation. Mutually supporting
or follow-on construction must be coordinated with other engineer units assigned to or projected for the
AO.
5-55. U.S. Army engineers must be prepared to support the LOTS mission because—
Existing ports may be damaged, incomplete, or unavailable.
Existing ports may be unable to handle resupply operations.
Existing port facilities are vulnerable to enemy activities, such as mining, CBRN, or air
interdiction.
Ports under repair may be unavailable for long periods.
5-56. Engineer units give construction, repair, and maintenance support to LOTS operations. An engineer
unit may expect the following missions when supporting a JLOTS operation:
Construct semipermanent piers and causeways.
Prepare and stabilize beaches.
Construct access and egress routes from beaches to backwater areas.
Construct access routes to marshaling areas and/or adjoining LOTS sites.
Construct marshaling and storage areas.
Construct road and railroad links to existing LOCs.
Construct utility systems.
Construct petroleum, oils, and lubricant storage and distribution systems.
Construct container collection sites.
Provide other assistance or maintenance determined by the terminal commander.
RECONNAISSANCE
5-57. The reconnaissance party includes representatives of the terminal group commander, the terminal
battalion command, the supporting engineer, the supporting signal officer, military police, U.S. Navy
personnel to provide advice on mooring areas, and a U.S. Army engineer dive team to conduct a detailed
hydrographic survey of the site. Hydrographic surveys provide a depiction of underwater bottom profiles of
an operational shoreline or port area. Such a survey can provide accurate water depths, bottom depth
gradients, ship channels, and the location and type of underwater obstructions or other hazards that may
impede vessel traffic. Others participate if the situation dictates or at the terminal commander’s request.
The reconnaissance party briefs the terminal commander on its findings. The briefing must cover the—
Engineer effort required to prepare and maintain the site, based on available units, equipment,
and materials.
Signal construction and maintenance required for necessary communications within the beach
area and between the beach and the terminal group headquarters.
Types of lighterage craft that may be used, based on beach conditions.
Safe haven for lighterage craft in stormy weather.
Location and desirability of mooring areas.
Adequate egress from the beach. This and the beach dimensions are key factors in determining
tonnage capacity for the beach.
Intensity of wave action and tidal range.
Climatic and weather conditions.
5-58. The supporting engineer must be informed about the layout of the LOTS site and should be involved
early in staff planning and coordinating because the layout determines the required engineer effort. A
LOTS layout varies with the situation and existing geographic conditions. The physical size of the
individual site depends on security considerations, soil trafficability, the number of ships to be unloaded at
the site, and the type of cargo coming ashore. For example, a LOTS terminal may need to be very large if
ammunition and/or petroleum, oils, and lubricants are being unloaded over a beach that is subject to enemy
attack. General cargo unloaded over a secure beach requires less area. (See ATP 4-13 for information on
layout figures.)
CONSTRUCTION
5-60. As discussed in other instances of construction in this publication, many construction practices apply
to, and remain constant for, seaports. Special consideration for seaport construction is discussed in the
following paragraphs.
PHASED CONSTRUCTION
5-61. Current procedures for port construction in undeveloped areas usually fall under the following
phases:
Phase One, Preliminary. This phase includes all requirements from the arrival of construction
units to the beginning of construction of deep-draft wharves. The LOTS operations are
conducted during this phase.
Phase Two, Initial Construction. This phase continues to the point at which the first cargo ship
berth is fully operational, including road and railroad connection; water supply and electrical
services; and bulk petroleum, oils, and lubricant handling facilities that can receive liquid fuels
directly from oceangoing tankers.
Phase Three, Completion. This phase ends when construction is complete and authorized
facilities are fully operational.
PORT CONSTRUCTION
5-62. Commercial records indicate that at least 9 months are required for a skilled construction crew of 30
to construct a modern (approximately 80 by 1,000 feet) steel or concrete pile wharf by conventional
(cast-in-place and/or on-site job erection) methods. This time requirement, even allowing for larger
construction crews, is excessive for current military operations and indicates that neither steel nor concrete
pile wharves will likely be built by military units using conventional methods in the future. Recent studies
indicate that although steel and concrete are the most common building materials used in new military port
construction, their use is limited to new, unconventional construction and lower cost methods. (See
TM 3-34.73 for additional information.)
SUPPORT FACILITIES
5-66. A large amount of construction effort goes into building port support facilities. If a port is located in
an area where an adequate railway or roadway network exists, then cargo-handling operations will be more
efficient when there are like connectors on the wharves. Engineer units are responsible for the construction
of railway and roadway facilities required by the port. Plans are staffed and coordinated with
Transportation Corps requirements.
5-67. Designs currently being recommended to the U.S. Army for future expedient military container port
construction include the use of tractor-trailers to transport individual International Standards Organization
shipping containers from the wharves. The wharf must be of sufficient load-bearing strength (capable of
supporting up to 1,000 pounds per square foot of live loads) and width (usually 80 to 100 feet) to
accommodate fully loaded tractor-trailers. They must be constructed in such a manner as to avoid excessive
breakover, approach, and departure angles and allow suitable gradients for connections to existing or
planned roadway networks. (See ATP 4-12 for additional information on U.S. Army container operations.)
5-68. Other on-shore construction requirements include—
Potable and nonpotable water supply for the port and ships docked or moored in the port.
Electric power systems, which may require overhead and underground systems.
Firefighting facilities and special systems as needed, such as special facilities for petroleum, oils,
and lubricant terminals.
5-69. Suitable water depths must be maintained at ports to accommodate deep-draft sea vessel
maneuvering requirements. According to TM 3-34.73, the normal draft for a container ship is 40 feet. Daily
tidal ranges can exceed 20 feet and, therefore, must be taken into consideration when determining
acceptable channel and pier side depths. A minimum low-tide water depth of about 35 feet should be used
for planning purposes, because it will accommodate most deep-draft vessels. Current commercial
container-shipping capacity requires port depths of at least 40 feet. The planned construction of wharves in
shallow water may also be justified where—
It is established that the required depth can be obtained by dredging, that such dredging is
practical as part of the construction project, and that dredging can be performed without
endangering the in-place wharf structure.
Short-term use is anticipated, thus making the use of lighterage a more feasible option than
dredging or wharf relocation.
5-70. Minimum water depths for new wharf construction are dictated by the intended use of the wharf
(petroleum, oils, and lubricant wharf; container wharf; and lighter wharf), the type of wharf, and the size of
the sea vessels to be accommodated. These depths are determined well in advance and are given in the
operations order and/or construction directive.
5-71. Dredging may be necessary to establish and maintain required depths. Experience gained during
World War II and the Vietnam War indicates that there are a number of specific problems associated with
dredging projects in an AO. Hopper dredges and side-casting dredges are the only ones that are seagoing.
The transportation of other types of dredges to the AO can be difficult, and they must be towed to the site
or assembled from components transported aboard cargo ships.
5-72. It may also be difficult to provide adequate security for dredges within a combat zone or wartime
TO. The routine patterns followed by dredges greatly limit the effectiveness of any passive defense
measures. Pipeline dredges are virtually stationary targets. The availability of dredges and crews for use in
the early stages of deployment in an AO can also be a major problem. The U.S. Army has no trained
military dredge crews or portable dredges that are suitable for use in an AO. USACE does possess dredges
and trained crews, but the availability of these is not certain and must be planned for and requested well in
advance.
5-73. Sweeping, covered in detail in TM 3-34.55, is a method of locating pinnacles or other obstructions
that limit the accessibility of some ships to use the area. Sweeping is always used as a final check after
dredging operations. When feasible, obstructions may be partially removed by explosives or other methods
to allow unfettered access. If a sufficient operating area with adequate water depths is available, hazards
may be properly marked with the appropriate use of lights and other signals placed on or near structures,
sunken vessels, and other obstructions for the protection of navigation.
ROAD CONSTRUCTION
5-77. Seaport road construction supports the LOTS site layout, road network within the port, and roads
connecting the port to the transportation network. The major engineer effort in LOTS is invested in road
construction and maintenance. Considerable effort must be spent to adequately stabilize soil conditions to
ensure a suitable foundation and improve trafficability in the beach area. Constructed roads must withstand
the large volume and impact of material-handling equipment carrying extremely heavy loads. Roads that
support LOTS are usually constructed in a loop to reduce their required width, eliminate vehicle turning as
much as possible, and prevent vehicle backups.
MAINTENANCE
5-79. Routine maintenance is essential to allow the port to continue its functionality and good service.
Inspections are scheduled to review maintenance service records and conduct physical inspections of port
infrastructure and individual facilities. This includes underwater inspections and assessments of port
facilities with the use of dive teams. Based on the inspections, repairs are scheduled and repair
parts/materials are ordered.
EMERGENCY REPAIR
5-80. Emergency repair is immediate work required to repair storm, accident, or other damage to prevent
additional losses and larger repairs. Emergency repairs include—
Repairs to breached breakwaters to prevent further damage to harbor installations.
Repairs of wharf damage caused by ships, storms, or enemy action to restore structural strength.
Adding rock to control foundation scour or breach erosion.
MAJOR REPAIR
5-81. Major repair is required when there is significant damage to the port facilities that requires
replacement work or rebuilding. This includes—
Replacing wharf decks.
Resurfacing access roads and earth-filled quays.
Replacing wharf bracings and anchorages that have been destroyed by decay or erosion.
Replacing entire spud barge pier, spud, or other major barge pier accessories.
EXPEDIENT REPAIR
5-82. The use of expedient repair methods should be encouraged during limited port operations while
major repair and rehabilitation go forward. (See TM 3-34.73.)
5-83. Possible measures to speed repairs are as follows:
Use launches or tugboats with a line to the shore for various hauling and hoisting functions in
construction work at the waterfront.
Erect a derrick or install a crawler or truck-mounted crane on a regular barge; a mechanized
landing craft; a barge of pontoon cubes; or a barge fabricated for military floating bridge units.
Fabricate rafts for pile bent bracing operations from oil drums, heavy timbers, spare piles, or
local material.
Improvise floating dry docks for small craft from U.S. Navy pontoons.
Improvise light barges, floating wharf approaches, and small floating wharves from steel oil
drums.
Lay diagonal flooring over existing decking to strengthen a structure by distributing the load
over more stringers.
Remove the decking to add stringers, or place smaller stringers on the pile cap between existing
stringers from beneath the decking and wedged tight against the deck.
Drive the piles through the hole, move several floor planks, and then cap new pile bents and
wedge them tight against the stringers. (This can only be done if the wharf can support the
weight of the pile driver.)
Use a rock- or ballast-filled timber crib to replace a gap in a pile wharf structure or to extend the
offshore end on the wharf. The timber crib may be built on land, launched by using log rollers,
floated into position, and filled with rock or ballast to hold it in place.
Use standard military floating bridges or U.S. Navy pontoons to supplement or temporarily
replace damaged causeways.
Use standard military floating bridges or U.S. Navy pontoons to provide access between
undamaged sections of off-loading piers.
Restore the face of the wharf first if a section of a wharf has been destroyed so that ships may be
worked while the area behind the face is being restored.
Use the shore end of a pier for lighters or other short vessels while the pier is being extended.
Use standard or nonstandard fixed bridging to bridge part of a solid-fill wharf. (See
TM 3-34.22/MCRP 3-17.1B, Military Nonstandard Fixed Bridging.)
Use camels, barges, or other devices to block slips that are filled with rubble. This prevents ships
from being brought to the face of the wharf and allows them to be retained in deep water for
unloading. Alternatively, it may be possible to use standard trestles, fixed bridging, and
assembled U.S. Navy pontoons to extend the width of the pier.
Use the hull of a capsized or sunken vessel as the substructure for a pier.
Anchor the shore end of a causeway constructed from U.S. Navy pontoon cubes onshore by
excavating a section of beach, floating the pontoons into the temporary inlet thus made, and then
backfilling to provide a solid anchorage.
Use field-expedient matting.
MARSHALING AREAS
5-85. Marshaling areas serve as centralized collection points where unloaded materials and equipment can
be temporarily stored while awaiting distribution to the proper units. The size of the marshaling area varies
with the size and type of shipping, the unloading rate, the exposure to hostilities, and the units being
supported. Marshaling areas are tailored to specific operations and can need as much as 500 acres for large-
scale operations. (See ATP 4-13 for layout information.)
5-86. In hostile environments, marshaling areas are dispersed, with acreage divided into many small
parcels. Other protection considerations must be integrated into the design of marshaling areas as well. (See
ATP 4-13 for specific details on planning, constructing, organizing, managing, and maintaining marshaling
areas.)
5-87. Marshaling area surfaces and foundations must be sufficiently stable to support a fully loaded piece
of material-handling equipment that weighs up to 100,000 pounds. Access and egress roads must be
capable of supporting the same loads. The surface must be protected with adequate drainage.
5-88. International Standards Organization container collection areas must be planned and provided. These
areas must have the same trafficability, drainage, and access/egress characteristics as the marshaling areas
and can require nearly as much space. Most material shipped to a JOA via surface transportation is
containerized. Once ashore, the containers are opened and unpacked for distribution to the intended units.
Empty containers are collected and reloaded aboard ships and then returned to their point of origin. (See
ATP 4-12 and JP 4-09 for information on container requirements, operations, and management.)
rapid runway repair; and build, improve, and sustain expeditionary airfields. (See NWP 4.04 for additional
information.)
SERVICE RESPONSIBILITY
6-10. The branch of Service that is the primary user of the airfield or heliport has the responsibility for
certifying that facility for flight operations. In most cases during airfield contingency operations, this is a
U.S. Air Force responsibility. U.S. Air Force engineers may assist U.S. Army engineers, U.S. Navy
Seabees, or Marine engineers, as directed, in airfield and heliport planning, design, construction, repair, and
maintenance. (See Air Force Doctrine Annex 3-34.)
6-11. The U.S. Air Force provides the following engineer support:
Performs the primary emergency repair of war damage to air bases and other ADR tasks.
Constructs expedient facilities for U.S. Air Force units and weapon systems. (This excludes the
responsibility for U.S. Army base development.)
Operates and maintains U.S. Air Force facilities.
Performs maintenance tasks.
Provides crash rescue and fire suppression.
Provides hazmat response.
Manages the emergency repair of war damage and force bed-down construction.
Provides infrastructure support for the disposal of solid and hazardous waste.
Supplies resources for its own engineering mission.
Provides the EBS and EHSA for the airfield and its support facilities.
AIRFIELD PLANNING
6-13. Engineers are responsible for airfield planning. This includes conducting site reconnaissance, making
recommendations, designing the airfield or heliport, and conducting the actual construction of the
individual airfield. Airfield and heliport planning and design include the runway or helipad and the
supporting facilities. The planning and design may include conceptual planning to support aircraft bed-
down, evaluation to rehabilitate or upgrade existing facilities, site adaption of existing standard designs,
preliminary plans and designs, detailed plans and designs, and project management planning. Key planning
actions include site selection, designation of controlling aircraft, construction standards (airfield and
support facilities), and estimation of required construction effort.
6-14. Airfield designs may be provided by one of the Services obtained from the TCMS or UFC 3-260-01;
developed by engineers using manual procedures discussed in FM 5-430-00-1/AFJPAM 32-8013, Volume
I; or developed by engineers using computer-aided processes. The TCMS provides information on how to
obtain detailed standard designs for the airfield type and capacity. However, the planner may need to alter
and adapt the designs to meet time and material restrictions or the limitations imposed by local topography,
area, or obstruction characteristics. Engineers may alter designs, but must obtain approval from the user for
major changes before starting work.
6-15. Early in the planning process, operations, logistics, and engineer planners should identify potential
forward airfields to support offensive air operations and logistics buildup and outline the engineer tasks
required to open the airfields. It is critical that joint engineers ensure early and effective coordination
between airfield planners and the commands that will operate aircraft at the airfields. Many of the decisions
made early in the planning process can have a critical impact on an airfield utility for aircraft operations.
(See JP 3-34.)
6-16. Most planning factors for road designs are also applicable for airfields. The most important factors
for engineer planners include—
Mission. To achieve a proper airfield design mission, it is essential to have a complete
understanding of the number and type of aircraft and the purpose, scope, and estimated number
of the particular air missions to be flown by the design-controlling aircraft. The design criteria
are based on the usage by a specific aircraft in relative location to the battlefield. The most
demanding characteristics of the using aircraft establish the controlling aircraft. Categories of
aircraft missions that may be conducted include reconnaissance, cargo transport, or attack.
Enemy. Devise an adequate plan to ensure that construction troops can protect themselves,
equipment, and materials against harassment and sabotage during airfield or heliport
construction. Consider requirements for additional security forces.
Terrain and weather. Within mission and operational requirements, establish reasonable site
requirements for each airfield type. Choose geographic locations based on topographic features
(grading, drainage, and hydrology), soils, vegetation, utilities, climatic conditions, and
accessibility of materials. Accurate airfield design requires a topographic survey with minimum
5-foot contour intervals. Other site characteristics to be studied include forecasted weather
effects (such as temperature, barometric pressure, precipitation, seasonal weather variations, and
wind speed and direction) and flight path obstacles. Evaluate all existing transport facilities to
determine the best methods and routes to logistically support the project. These include ports,
rail lines, road nets, and other nearby airfields that might be used for assembling construction
equipment and materials and moving them to the construction site.
Troops and support available. Evaluate the availability and type of engineer construction
forces to determine if construction capability is sufficient to carry out the required airfield
construction. Weigh the type and availability of local construction materials against the overall
needs for proposed construction. Consider examining naturally occurring materials and other
possible sources of materials for subgrade strengthening. Requirements for importing special
materials for surfacing, drainage, and dust control must be feasible for available construction
time and resources. Have a working knowledge of forces dedicated to ADR. Depending on the
base location, local agreements, and the overall military situation, any combination of U.S.
Army, U.S. Air Force, HN, or contract engineer support may be possible. Consider time-phased
force and deployment data or population flow into the airfield when developing the airfield
master plan.
Time available. Operational and mission requirements will dictate when the airfields are needed
to support aircraft operations.
Civil considerations. Consider what civilian construction resources are available in the local
area and what structures already exist that could be used to support airfield construction, repair,
and maintenance. Consider the environmental impact, restricted areas, political and cultural
factors, and other factors that could impact airfield layout and construction.
MOG. MOG is the maximum number of aircraft that can be accommodated on an airfield. MOG
is normally expressed in terms of C-141s. A minimum of MOG 2 is desired for contingency
operations airfields. (Refer to AFPAM 10-1403 for aircraft dimensions.) There are two types of
MOG:
Parking MOG is the total number of aircraft that can be parked at an airfield. Parking MOG
is affected by the overall size of the airfield and by how available space is managed.
Working MOG refers to how many parked aircraft can be off-loaded, how much material
can be through-putted from the aerial port of debarkation, and how many aircraft can be
serviced and prepared for departure. It also refers to how quickly these can be
accomplished. Factors affecting the working MOG include material-handling equipment,
trucks, busses, other surface transport vehicles, road networks, aircraft support equipment,
fuel tankers, and personnel. Ideally, working MOG equals parking MOG; when it does not,
backlogs occur.
Airfield Reconnaissance
6-17. Airfield reconnaissance differs from road reconnaissance in that more comprehensive information is
typically required. An airfield project involves more effort in man-hours, machine-hours, and material than
road projects. Air traffic also imposes stricter requirements on traffic facilities than does vehicular traffic.
Consequently, the site selected has to be the best available.
6-18. When new construction is undertaken, the planner and the reconnaissance team must choose a site
with soil characteristics that meet strength and stability requirements or a site that requires minimum
construction effort to attain those standards. Airfields present more drainage problems than roads. Their
wide, paved areas demand that water be diverted completely around the field or that long drainage
structures be built. Sites at the low point of valleys or other depressed areas should be avoided because they
tend to be focal points for water collection. As in road construction, subsurface water should be avoided. A
desirable airfield site lies across a long, gentle slope, because it is relatively easy to divert water around the
finished installation. (See TM 5-820-1/AFM 88-5 for information on drainage and erosion control for
airfields and heliports.)
6-19. Airfield reconnaissance must consider the quality and quantity of land available. To accommodate
missions efficiently, airfields require large areas of relatively flat land. Advance location and layout
planning will avoid the overcrowding of facilities. To obtain the required area, the airfield may have to be
spread over a large area. This may call for a complex network of taxiways and service roads. Runways
should be aligned in the direction of the prevailing wind.
6-20. Airfield reconnaissance must consider elevation and the obstacles obstructing aircraft approaches.
The safe operation of fixed- or rotary-wing aircraft requires that all obstacles above elevations specified by
design criteria be removed. These criteria vary according to the operating characteristics of the aircraft that
use the airfield. For example, most heliports require an approach zone with a 10:1 glide angle, whereas
heavy cargo aircraft in the rear area require a glide angle as flat as 50:1. To achieve the right glide angle, it
is often necessary to remove hills and do major earthwork on distant approaches to the airfield proper. The
reconnaissance team should avoid locations requiring extensive earthwork to achieve the necessary glide
angle. Clearances are also required along the sides of runways, taxiways, and parking aprons. An area of
specified width must be cleared of all obstacles and graded according to specifications.
Note. See FM 5-430-00-2/AFJPAM 32-8013, Volume II, for additional information on the types
of airfields and heliports.
6-22. Classifying runways in terms of their length is still common among military planners. Typical
runway lengths are 2,000, 2,500, 3,000, 3,500, 6,000, and 10,000 feet. A controlling aircraft or combination
of controlling aircraft has been designated for each category to establish limiting airfield geometric and
surface strength requirements. Pavement structures are classified as rigid (Portland cement) or flexible
(surfaced or unsurfaced). Runways are classified as follows:
Class A runways are primarily intended for small, light aircraft. These runways do not have the
potential of foreseeable requirement for development for use by high-performance and large,
heavy aircraft. (See UFC 3-260-01.)
Class B runways are primarily intended for high-performance and large, heavy aircraft.
(See UFC 3-260-01.)
6-23. U.S. Army airfields and heliports are divided into six classes:
Class I. Helipads and heliports (Type B) with aircraft 25,000 pounds (11,340 kilograms) or less.
The controlling aircraft is a UH-60 aircraft at a 16,300-pound (7,395-kilogram) operational
weight.
Class II. Helipads and heliports (Type B) with aircraft over 25,000 pounds (11,340 kilograms).
The controlling aircraft is a CH-47 aircraft at a 50,000-pound (22,680-kilogram) operational
weight.
Class III. Airfields with three traffic areas (Type A, B, and C). The controlling aircraft
combination is a C-23 aircraft at a 24,600-pound (11,200-kilogram) operational weight and a
CH-47 aircraft at a 50,000-pound (22,680-kilogram) operational weight. Class A runways are
primarily intended for small aircraft, such as C-12s and C-23s.
Class IV. Airfields with Class B runways. The controlling aircraft is a C-130 aircraft at a
155,000-pound (70,310-kilogram) operational weight or a C-17 aircraft at a 580,000-pound
(263,100-kilogram) operational weight. Class B runways are primarily intended for high-
performance and large, heavy aircraft, such as C-130s, C-17s, and C-141s.
Class V. Contingency (TO) heliports or helipads (Type B) contingency (TO) supporting U.S.
Army assault training missions. The controlling aircraft is the CH-47 aircraft at a 50,000-pound
(22,680-kilogram) operational weight.
Class VI. Assault landing zones for contingency (TO) airfields or airstrips (Type A) supporting
U.S. Army missions that have semiprepared or paved surfaces. The controlling aircraft is the
C-130 aircraft at a 155,000-pound (70,310-kilogram) operational weight or the C-17 aircraft at a
580,000-pound (263,100-kilogram) operational weight.
Note. See UFC 3-260-02 for additional information on the classes of airfields and heliports.
6-24. U.S. Air Force airfields are classified into one of six types based on their airfield mission and
operational procedures. A controlling aircraft or combination of controlling aircraft has been designated for
each type to establish limiting airfield geometric and surface strength requirements. These airfield types
include—
Light—F-15 and C-17.
Medium—F-15, C-17, and B-52.
Heavy—F-15, C-5, and B-52.
Modified Heavy—F-15, C-17, and B-1.
Auxiliary—F-15.
Assault Landing Zone—C-130 and C-17.
6-25. A bare-base airfield has the minimum essentials to house, sustain, and support operations, to include,
if required, a stabilized runway, taxiways, and aircraft parking areas. A bare base must have a source of
water that can be made potable. Other requirements to operate under bare-base conditions form a necessary
part of the force package deployed to the bare base. (See Air Force Doctrine Annex 3-34 and JP 3-05.)
6-26. The airfield must be capable of supporting assigned aircraft and providing other mission-essential
resources, such as a logistics support and services infrastructure composed of people, facilities, equipment,
and supplies. This concept requires modular, mobile facilities; utilities; and support equipment packages
that can be rapidly deployed and installed. A bare-base airfield forms the baseline for contingency
operations airfield planning. (See FM 5-430-00-1/AFJPAM 32-8013, Volume I for additional information.)
6-27. Preplanned design layouts within TCMS for each type of field are based on the assumption that
previously unoccupied sites will be chosen. However, the layouts have been coordinated so that, within
terrain limitations, it is practicable to develop a larger field from a smaller one with minimal construction
effort. An existing airfield or a bare-base site can be used if it meets minimum requirements or can be
upgraded to meet operational or mission requirements.
6-28. The U.S. Air Force issues Engineering Technical Letters to provide engineers with criteria and
guidance for the design, construction, maintenance, and evaluation of airfields and other support facilities.
Many Engineering Technical Letters have been revised and converted into Unified Facilities Criteria. ETLs
are available at the Whole Building Design Guide ETL Web site.
AIRFIELD DESIGN
6-29. There are a variety of airfield designs that must be considered by the engineer. There are design
processes and steps that can be applied. These airfield designs include geometric, pavement, drainage,
support facility, protection, and special.
6-30. Airfield design steps include the following:
Select the runway location.
Determine the runway length and width.
Calculate approach zones.
Determine the runway orientation based on the wind rose, which statistically quantifies
prevailing winds.
Plot the centerline on graph paper, design the vertical alignment, and plot the newly designed
airfield on the plan and profile.
Design the transverse slopes.
Design taxiways and aprons.
Select visual and nonvisual aids to navigation.
Design logistics support facilities.
Design aircraft protection facilities.
Geometric Design
6-31. Airfield geometric design consists of meeting the minimum geometric requirements for the elements
that compose the airfield—runway, overrun, taxiway, apron, shoulders, graded area, transitional area,
runway end clear zone, turnarounds (hammer heads), imaginary surfaces (approach-departure clearance
surface), and accident potential zones.
Notes.
2. See UFC 3-260-01 for information on C-130 and C-17 airfield dimensional criteria.
6-34. There are four types of airfield pavement system surface structures above the subgrade. They are—
Notes.
2. See ETL 97-9 and UFC 3-260-02 for information on the strength and thickness of pavement
and structural evaluation criteria of semiprepared and matted airfields for the C-17.
6-36. There are several types of bituminous pavement; however, flexible-pavement airfields usually have
an asphalt concrete wear surface. The frost filter layer to prevent pavement heaving and thermal cracks is
more common in airfield construction than in roads.
Notes.
1. See TM 3-34.63 and UFC 3-260-02 for a discussion on the design of pavements for frost
action.
6-39. The design of support facilities should be based on the number and type of other organizations
collocated on, or supported by the airfield. The base camp technique of using a design population can help
properly design the airfield support facilities and services. Considerations for airfield or heliport
development, master planning, facility siting, and layout planning include—
Airfield location.
Functional effectiveness and efficiency, sustainability, resiliency, security, expandability, and
ease of construction.
Layout space for land use functions and relationships, facilities, separation distances, accesses,
protection methods, and expansion procedures.
Adequate drainage.
Environmental considerations.
Protection Design
6-41. The planning and design of protective measures and structures on airfields and heliports are based on
the evaluation of the threat.
Notes.
2. See ADRP 3-37 and ATP 3-39.32 for information on force protection measures.
4. See AFMAN 91-201 for information on U.S. Air Force aircraft survivability.
Special Designs
6-42. Special airfields include—
Drop zones.
Extraction zones.
Special operations forces airfields.
Blacked-out airfields.
Airfields for unmanned aircraft systems.
6-43. New construction for some unmanned aircraft systems should only be required when they are
operated from a location without a paved road or an existing runway. To support mobile, unmanned aircraft
system operations, most unmanned aircraft system airfields are constructed with matting. Unmanned
aircraft system operators must provide runway design criteria for systems that do not have standard designs
already developed. (See ETL 09-1 and UFC 3-260-01 for additional information.)
6-44. It may be required to build airfields and heliports in arctic and subarctic conditions. (See TM 5-852-
1/AFR 88-19, Volume 1; TM 5-852-2/AFR 88-19, Volume 2; TM 5-852-4/AFM 88-19, chapter 4; TM 5-
852-5/AFR 88-19, Volume 5; TM 5-852-6/AFR 88-19, Volume 6; and TM 5-852-3 for more information.)
HELIPORTS
6-45. There are four levels of heliport development: landing zones of opportunity, austere forward area
fields, substandard but operational support area fields, and deliberate rear area fields. (See FM 5-430-00-
2/AFJPAM 32-8013, Volume II.) The geometric design requirements for helicopter landing areas can be
simplified into four types:
Helipads.
Heliports with taxi hover lanes.
Heliports with runways.
Mixed battalion heliports.
6-46. The design of a pavement structure for a heliport or helipad is similar to the pavement structure
design for airfields. The three types of heliport and helipad pavement structures include—
Unsurfaced.
Surfaced (membrane-surfaced or mat-surfaced design).
Flexible pavement (thickness design procedure).
6-47. For additional airfield and heliport planning and design information, see the following sources:
AFCS (TCMS).
ATTP 3-90.4/MCWP 3-17.8.
FM 5-430-00-1/AFJPAM 32-8013, Volume I.
FM 5-430-00-2/AFJPAM 32-8013, Volume II.
UFC 3-260-01.
UFC 3-260-02.
UFC 3-260-17.
UFC 4-141-10N.
CONSTRUCTION
6-49. FM 5-430-00-1/AFJPAM 32-8013, Volume I, provides a complete discussion of airfield and heliport
construction. The construction directive usually provides the airfield and heliport geometric design,
pavement structure design, and drainage system design. The constructing unit may site-adapt the designs to
local conditions. Airfield and heliport construction planning tasks to determine earthwork quantities,
material, equipment, personnel, quality control, and environmental requirements are similar to those for
roads and railroads.
CONSTRUCTION ESTIMATES
6-50. Developing an accurate construction estimate can be difficult, as each project must be considered on
a case-by-case basis. A reasonable estimate of construction effort and time required can be made after
thorough research and planning. Engineers estimate the construction of airfields and heliports based on the
following key factors:
Volume of earthwork required.
Difficulties of grading and constructing.
Drainage required.
Site clearance required.
Previous construction experience.
Capability of the engineer unit assigned.
6-51. Construction may involve new construction or the restoration or upgrade of existing airfields or
heliports simultaneously. A complete air base is a complex construction project. However, careful project
planning, a strict focus on essentials, and phased construction can result in a facility that will support air
operations soon after construction begins. Subsequent improvements and modifications can be made during
use. If construction is guided by a master plan, the staged completion of each structure can be designed to
serve the expedient operation and meet the criteria for the final design plan.
6-52. It is best to complete an air base to its ultimate design in a single construction program. It may be
necessary to initially design it to a lower construction standard to expedite getting the base into operation
within the available time with the available construction support. In such cases, every effort must be made
to proceed to the ultimate design standard for the airfield. The repeated modification of a facility plan is to
be avoided.
Stage II. Construct a new runway. The Stage I runway now becomes a taxiway; and aprons,
hardstands, and additional taxiways are built.
Stage III. Further expand facilities to accommodate additional aircraft as needed. If an existing
surface in the rear area is inadequate for all-weather operations in support of heavy transport
aircraft or high-performance fighter aircraft, an appropriate pavement structure is designed and
constructed.
PRINCIPLES
6-56. Except for staking requirements, the techniques and principles for conducting airfield and heliport
construction surveys are identical to those for roads. An accurate estimate of earthwork volume is essential
to the proper control and management of a horizontal construction project. Following mass diagram
construction and analysis, equipment is scheduled and project durations are determined. An analysis of the
mass diagram will also determine haul routes, locations of equipment work zones, and areas for waste and
borrow sites.
6-57. Earthwork balancing may also occur between adjacent projects (runway and taxiway, for example).
The constructing unit selects materials that meet design specifications from soils in cuts, borrow pits,
quarries, or local procurement.
6-58. During construction, permanent drainage structures are essential to the successful completion of an
airfield or heliport. Planning considerations are similar to those used for road construction.
PAVEMENT
6-59. The decision to pave an airfield or heliport during contingency operations is based on the urgency to
complete the airfield, the tactical situation, the amount and type of anticipated traffic, the soil-bearing
characteristics, the climate, and the materials and equipment of availability. Surfacing must meet the
allowable roughness criteria for each type of aircraft that will use the facility. Soil stabilization operations
improve strength, control dust, and render surfaces waterproof. The process is discussed in TM 5-822-
14/AFJMAN 32-1019.
EXISTING FACILITIES
6-60. Maximize the use of existing facilities if they meet the minimum design requirements or can be
economically upgraded to meet requirements. Existing airfields and heliports may need an additional
pavement layer (airfield pavement upgrade). There may be requirements to construct or expand an existing
airfield structure (geometric upgrade) or support extensive new support facility construction. Consider the
expansion and rehabilitation of existing infrastructure over new construction. There is generally a
substantial savings in time, effort, and materials to upgrade rather than to build from scratch. Except in
highly developed areas, existing airfields are seldom adequate to handle modern, high-performance aircraft.
6-61. The evaluation of existing airfield pavements is generally a reverse of the design process. The
existing airfield evaluation technical details are fully discussed in FM 5-430-00-1/AFJPAM 32-8013,
Volume I, and UFC 3-260-03. Consider the following general guidelines:
Determine the airfield physical characteristics.
Determine if the design aircraft can operate from the existing field, based on its minimum
geometric requirements.
Determine the allowable number of passes, based on the evaluation of the existing airfield in-
place soil strength and pavements structure.
Outline corrective actions to meet minimum geometric requirements or increase the allowable
number of passes.
6-62. Existing airfield dimensions and pavement structures must be evaluated by the reconnaissance team,
based on mission and operational requirements to determine if the airfield can support air traffic. They also
determine the construction effort required. Some airfields can be made adequate with minimal effort. They
may also serve as the nucleus for larger fields that meet the specifications of high-performance aircraft.
6-63. Helicopters and light planes can often use existing roads, pastures, and athletic fields. Combat
engineers can upgrade these for initial or temporary use through forward aviation combat engineering.
Support facilities are converted to standards per the theater construction policy. The imaginative use of
existing facilities is preferable to new construction. The ground reconnaissance of an airfield previously
occupied by enemy forces must be cautious, since facilities may contain explosive hazards. Coordinate
facility use with HN authorities because existing airfields, particularly in the rear area, may be needed by
HN air forces or for commercial purposes.
OTHER CONSIDERATIONS
6-64. Expedient surfaces include matting and membranes. Matting gives the U.S. Army and Marines the
capability to build a runway quickly with minimum effort. Membranes provide airfield surfacing (but no
structural strength), dustproofing, and waterproofing. (See ATTP 3-90.4/MCWP 3-17.8 and FM 5-430-00-
1/AFJPAM 32-8013, Volume I.)
6-65. Upon airfield construction completion, the airfield manager or other individual authorized to monitor
and control on-site aircraft operations certifies the airfield and issues a notice to Airmen to change the
airfield status.
MAINTENANCE
6-67. Airfield maintenance is the routine prevention and correction of damage and deterioration caused by
normal use, wear and tear caused by aircraft, and exposure to the elements. Routine maintenance includes
inspections; stockpiled materials for repair and maintenance work; maintenance and repair of pavement
surfaces and drainage systems; dust control; and snow, ice, and foreign object damage repair. Foreign
object damage removal is generally accomplished using motorized sweepers. The user of the airfield
coordinates with engineers, who are responsible for airfield maintenance, to conduct routine foreign object
damage inspections.
6-68. The procedures and considerations for airfield maintenance are similar to those for road maintenance
and repair. The materials used for airfield maintenance are generally the same as those used for airfield
construction and repair. (See FM 5-430-00-1/AFJPAM 32-8013, Volume I; UFC 3-270-01; UFC 3-270-02;
UFC 3-270-03; UFC 3-270-04; and UFC 3-270-08 for additional information.)
6-69. Upon completion of an airfield repair or maintenance mission, crater repair evaluations must be
conducted before resuming aircraft operations. When conducting repair evaluations, consider the following:
Repair compaction. Verify the strength of the backfill, debris, or subgrade materials.
Depending on the repair method used, verify the thickness and strength of all surface and base
course materials. Test the soil structure using a dynamic cone penetrometer to determine the
California bearing ratio of each layer. Conduct these tests before placing foreign object damage
covers, AM-2 matting, stone and grout, asphalt, concrete, or other surface materials that would
prevent the use of the dynamic cone penetrometer.
Surface roughness. Check the final grade of the repair using line-of-sight profile measurement
stanchions, upheaval posts, or string lines to ensure that the repair meets surface roughness
criteria. In the case of a crushed-stone repair without foreign object damage cover, check the
repair surface for loose aggregate or potential foreign object damage.
Foreign object damage cover. Ensure that foreign object damage covers are no more than 5°
off parallel with the runway centerline. Check connection bolts, and verify that all connections
between panels are tight and secure. Check anchor bolts, and verify that all bolts are secure and
that the foreign object damage cover is held snugly against the pavement surface. In taxiway and
apron applications, anchor the leading and trailing edges of the foreign object damage cover.
Anchor the side edges if the cover is located in an area where aircraft are required to turn.
Setting and curing operations. If the repairs are capped with concrete, stone and grout, or
rapid-set materials, verify that the surface material has set and that adequate cure time is allowed
prior to aircraft operations.
Cleanup. For all repair methods, verify that the repair and adjacent areas are clear of any excess
repair materials.
Airfield certification. The on-site engineer who is responsible for the repair certifies that the
repair was accomplished according to the procedures in the appropriate Unified Facilities
Criteria and other applicable publications. The repair procedures are documented on an ADR log
form, which is updated to reflect subsequent aircraft traffic and required maintenance throughout
the repair history. If another team replaces the initial repair team, this form is transferred to the
follow-on team. The information is useful in planning or performing further maintenance or
upgrade of the repairs. Upon completion of repairs, provide the airfield repair status to the
airfield manager or other individual authorized to monitor and control on-site aircraft operations.
This individual then issues a notice to Airmen to change the airfield status.
6-73. Engineers must conduct a damage assessment, prepare for explosive hazard reconnaissance and
removal, understand the repair quality criteria, and know the requirements for the minimum aircraft-
operating surface. Consider including U.S. Air Force technical experts and airborne RED HORSE elements
as a part of the U.S. Army combat engineer element participating in the forcible-entry operation. They can
assist in approving the aircraft-operating surface, control aircraft landing and departure, and serve as liaison
to the airfield-opening team. The airfield-opening team can work with general engineer elements to take the
airfield to a higher standard of repair after the lodgment area has been secured.
6-74. For intelligence on all existing airfields and their dispositions or to request airfield damage
assessment and pavement evaluations, see the U.S. Air Force Civil Engineer Center Web site.
Repair Priorities
6-77. The airfield commander prioritizes essential ADR missions, usually in the following order:
Reconnaissance and damage assessment.
Explosive-ordnance disposal.
Minimum airfield-operating surface repair.
Repair to operational facilities, communication systems, ammunition storage facilities, essential
maintenance facilities, fuel storage and distribution areas, utilities, on- and off-base access routes
as a result of indirect damage due to direct-attack explosives that missed their primary targets.
Environmental and occupational health hazards.
Emergency Repair
6-78. Emergency repairs provide an expedient and temporary fix to allow the earliest resumption of air
missions. The Service that is responsible for the airfield determines the minimum operating strip and
performs crater and surface repair. The minimum operating strip is the minimum width and length required
for an aircraft to land and take off. Normally, the largest area of the airfield with the least amount of
damage is selected and identified as the minimum operating strip. All explosive hazards, including
remotely delivered mines, must be cleared from the minimum operating strip before surface repair starts.
6-79. U.S. Army engineers organic to the BCTs will typically conduct the initial forcible entry. ADR is
performed by airborne and air assault engineer elements who center on combat engineering skills and use
specific force packages or modules to conduct emergency repair primarily using a sand grid. Forward
aviation combat engineering is a combat engineering mission. However, GE units may be required to
perform, or augment combat engineers who are performing, forward aviation combat engineering missions,
depending on the situation. At this level of repair, this is a forward aviation combat engineering task that is
enabling mobility operation. (See ATTP 3-90.4/MCWP 3-17.8 for a discussion on forward aviation combat
engineering operations.)
Legend:
ft foot/feet
kg kilogram(s)
lb pound(s)
m meter(s)
6-80. U.S. Air Force engineers have sole responsibility for conducting emergency repair of established
U.S. air bases. The goal is to achieve sustained operations within 4 hours. This is done by specific force
packages or unit types formed from U.S. Air Force RED HORSE or Prime BEEF units. The U.S. Air Force
uses the following emergency repairs, depending on the nature of the damage:
Crushed stone over debris.
Choke ballast repair.
Choke ballast over debris.
6-81. U.S. Army engineers use two methods to make beyond-emergency repairs to established U.S. air
bases: stone and grout repair and concrete cap repair.
6-82. Air Force, Navy, and Marine engineers use similar techniques. The airfield commander directs the
priority of pavement repair effort, allowing permanent repair to begin as soon as the tactical situation,
available equipment, and labor permit. Pavements outside the minimum operating strip, including taxiways,
usually have a lower repair priority. Deliberately marking or clearing explosive hazards (to include
unexploded ordnance and improvised explosive devices) must be completed before permanent repairs can
begin. Explosive-ordnance disposal personnel are usually available for these types of area clearance
operations. However, engineers may have to perform these tasks if time is critical and the risk is
acceptable.
6-83. U.S. Army engineers are responsible for assisting U.S. Air Force RED HORSE or Prime BEEF
teams to repair critical airbase support facilities when such repairs exceed the U.S. Air Force capability.
Methods for repairing indirect damage are much the same as ordinary engineer construction techniques.
ROADS
7-2. Whether they are temporary or permanent, roads require some degree of Service support. This
section discusses the similarities and differences between each Service in providing road repair or
construction.
Combat Engineers
7-4. Combat engineers are responsible for combat trails and roads. Building combat trails and roads is a
combat engineering task that is conducted in close support to ground maneuver forces that are in close
combat and to support mobility. (See ATTP 3-90.4/MCWP 3-17.8.)
7-5. Baseline U.S. Army combat engineer units consist of sapper companies, mobility augmentation
companies, clearance companies, and multirole bridge companies. Their basic capabilities include
earthmoving assets for the hasty (expedient and temporary) construction of combat trails, roads, or
protective berms. Combat engineers can perform road-clearing operations, to include demolitions for
blasting, removing, and hauling away road obstructions, such as rock or heavy debris. They may be
required to link these combat trails and roads across gaps by bridging. (See ATP 3-34.22.)
7-6. Combat engineers have the capability to deny enemy access to combat roads and trails through
obstacle systems and networked munitions in support of their countermobility mission. (See ATP 3-
90.8/MCWP 3-17.5.)
7-7. There are limitations to combat engineer road-building capabilities. Combat engineers lack the
personnel, equipment, and expertise to construct surveyed and graded roads or to pave road surfaces.
Combat engineers may require augmentation with additional engineering assets and training. Therefore,
general engineers may be tasked to assist in the construction and repair of combat roads and trails if the
repair exceeds combat engineer capabilities. (See ATTP 3-34.23 and ATP 3-34.22 for more information on
capabilities.)
General Engineers
7-8. General engineers are responsible for military roads. Higher-level road work is a general engineer
task. General engineers have the capability to plan, design, construct, and maintain military roads. General
engineers possess horizontal and vertical assets, which expand and enhance their capabilities beyond
combat engineers. They can construct and repair roads, MSRs, and railroads and handle large-scale
projects. They possess specialized expertise, such as the ability to perform quality road construction and
pave road surfaces, and include surveyors and soil analysts. (See ATTP 3-90.4/MCWP 3-17.8.)
7-9. General engineers can be augmented and enhanced with specialized engineer units to support road-
building efforts. They include construction management teams, topographic units, equipment support
platoons, survey and design teams, asphalt teams, concrete sections, and geospatial planning cells.
7-10. General engineers possess a variety of heavy construction equipment, to include graders, scrapers,
loaders, large dump trucks, excavators, cranes, concrete trucks, asphalt producers, and pavers. Their
capabilities also include quarry platoons with rockcrushers to produce and haul road base construction
material and asphalt teams for road surface paving.
7-11. The basic capabilities of engineers can be expanded through the augmentation of additional
expertise, personnel, and equipment for extensive road construction projects. Engineers also have the
capability of reachback for accessing additional construction expertise as needed. (See ATP 3-34.22 for
additional information on capabilities.)
7-12. General engineers coordinate geospatial support as needed. (See ATP 3-34.80 and FM 5-430-00-
1/AFJPAM 32-8013, Volume I.)
7-13. U.S. Army engineer construction units have the following responsibilities and capabilities:
Route, road, and bridge reconnaissance.
Road base materials testing.
Maintenance, repair, and upgrade of existing roads.
Construction of new roads.
Recommendations for traffic control procedures.
Construction and installation of signs and other route-marking materials.
Regulation traffic where engineer work is being performed.
RAILROADS
7-17. The process for authorizing the construction, acquisition, or operation of railroad lines is discussed in
49 USC 10901. Military construction projects are discussed in 10 USC 2801.
7-18. General engineers are responsible for new railroad construction. With vertical and horizontal
companies, they can perform repairs to restore railroads to service and perform the limited construction of
railroads. U.S. Army general engineers have no railroad-specific technical training, but apply their road and
facilities capabilities to railroads. (See ATP 3-34.22.)
7-19. The U.S. Army transportation battalion (railway) is responsible for operating railroads and
performing rehabilitation and routine maintenance. The railway battalion is responsible for the operation of
railway locomotives and trains, conduct of railway inspections and maintenance, and repair of major track
damage. The battalion must also inspect, maintain, and repair diesel-electric locomotives and rolling stock,
provide train wreck support, conduct vehicle recovery, and operate up to 240 miles of track.
7-20. Each transportation railway battalion may be assigned from 90 to 150 miles of main line with
terminal operating and maintenance facilities, signaling equipment, and interlocking facilities necessary for
operation. The rail transportation officer task is to make the most efficient use of existing facilities by
maximizing maintenance efforts. Where HN agreements exist, day-to-day O&M may be largely conducted
by the local work force.
7-21. U.S. Army railway transportation units are organized to provide the U.S. Army with train operations
and railway maintenance support crews. Their rolling stock includes diesel-electric locomotives, cranes,
tank cars, freight cars, and other equipment. They are capable of operating railway main line and yard
operations, operating freight and passenger trains, switching in yards and terminals, and providing
personnel to operate trains on a 24-hour basis. (See ATP 4-14 for additional information on U.S. Army rail
operations.)
7-22. The U.S. Army capacity to operate railways does not include the equipment needed to mount a
railway operation. For this reason, the U.S. Army ability to use rail transportation depends largely on the
existing capacity of the AO. Rail is a strategic asset and an operational-level-of-war asset. Within CONUS,
the Military Traffic Management Command arranges for all rail movements of cargo and personnel to the
seaport of embarkation. In CONUS, the ASCC is responsible for doing the same when deploying armed
forces in support of a military operation. Because of limited military resources, the use of HN personnel or
contractors may become the primary source of O&M capability. (See FM 4-01.)
ROUTE SELECTION
7-27. Based on operational requirements and reconnaissance data, the engineer and transportation staff
officers propose an initial route for roads and railroads. This proposed route is analyzed based on obstacles,
route restrictions, grades, and the best horizontal and vertical alignment. The original route survey consists
of straight-line segments or tangents that are then connected through an iterative design process with
horizontal and vertical curves to achieve the shortest, smoothest, most efficient route that requires the least
construction resources.
ROADS
7-28. Military roads are classified according to their degree of permanence and the characteristics of traffic
they are designed to support—wheeled or tracked of a specific volume (number of vehicles per day).
Military roads are classified as Type A, B, C, or D, depending on the amount of traffic they are expected to
sustain per day. Type A roads (four-lane) are designed for the highest capacity, while Type D roads (one-
lane) are designed for the lowest. Normally, Types B, C, and D apply to TO construction. (See FM 5-430-
00-1/AFJPAM 32-8013, Volume I, for additional information.)
7-31. A combat trail is a travelled way that has been cleared of obstacles, but has not been temporarily
surfaced. A trail may be roughly graded by combat earthmoving equipment (such as an armored combat
earthmover [M9] or a deployable, universal combat earthmover) to provide a relatively smooth surface.
Combat trails are usually adequate for tracked and wheeled combat vehicles. A combat trail is a route
through areas where routes do not exist.
7-32. A combat road is a travelled way that has been cleared of obstacles and temporarily surfaced by an
expedient means to increase its trafficability. Combat roads usually do not have bituminous or concrete
surfaces. Combat roads require more effort to build than combat trails, but they support a broader range of
vehicles and tend to last longer.
7-34. Surfaced roads are laid out, designed, and constructed to specific criteria. The subgrade is compacted
to design specifications, and layers are added to create the road structure. Surfaced roads—
Are used in rear areas or support areas where general engineers and resources are available.
Are not limited by most weather and are designed for specific traffic loads.
Are used as more permanent road networks, such as MSRs and primary LOCs.
Require periodic maintenance and can be easily upgraded.
Are designed to temporary standards to sustain mobility for a longer period (up to 2 years).
7-35. During contingency operations, nearly all roads are constructed to temporary standards. In some rare
cases, semipermanent and permanent roads may be designed to provide long-term mobility (up to 20
years). Permanent roads are often planned, designed, and constructed in conjunction with USACE or
similar organizations. The employment of civilian contractors or Service general engineer organizations
may be used.
7-36. Most new, two-lane military roads are surfaced with aggregate (sand; gravel; crushed rock; slag; or
recycled, crushed concrete), stabilized soil, or the best locally available materials. This allows for future
upgrades and permits the maximum use of readily available materials to complete the road rapidly.
Selected high-use portions, such as intersections, may be surfaced with more durable materials to support
heavier loads. Only a few highly used, new military roads receive asphalt concrete or Portland cement
concrete surfaces due to the time required and the added cost for this type of construction.
7-37. Asphalt is a petroleum-based product with two primary subgroups used in construction: asphalt
cement and liquid asphalt materials. Asphalt cement is mixed with aggregate and sand to make asphalt
concrete. Liquid asphalt materials are sprayed on roads for various purposes. Bitumen (a generic term) is a
broad category of materials that occur naturally, or it could be an asphalt that is distilled from petroleum or
a tar that is distilled from coal. Bitumen and asphalt are often used interchangeably; bitumen is often used
outside the United States. Asphalt concrete (often called asphalt) and bituminous concrete are made with a
bituminous material as a binder for sand and gravel. Bituminous design is described in detail in
TM 3-34.63.
Road Networks
7-38. There are a number of factors that must be considered when establishing any road network. They
include the following:
Mission. Operational and mission requirements will determine the minimum road classification
and design requirements, based on the expected period of usage and the anticipated traffic load.
Enemy. Threat capabilities and anticipated types of action could affect the methods of
construction and the road location and design. Avoid creating choke points and other potential
ambush points when possible.
Terrain and weather. The location of a road is dictated by operational and mission
requirements. Existing slopes, drainage, vegetation, soil properties, weather patterns, and other
conditions may affect layout and construction.
Troops and support available. Use local materials, labor, and equipment when and where
possible. Use simple or preexisting designs, such as those in the TCMS that require minimal
skilled labor and specialized equipment when possible.
Time available. Speed is critical when establishing a road network during a contingency
operation because of the rapid and dynamic tempo of military operations. It is essential to save
as much time as possible by efficiently using the minimum amount of resources. Use effective
project management techniques to save resources. When possible, use staged construction to
allow the early use of roadways while further construction, maintenance, repair, and upgrades
continue.
Civil considerations. Civilian property restrictions, real estate actions, existing structures,
restricted areas, cultural beliefs, environmental considerations, and other factors may also affect
road layout and construction.
Route Reconnaissance
7-39. It may be necessary to conduct bridge reconnaissance and classification computations. (See FM 3-
34.170/MCWP 3-17.4 for additional information on route reconnaissance.)
7-40. Proper site selection is a crucial step in new road construction. Future construction problems can be
avoided by the careful reconnaissance and wise consideration of future operational requirements. A road
project that is poorly laid out will not meet the requirements for construction ease and efficiency,
maintainability, usability, capacity, and convenience.
Soil Properties
7-44. The engineer reconnaissance team may also determine soil properties on-site and at potential borrow
pits and quarry sites along the proposed route. Soil properties (such as the liquid limit, plasticity index,
California bearing ratios, and gradation) are required to properly design a new road pavement structure or
upgrade an existing road pavement structure, based on the anticipated traffic that the road will support.
These soil properties are also required to evaluate the suitability of aggregate taken from potential borrow
pits and quarries for use in road construction, maintenance, and repair.
Drainage
7-45. Drainage patterns impacting roads are also important in site selection. When the tactical situation
permits, roads should be located on ridgelines. Thus, natural drainage features minimize the need for the
costly and time-consuming construction of drainage structures. When possible, avoid excessive subsurface
water. If it is impossible to avoid road construction in locations with saturated terrain, water tables must be
lowered during construction. Steps must also be taken to minimize adverse effects of water on the strength
of the supporting subgrade and base course.
Obstacles
7-46. Where possible, avoid obstacles (such as rivers, ravines, and canals) to minimize the need for bridge
construction or similar structures. Such construction is time-consuming and calls for materials that may be
in short supply. Make maximum use of existing structures to decrease total work requirements. Do not
bridge an obstacle more than once. Should gap-crossing operations be necessary, ensure that the proper
type of bridging or other methods provides an adequate and sustainable solution.
7-47. To sustain traffic, roads have a crowned driving surface and pavement structure, a shoulder area that
slopes directly away from the driving surface to provide drainage off the driving surface, and side ditches
for drainage away from the road itself. The shoulder areas and side ditches along many roads may be
minimal, depending on their location and their road classification.
Road Design
7-48. The four major road designs that can be applied are—
Geometric design.
Pavement structure design.
Drainage system design.
Bridge design.
7-49. The road geometric design consists of the selection of road type, estimated traffic volumes, grade and
alignment, horizontal curves, and vertical curves. Each road type has geometric design data, such as cross
section elements and alignment elements that provide safe and rapid traffic movement. The geometric
design data is provided to the constructing unit that lays out the design information on the ground with the
construction survey. The construction survey provides stakes with survey details that construction
equipment operators can use to conduct earthmoving.
7-50. Unsurfaced roads use the natural soil or borrow soil as the road surface. The design of unsurfaced
roads is based on traffic characteristics and the compacted in-place soil strength. Unsurfaced roads meet all
geometric design data for the selected road.
Pavements
7-51. During contingency operations, consider whether to pave a road by considering the urgency of its
completion, the tactical situation, the expected traffic, the soil-bearing characteristics, the climate, the
availability of materials and equipment, and the necessity of dust control. (See UFC 3-260-17.)
7-52. Pavements, including the surface and underlying courses, may be rigid and flexible. The wearing
surface of rigid pavement is made of Portland cement concrete. Asphalt cement concrete pavements are
classified as flexible pavements. The typical road pavement structure (cross section) consists of layers
(pavement or surface course, base, subbase, and select material) on top of a compacted subgrade. (See UFC
3-250-04 and UFC 3-250-06.)
7-53. There are four types of road pavement structure designs, which are distinguished by the pavement or
surface layer. These types are as follows:
Unsurfaced roads.
Aggregate-surfaced roads. (See UFC 3-250-09FA.)
Bituminous-surfaced roads.
Concrete-surfaced roads.
7-54. Flexible pavements are used almost exclusively in contingency operations. They are adaptable to
almost any situation and fall within the construction capabilities of normal engineer troops. Rigid
pavements are not usually suited to construction requirements during contingency operations. Because
flexible pavements reflect distortion and displacement from the subgrade upward to the surface course,
their design must be based on complete and thorough investigations of subgrade conditions, borrow areas,
and sources of select materials, subbase, and base materials. (See UFC 3-250-03 and UFC 3-250-08FA for
more information on flexible pavements.)
7-55. A road pavement structure sits on top of the subgrade or the soil in place. A layer of compacted
subgrade sits on top of the subgrade, and a layer of select material sits on top of the compacted subgrade. A
layer of subbase material sits on top of the select material, and the base course sits on top of the subbase. A
road may have a flexible pavement (asphalt) or a rigid pavement (concrete) surface on top of the base
course. The thickness of a layer depends on the strength of the layer below it. Depending on design
requirements, some layers may not be required. These pavement structures are designed to distribute wheel
loads over a wider area of each subsequent underlying layer within the pavement, thereby reducing
pressure on the subgrade soils.
7-56. During contingency operations, nearly all roads are constructed as aggregate-surfaced roads. These
designs permit the maximum use of readily available materials and are easy to upgrade–permitting great
flexibility to respond to changing operational and mission requirements. When possible, the roadbed should
be aligned to take advantage of the most favorable surface and subsurface terrain. An alignment over soil
with good properties meets the design standards for strength and stability and minimizes the need to
remove undesirable materials.
bonded to form a more stable mass, using additives such as lime, bitumen, or Portland cement. (See UFC
3-250-11 for additional information.)
7-60. Traffic flow over roads is far more efficient if curves and grades are held to a minimum. Even gentle
curves significantly decrease traffic capacity if there are too many on a route. Therefore, lay out all routes
with a minimum of curves by making the tangent lines as long as possible. The availability of long tangents
is influenced by terrain. It is also limited by other principles of efficient location, such as minimizing
earthwork, avoiding excessive grades, and obtaining desirable soil characteristics.
RAILROADS
7-61. The ability to rapidly move troops and materiel to key locations may well decide the outcome of a
conflict. Railroads provide one of the most effective and efficient forms of land transportation available to
forces during contingency operations. They can move great volumes and tonnages of materiel and large
numbers of personnel over long distances with considerable regularity and speed in nearly all weather
conditions. Railroads are flexible and versatile, and rolling stock may be tailored for transporting cargo.
Extensive railway systems exist in most regions of the world and have an interoperability provided by
standard equipment and common gauge. These capabilities make railroads a preferred means of
transportation during contingency operations.
7-62. Maximizing a rail system may depend on its capacity (length and condition of existing track,
condition of rolling stock and other facilities) and its ability to support operational and mission
requirements while still maintaining essential commercial traffic. ATP 4-14 describes the organizations,
processes, basic construction and maintenance standards, and systems involved in rail operations. (See
UFC 4-860-01FA for additional information on railroad design. See TM 5-628/AFR 91-44 for more
information on railroad track standards.)
7-63. All existing facilities must be used to the maximum extent possible to minimize construction time
and effort. Transportation units in coordination with engineers conduct a reconnaissance and select new
routes. New railroad construction will normally consist of short spurs to connect existing networks with
military terminals or to detour around severely damaged areas. The focus of engineer effort should be on
modifying and repairing existing railroads to meet operational and mission requirements.
7-64. Local labor and management are key to the rapid modification and continuing maintenance of
existing facilities. Local personnel can often supply materials and skilled labor to speed the work and
relieve military personnel for other projects. Local railway operating personnel can be a good source of
information on existing conditions, operations, and supply facilities in a given area.
7-65. In order to expedite operations, railroads constructed during contingency operations may have
accepted lower safety factors, sharper curves, and steeper grades than recommended by the American
Railway Engineering Association. Once the minimum standard for immediate service has been attained,
phased improvements can be made, provided the importance of the line justifies the effort.
Railroad Bridges
7-66. A railroad bridge is a LOC bridge and is classified as a nonstandard bridge. The U.S. Army does not
have design criteria for nonstandard railroad bridges, nor does it possess railroad float bridge equipment.
Many varieties of standard railroad bridges are available through AFCS. Construction details and bills of
material are addressed in TM 5-302-1. Standard railroad bridging is available for the Bailey bridge and for
certain contracted panel bridges.
7-67. The railway bridge construction process begins with a proper determination of design requirements.
The engineer must determine the appropriate load-bearing capacity of the intended bridge to support the
full weight of the train itself, plus its maximum cargo load. In most cases, the design criteria should
consider Copper E80 loads (train with a locomotive weight of 520 metric tons and axle loads equal to 37
metric tons).
7-68. Steel stringer bridges supported on timber trestles or piles satisfy most railway bridging
requirements. (See TM 3-34.23 for information on Bailey bridge railway bridges.)
7-69. Panel bridge equipment can be used as a field expedient for the assembly of railway bridges.
However, it can only be used in special conditions because there is much deflection. Because of this,
railway bridging is restricted to spanning gaps no longer than 70 feet (21.5 meters). Usually, panel bridges
can be assembled as a single-track bridge. (See TM 3-34.23 for more information.)
7-70. The engineer must establish immediate liaison with the Transportation Corps for support in railroad
planning. The following information is needed:
Mission and required capacity of the proposed systems.
Type, size, and weight of rolling stock to be operated.
Track gauge.
Initial, intermediate, and final terminal points along the route.
Servicing and maintenance facilities required.
Connections with other railway systems.
Maximum gradient and degree of curvature required.
Scheduling or timetable for completing construction.
Direction of future development and expansion.
Outbound movement—the ready track and wye.
7-71. Railroad service facilities should be laid out so that servicing operations can be performed in proper
sequence as the locomotive moves through the terminal. The usual relationship of operations and facilities
from terminal entrance to terminal exit is—
Inspections. Inspection pits or platforms.
Lubrications. Oil and grease service areas.
Ash pits. Ash pits for cleaning fires if steam locomotives are used.
Facilities. Coal, sand, diesel oil, and water-appropriate facilities.
Repairs. Running repairs (engine house).
7-72. The urgency of the situation or lack of additional bridging assets may require that a railroad bridge
be converted into a highway bridge by constructing a smooth roadway surface. The use of the bridge by
rail, wheeled, and tracked vehicles can be achieved by constructing planks along the ties between and
outside the rails, up to the level of the top of the rail.
7-73. The repair and reinforcement of existing railroad bridges is a much more viable option than new
construction. Nonstandard railroad bridging can be repaired or improved using any available and suitable
materials. Railroad bridges will require specialized construction equipment and is labor-intensive. This
generally precludes the construction of railroad bridges at locations away from existing rail lines. When a
site must be selected, use the basic criteria for general bridge sites.
Railroad Reconnaissance
7-74. After design requirements have been determined, transportation unit representatives and engineers
will conduct a field reconnaissance to determine the siting of the rail system. The surveys, studies, and
plans required for railroad construction are necessarily more elaborate than those for most road
construction. Studies of the best available topographic maps, imagery, and other geospatial products narrow
the choice of routes to be reconnoitered. Factors that affect the location of a route include logistics, length
of line, curvature, gradients, load-bearing capacity of travelled surface, and ease and speed of construction.
Each of the factors of METT-TC can impact on railway site selection, just as they affect the location of a
road.
Logistics
7-75. Logistics is a major consideration in selecting a rail route during contingency operations. Normally, a
rail line will extend from a seaport of debarkation, aerial port of debarkation, beachhead, or another source
of supply in theater to the logistics support areas sustaining the forces present. Alternate routes are
desirable for greater flexibility of movement and as insurance against cases of mainline obstruction because
of threat actions, wrecks, washouts, floods, fires, landslides, or enemy activity.
7-76. The length of line (mileage from point of origin to terminus) is important only when it adds
materially to the time of train movement. As much as a 30 percent increase in mileage is permissible when
it proves advantageous to the other factors involved.
Curvatures
7-77. Sharp curvatures should be minimized as much as possible, consistent with the speed of construction.
Determining the curvature for a military railroad will depend largely on the maximum rigid wheelbase of
train cars and locomotives. Superelevation is used to counteract centrifugal force on curves by raising the
outer rail higher than the inner rail. (See TM 3-34.55.)
Ruling Grades
7-78. The ruling grade of a route is the most demanding grade over which a maximum-tonnage train can be
handled by a single locomotive. Where diesel-electric units are used, a single locomotive may consist of
two or more units that are coupled and controlled from the cab of the leading unit. The ruling grade is not
necessarily the maximum grade. Steeper grades can be negotiated with the use of an additional locomotive
as a helper engine; or if the grade is very short, the train may be carried over the crest by momentum. Since
military railroads operate at slow speeds, the ruling grade must be kept to a minimum. As always, the
necessity for rapid construction must be a top priority.
Ground Reconnaissance
7-79. Select a good route that will allow the rail line to be rapidly constructed using minimal resources.
Many additional hours of earthwork and grading can be avoided by a careful route selection.
7-80. A complete ground reconnaissance of the possible railroad routes is required. The reconnaissance
team should note distance and elevation odometer and barometer observations, general terrain
characteristics, controlling curvatures, soil and drainage conditions, bridge and tunnel sites, bridge sizes
and types, railway or important road intersections, ballast and other construction material availability, and
points at which construction units would have access to the railway route. Factors to be taken into
consideration include the roadbed, rock cuts, hillsides, drainage, security, water supply, passing track, and
surveys.
Roadbed
7-81. The roadbed should be built on favorable soils. Clay beds, peat bogs, muck, and swampy areas are
unstable foundations and provide unsuitable soils for building fills. Cuts through unfavorable soils will
slough and slide. Seek minimum earthwork in locating the roadbed and track. Where rock cuts are
proposed, select locations that will allow the bedding planes to dip away from the track to prevent
rockslides. Avoid locations at the foot of high bluffs, which will subject the track to rock falls, slides, and
washouts. Rockwork is time-consuming; avoid it when practicable. In a temperate zone, choose sites along
the lee side of hills. This prevents snowdrifts and resists wind effects.
Surveys
7-83. The preliminary railroad survey includes cross sections along the feasible routes. Trail locations are
plotted and adjusted to give the best balance of grades, compensated grades, cuts, and fills. This establishes
or fixes the line of the railroad. Field survey parties locate the precise line and stake it. This requires much
more precision than the location survey of most new roads, since curves and super elevations must be
accurately computed.
7-84. Once the necessary railroad reconnaissance and surveys are complete, the engineer prepares an
estimate of the work and materials required and a plan for carrying out the construction. The engineer must
schedule the priority and rate of construction and provide for the even flow of material to ensure orderly
progress. Schedules must continually be updated to accommodate changed field conditions or other
exigencies. In addition to their planning function, the schedules can also serve as progress charts.
CONSTRUCTION
7-85. Road and railroad construction require carefully planned methodologies. This section discusses the
reconnaissance, steps, processes, estimating, and sequence required for sound construction and the
upgrading requirements.
ROADS
7-86. The construction directive usually provides the road geometric design, pavement structure design,
and drainage system design, but probably not the temporary construction drainage structures. Road
construction encompasses the following considerations:
Site reconnaissance.
Site preparation.
Construction planning.
Construction survey.
Construction sequence of execution.
Existing intelligence reports and threat analysis.
Strategic and technical reports, studies, and summaries.
Road, topographic, soil, vegetation, and geologic maps or other geospatial information.
Existing aerial reconnaissance reports.
Existing road design information or maintenance plans.
7-88. Clearing, grubbing, and stripping are the same in road and airfield construction. Earthmoving
operations are usually the largest single work item on any project involving the construction of a road,
unless the road will have significant gaps to cross. Any step that can be taken to avoid excessive earthwork
will increase job efficiency.
7-89. Adequate drainage is essential during the construction of a military road or airfield to control water
runoff. A construction drainage system is temporarily established to prevent construction delays and
structural failure before completion. The construction drainage system requires continuous inspection and
maintenance.
7-90. Consider the proposed use of the road. If it is to be used only for a short time, such as 1 or 2 weeks, a
detailed drainage system design is not justifiable. However, if improvement or expansion is anticipated,
design drainage so that future construction does not overload ditches, culverts, and other drainage facilities.
(See FM 5-430-00-1/AFJPAM 32-8013, Volume I.)
7-91. Drainage problems are greater when all-weather use occurs as opposed to intermittent use. Consider
the availability of engineer resources. Heavy equipment (such as dozers, graders, scrapers, and excavators)
is commonly used on drainage projects. However, where unskilled labor and hand tools are readily
available, drainage work can be done by hand.
Work Estimates
7-92. When the necessary reconnaissance and mission analysis are complete, the engineer prepares an
estimate of the work and materials required and a plan for carrying out the construction. The engineer must
schedule the priority and rate of construction and provide for the even flow of material to ensure orderly
progress. Schedules must continually be updated to accommodate changed field conditions or other
exigencies. In addition to their planning function, the schedules can also serve as progress charts.
Construction Sequence
7-93. Once earthwork estimation, equipment scheduling, and necessary surveys are complete, the
construction sequence can begin. Prepare the construction site by clearing, grubbing, and stripping. These
operations are usually done with heavy engineer equipment. Use hand or power felling equipment,
explosives, or fire when applicable. The factors determining the methods to be used are the acreage to be
cleared, the type and density of vegetation, the effect of the terrain on equipment operation, the availability
of equipment and personnel, and the time available for completion. For best results, use a combination of
methods, choosing each method for the operation in which it is most effective.
7-94. Conduct cut and fill operations when clearing, grubbing, and stripping are finished. Cut and fill
operations are the biggest part of the earthwork in road construction. The goal of cut and fill work is to
bring the route elevation to design specifications. Throughout the fill operation, compact the soil in layers
(lifts). Achieve soil compaction with self-propelled or towed rollers. The end state is a structure that
minimizes settlement, increases shearing resistance, reduces seepage, and minimizes volume change.
7-95. The advantages that accompany soil compaction make this process standard procedure for
constructing embankments, subgrades, and bases for road and airfield pavements. Cut, fill, and compaction
efforts are intended to achieve the final grade. This alignment takes into consideration superelevation along
curves to ensure load stability and falls within military road grade specifications. When final grade is
achieved, cut ditching to control drainage runoff and crown the road along its centerline. The road is now
ready for surfacing.
Surfacing Considerations
7-96. All unpaved roads will emit dust under traffic, making it an inherent problem. The amount of dust
that an unpaved road produces varies greatly depending on local climatic conditions and the quality and
type of aggregate used for road construction. Common dust control agents include chlorides, resins, natural
clays, asphalts, and other commercial binders and membranes. Dust control and soil waterproofing can be
carried out by applying these agents in a spray (soil penetrants) or admixture or by laying aggregate,
membrane, or mesh as a soil blanket. (See UFC 3-260-17 for additional information on dust control
measures.)
7-97. The agronomic method (using vegetation cover) is suited to stable situations, but is rarely useful
during contingency operations. To effectively apply stabilizers and dust control agents, ensure that the
aggregate road surface has good gradation, construct a good crown on the driving surface, ensure good
drainage, ensure that the equipment is calibrated accurately and is working properly, and rehearse the
application of the agent using a test strip.
7-98. Use expedient surfaces as temporary means to quickly cross small areas with extremely poor soil
conditions (such as swamps, quicksand, and wetlands) when lacking the time or resources for standard road
construction. These are unsurfaced roads where some material has been placed on the natural soil to
improve trafficability. There are two types of expedient roads—hasty and heavy. Hasty expedient roads are
built quickly to last only a few days. Heavy expedient roads are built to last until a durable standard road
can be constructed. Expedient surfacing methods include cross-country tracks, corduroy, chespaling
landing mats, U.S. Army track, plank tread, wire mesh, snow and ice, and sand grid.
7-99. The availability of construction material determines the types and strength of roads that can be
constructed. Naturally occurring materials, such as rock and wood, may be scarce or of poor quality.
Portland cement may not be available or may be prohibitively expensive to use. Sand grid material is
excellent for use in areas of cohesionless soil. Matting, steel planking, or geotextiles may be used if they
are available. When roads are constructed in areas of poor soil conditions, roadways must be well marked
and adequate drainage must be provided. (See ATP 4-13.)
7-100. Spray applications and surface treatments are the most economical, troop-constructed surfaces.
Surface treatment can be divided into two categories—sprayed treatments and sprayed bitumen with
aggregate surface. Bituminous materials are tars, road tar cutbacks, or asphalt emulsions. Spray
applications provide soil or aggregate with the following surface treatments:
Prime coat (waterproofing).
Tack coat (binds bituminous pavement to the surface).
Dustproofing.
7-101. Spray bitumen with an aggregate surface provides a waterproof, abrasive, wear-resistant surface
with no significant structural strength.
Upgrades
7-102. Where possible, use existing road facilities. In most areas, an extensive road network already
exists. With the expansion and rehabilitation of the roadway and the preparation of adequate surfaces, the
road network can be improved to carry required traffic loads. Upgrading an existing road, combined with
routine maintenance and repair, usually involves reducing or eliminating obstructions. It is the preferred
method of improving the trafficability of a selected route.
7-103. Techniques, equipment, and materials needed for upgrading roads are generally the same as those
for new construction. A changing tactical situation and unpredictable military operations may also require
that military engineers modify and expand completed construction. The location of a road should allow for
potential expansion. Expanding an existing route or facility conserves labor and material and permits
speedier completion of a usable roadway.
RAILROADS
7-104. As a first stage in organizing railroad construction work, the engineer divides the line into sections
in which special features (such as bridges, stations, yards, and rock cuts) can be constructed while other
work is in progress. Work can proceed concurrently at several locations. The standard construction
sequence is as follows:
Clear and grub.
Prepare the subgrade by cutting or filling and compacting.
Unload and distribute track materials.
Align and space cross ties.
Place line rails or ties.
ROADS
7-112. The operation of roads is often performed and controlled by transportation units or movement
control teams when they are designated MSRs or alternate supply routes. Operation involves controlling
traffic with orders, signs, checkpoints and, possibly, patrols.
7-113. Road maintenance requires a substantial amount of resources and technical expertise on a
continuous basis. Roads must be maintained and repaired for safe and speedy traffic movement.
Maintenance is the routine prevention and correction of damage and deterioration caused by normal use
and exposure to the elements. Repair restores damage caused by abnormal use, accidents, hostile forces,
and severe weather actions. Repair includes the resurfacing of a road or airfield when maintenance can no
longer accomplish its purpose. Rehabilitation restores roads or airfields that have not been in the hands of
friendly forces and do not meet operational requirements. Rehabilitation resembles war damage repair,
except that it is accomplished before occupancy.
7-114. Routine maintenance and repair operations include inspections, stockpile of materials for
maintenance and repair work, maintenance and repair of road surfaces and drainage systems, dust and mud
control, and snow and ice removal. The main purpose of maintenance and repair work is to keep road
surfaces in usable and safe condition. Routine maintenance and repair also maintains route capacity and
reduces vehicle maintenance requirements. Effective maintenance begins with a command-wide emphasis
that stresses good driving practices to reduce unnecessary damage. Once damage has occurred, prompt
repair is vital. After deterioration or destruction of the road surface begins, rapid degeneration may follow.
A minor maintenance job that is postponed becomes a major repair effort involving the reconstruction of
the subgrade, base course, and roadway surface.
7-115. The following guidelines should be observed in conducting sound road maintenance and repair:
Minimize interference with traffic. To keep surfaces usable, maintenance and repair activities
should interfere as little as possible with the normal flow of traffic. A temporary bypass may be
required.
Correct the basic cause of surface failure. Efforts spent to make surface repairs on a defective
subgrade are wasted. Any maintenance or repair should include an investigation to find the cause
of the damage or deterioration. That cause must be remedied before the repair is made. To ignore
the cause of the damage is to invite prompt reappearance of the damage.
Reconstruct the uniform surface. Maintenance and repair of existing surfaces should conform as
closely as possible to the original construction in strength and texture. Simplify maintenance by
retaining uniformity. Spot strengthening often creates differences in wear and traffic impacts,
which are harmful to the adjoining surfaces.
Assign priorities. Priority in making repairs depends on the operational requirements,
commander’s guidance, traffic volume, and hazards that would result from the complete failure
of the facility.
Maintenance Inspections
7-116. The purpose of road maintenance inspections is to detect early defects before actual failure occurs.
Frequent inspections and effective follow-up procedures early in the process prevent minor defects from
becoming serious and causing major repair jobs later. Prompt and adequate maintenance (care of joints,
repair of cracks, replacement of broken areas, and correction of settlement) and drainage involves retaining
a smooth surface and keeping the subgrade as dry as possible. A smooth road surface protects the pavement
from the destructive effects of traffic, and it reduces vehicle wear and tear. (See TM 3-34.63 for more
information.)
7-117. Road inspections are essential to prevent road failure. When inspecting road surface and drainage
defects, look for actual causes of the defects. Potholes are the most common type of road failure in
bituminous wearing surfaces. Potholes and pavement defects can usually be attributed to excessive, heavy
loads and traffic; inferior surfacing material; frost in the base; poor subgrade; excessive settlement in the
base; inadequate drainage; or a combination of these conditions. Ensure that all drainage channels and
structures are kept unobstructed. Exercise extra vigilance during rainy seasons and spring thaws and after
every heavy storm.
Notes.
1. See TM 3-34.63, UFC 3-270-01, UFC 3-270-02, and UFC 3-270-08 for additional
information on road inspections and repairs.
RAILROADS
7-125. Railroads may be operated by the HN, private companies, contractors, or military transportation
railway personnel. Although transportation units have the responsibility for routine maintenance, engineers
must be prepared to provide construction support when additional maintenance beyond the organic
capabilities of transportation units is required. Rail lines and supporting facilities must be inspected
regularly to ensure adequate maintenance and proper operation. Necessary action must be undertaken as
quickly as possible to minimize future repair requirements.
7-126. Railroad preventive maintenance, including the proper cleaning and lubrication of equipment and
machinery, will minimize the need for unnecessary maintenance and repair. Railroads are susceptible to
maintenance problems and are vulnerable to enemy attack, guerilla operations, and sabotage. Railroads
used by the transportation railway service already exist. Maintenance is required on supporting facilities,
road crossings, railroad bridges, tracks, sidings, and switching equipment. (See ATP 4-14 for additional
information on railroad maintenance.)
Notes.
1. See ATTP 3-90.4/MCWP 3-17.8 for more information on combined arms gap crossings.
3. See ADRP 4-0 for more information on bridging to support sustainment and the LOC
transportation system network.
OTHER COUNTRIES
8-10. U.S. military allies can be a viable option for obtaining additional bridging assets. Countries like
Great Britain and Germany maintain organic bridging assets with military engineers. Specific, allied
bridging assets are discussed later in this chapter. (See ATTP 3-90.4/MCWP 3-17.8 for additional
information.)
TACTICAL BRIDGING
8-13. Tactical bridging is rapidly deployable and has the mobility to maintain the pace of operations with
the maneuver force that it supports. Tactical bridging is typically linked to combat engineers and the
immediate support of ground maneuver forces. Tactical bridging criteria includes the following:
The bridge can be deployed and recovered.
There is little bank preparation work required.
There is minimum time needed to recover.
8-14. The actual bridge can usually be deployed and recovered without exposing the crew to direct or
indirect fire. There are little to no requirements for bank preparation when using tactical bridging assets. It
takes minimal time to deploy and recover for temporary crossings.
8-15. Engineers primarily use four bridge systems to conduct tactical bridging operations. These systems
include—
The armored vehicle-launched bridge.
The joint assault bridge.
The Wolverine bridge.
A rapidly employed bridge system.
8-16. Although tactical bridging can be used on LOCs, planners should consider using this limited resource
temporarily until it is replaced by a better bridging solution. Tactical bridging is not designed to sustain or
support the heavy volume of vehicle traffic sustained through LOC bridging. Tactical bridging assets
should be freed up as soon as possible to ensure that they support combat maneuver and sustain the tempo
of operations. (See ATTP 3-90.4/MCWP 3-17.8 for additional information on employing the armored
vehicle-launched bridge, the joint assault bridge, the Wolverine bridge, and the rapidly employed bridge
system.)
SUPPORT BRIDGING
8-17. Support bridging is used to establish semipermanent or permanent support to planned movements
and road networks. Support bridges are normally used to replace tactical bridging as they provide greater
gap-crossing capability to the force than tactical bridging. Units typically deploy and recover these systems
when and where little or no direct fire threat exists. Bank preparation and improvement are important
planning factors for support bridging.
8-18. The support bridging category contains the float bridge (standard and improved ribbon), medium
girder bridge, dry support bridge, Bailey bridge, and rapidly employed bridge system. Although a rapidly
employed bridge system is often considered a tactical bridge, it is more accurately described as a support
bridge because it lacks crew survivability.
Commercial Bridging
8-19. Another support bridging option is procurement of commercially available panel bridges. (See ATTP
3-90.4/MCWP 3-17.8 for more information on employing the Bailey bridge, medium girder bridge, dry
support bridge, and logistics support bridge. See TM 3-34.23 for more information on the Bailey bridge.
See TM 3-34.21/MCRP 3-17.1A for additional information on the medium girder bridge.)
Float Bridging
8-20. A float bridge is designed as a rapid and temporary means to cross maneuver forces over wet gaps by
building raft configurations to transport forces across the wet gap or by emplacing bays to span the entire
width of the wet gap. U.S. forces can use float bridge rafts as assault bridging assets if needed. These rafts
can be used during buildup to assist in assembling full floating bridges during bridgehead operations.
Floating causeways can be used as floating bridges to augment standard floating bridge capability. There is
generally no design limit to the length of this bridge. The normal limiting factor is the quantity of bays and
boats; however, the velocity or current of the water, tidal variations, water depth, underwater obstructions,
floating debris, and entry and exit bank slopes can also limit float bridge operations. Descriptions and
construction techniques for the standard ribbon bridge are found in TM 3-34.85/MCRP 3-17A, and
techniques for the improved ribbon bridge are explained in TM 5-5420-278-10.
8-21. Float bridging may be used when there is a lack of existing fixed facilities or no suitable construction
materials to fabricate, reinforce, or repair existing bridges. When the situation calls for prolonged use or
heavy traffic, an existing bridge should be upgraded or new construction initiated. (See ATTP 3-
90.4/MCWP 3-17.8 for technical information on employing float bridging.)
LINE-OF-COMMUNICATIONS BRIDGING
8-22. LOC bridging is generally conducted in areas that are free from the direct influence of enemy action.
Typically, its primary purpose is to facilitate the sustainment of the force according to ADRP 4-0. It can be
used as a semipermanent or permanent structure. LOC bridges are built with the assumption that, once
emplaced, will not likely be removed until replaced by a more permanent structure. LOC bridges may be
tactical fixed bridges if the intention is to leave the system in place for an extended period and they are not
required to support combat maneuver.
Planning Considerations
8-23. Planning factors should account for the extended use of the bridge and increased wear because of
extended use. When planning for LOC bridging, planners should consider that an existing permanent
bridge may be damaged or may not be strong enough for mission requirements. Engineers repair and
reinforce a bridge using standard or nonstandard materials to meet mission requirements. The new
construction of LOC bridges is possible; however, improving existing structures is most desirable to avoid
the intense resource and time requirements associated with new construction. Examples of common U.S.
LOC bridging are the Bailey bridge and the logistics support bridge. (See ATTP 3-90.4/MCWP 3-17.8 for
more information on LOC bridging.)
Geospatial Considerations
8-25. Engineers use the engineer function of geospatial engineering to greatly improve situational
understanding (to include terrain) and select optimal bridging sites through enhanced terrain visualization
using high-resolution satellite imagery or unmanned aircraft system video. The requirement for the
engineer is to have the appropriate software. Engineer terrain teams should assist in reconnaissance and
assessment conditions in areas at or around potential gap-crossing sites. Terrain teams have software that
can assist in mission planning by determining soil conditions, hydrology, vegetation types, general weather
conditions, and other useful aspects of the terrain. (See ATP 3-34.80 for additional information on
geospatial engineering.)
Bridge Reconnaissance
8-26. ERTs should be used to collect data to determine acceptable terrain and conditions for new bridge
construction. Through reconnaissance information, planners can determine which type of bridge or bridge
combinations are right for the mission based on available resources. (See FM 3-34.170/MCWP 3-17.4.)
Note. See ADRP 5-0 for information on bridges in mission planning variables.
8-27. The final selected bridge site is determined by numerous factors, which are reflected in its structural
design. Primary screening considerations include—
Access and approach roads. Determine if the preexisting roads are adequate. The time to
construct approaches can be a controlling factor in determining if a crossing site is feasible.
Approaches should be straight, with two lanes, and have less than a six percent slope.
Widths. Determine the width of the gap to be spanned at normal and flood stages for wet gaps.
Banks. Estimate the character and shape of the banks accurately enough to establish abutment
positions. The banks should be firm and level to limit the need for extensive grading. Select
straight reaches to avoid scour.
Flow characteristics. Determine the stream velocity and erosion data, taking into consideration
the rise and fall of the water. A good site has steady current that runs parallel to the bank at less
than 3 feet per second.
Stream bottoms. Record the characteristics of the bottom. This will help determine the type of
supports and footings required. An actual soil sample is useful in the planning process,
particularly in wide gaps that may require an intermediate pier.
Elevations. Determine and record accurate cross-sectional dimensions of the site to determine
the bridge height. Planners must also know of any existing structures that the bridge must cross
over.
Materials. Determine the availability and accessibility of firm material, such as rock, for
improving bank conditions.
8-28. If these primary considerations for bridge site selection appear favorable, planners may apply the
following evaluation criteria:
Proper concealment for personnel and equipment on both sides of the gap.
The location of bivouac and preconstruction storage sites.
Firm banks with less than a five percent grade to reduce preparation work. Less than one percent
grade will also require site preparation.
Terrain that permits the rapid construction of short approach roads to existing road networks on
both sides of gap.
Turnarounds for construction equipment.
Large trees or other holdfasts near the banks for fastening anchor cables and guy lines.
A steady, moderate current that is parallel to the bank.
A bottom that is free of snags, rocks, and shoals and is firm enough to permit some type of
spread footing.
Determination of the number of assembly sites (upstream or downstream) for floating portions
of the bridge. If the current is strong, locate all assembly sites upstream from the bridge site.
Proper siting of logistics support operations to mitigate the possible effects of flooding.
8-29. Criteria for establishing a float bridge site may be the same as those for general bridge site selection.
The following are specific float bridge site considerations:
Banks should be low, firm, moderately sloping, and free from obstructions. Existing or easily
prepared assembly sites are desirable.
The stable bank should have a slope of 8° or less and a water depth of at least 48 inches on the
near shore.
The water velocity near the shore should be less than 5 feet per second. If the current is faster
(up to 10 feet per second), additional boats, personnel, and time will be required to emplace the
bridge.
Natural holdfasts for anchorages are desirable. Float bridging must be installed far enough
downstream from a demolished or under-capacity bridge to avoid interference with
reconstruction or reinforcement operations. Unstable portions of a demolished bridge and other
debris that may damage the float bridge should be removed before emplacing the float bridge.
structure; repair and demolition information; and the possibility of alternate crossing sites. After a proper
reconnaissance, a bridge study is completed. This is the detailed analysis of the selected site. To complete
the bridge study, the engineer should—
Request a topographic map to a scale of approximately 1:25,000. The map is used to plot the
location and obtain the distances and elevations for design purposes.
Determine whether physical characteristics at the site limit normal construction methods or
interfere with construction plant installation.
Make a detailed survey to furnish accurate information from which the bridge layout can be
developed, materials requisitioned, and the construction procedure outlined. Submit the survey
as plan and profile site drawings.
Conduct a foundation investigation. Develop a soil profile along the proposed bridge centerline
and at pier and abutment locations.
BRIDGE DESIGN
8-33. Bridges are designed to match the specific site conditions, proposed traffic, load-bearing capacity,
type of materials available, and time available for actual construction. The various combinations of bridge
types allows for a variety of designs, ranging from beam bridges, arch bridges, suspension bridges, and
truss bridges. Bridges are usually designed to be standard or nonstandard. Consult the specific standard
bridge model technical manuals for detailed information on applying design variations. (See TM 3-
34.22/MCRP 3-17.1B for more information on designs for military nonstandard fixed bridges.)
BRIDGE CLASSIFICATION
8-34. An efficient MSR network must be capable of carrying expected traffic loads. Often, bridging is the
weak link in the load-carrying capacity of a route. Military standard bridging is assembled in modules that
result in a bridge of known capacities. Support bridging is designed to pass an uninterrupted flow of
combat and tactical vehicles that generally fall within a military load classification below 60. However,
some combinations of vehicle size and weight may exceed a given bridge design capacity.
8-35. Where heavier loads are anticipated, it is best to designate MSRs along routes that already possess
bridges with appropriate classification ratings or to design and emplace bridges that can carry these loads.
The selective use of fords, in conjunction with MSR bridge sites, can provide a solution in selected cases.
8-36. Situations may arise when it is not possible to safely accommodate all traffic designated to cross
MSR bridges. Guidelines are set for special crossings (caution and risk) for oversize or overweight loads on
military standard, nonstandard, and float bridging. Specific guidance for determining special crossings is
contained in TM 3-34.85/MCRP 3-17A, TM 5-5420-212-10-1(Army)/TM 08676A-10/1-1 (Marine Corps),
TM 3-34.23, TM 5-5420-278-10, and TM 5-5420-279-10. Joint task force engineer planners must
recommend appropriate circumstances for risk or caution crossings to the commander and receive the
delegation of authority for approval of such crossings.
8-37. An engineer officer must periodically inspect the bridge for signs of failure when routine caution
crossings are made and after each risk crossing. Structurally damaged parts must be replaced, repaired, or
reinforced before traffic can resume. An engineer light dive team can assist in determining the extent of any
subsurface damage and can complete repairs. (See TM 5-600/AFJPAM 32-1088 for additional information
on bridge inspections, maintenance, and repair.)
8-38. All civilian bridges are not designed to support military MSR traffic, and the required load
classifications may not be known when forces initially enter the AO. There are numerous bridge types that
forces may encounter in a given AO, and there is no single, easy approach to classifying all of them.
COMBATANT COMMANDER
9-5. The CCDR is responsible for the major decisions involving base camp location and development
within the AO. The CCDR may delegate authority for base camp decisionmaking to Service component
commanders or to commanders exercising Title 10 USC Service responsibilities. Decisions are often made
in consultation with the HN, subordinate commanders, and U.S. Department of State representatives. The
CCDR establishes the policies, requirements, and procedures for master planning in the JOA. The
requirements for master planning are linked to the theater-basing strategy. The CCDR specifies (in
OPLANs and OPORDs) the construction standards for the overall operation of facilities in the theater to
minimize the construction effort expended on any given facility, while assuring that the facilities
adequately support the mission and meet health and safety requirements.
ENGINEER COMMANDERS
9-7. Engineer commanders and staff are responsible for assisting the supported commanders by
furnishing engineer advice and recommendations to the commander and other staff officers; preparing the
engineering portions of plans, estimates, and orders that pertain to base camps; participating on project
approval and acquisition review boards and base camp working groups as necessary; and coordinating and
supervising specific engineer activities for which the engineer staff is responsible. The engineer staff assists
the commander by performing a variety of functions to synchronize engineer operations in the operational
area. (See FM 3-34 and MCWP 3-17 for more information.)
9-12. Base camps and bed-down facilities may include new or prefabricated construction and make
maximum use of existing structures (with and without repair or modification).
9-19. A design guide is a design tool for standardizing sustainable energy and water efficiency, safety, and
protection measures; and promoting visual order and consistent architectural themes. It is a written and
graphically depicted set of standards that governs the design, development, visual aspects, and
maintainability of a specific base camp. A design guide applies mostly to longer-duration base camps and
those that will likely be transferred and become permanent facilities/sites in the HN. The guide also may be
used to define performance and customer service standards for various base operations functions. (ATP 3-
37.10/MCRP 3-17.7N and EP 1105-3-1 for additional information.)
9-20. An environmental baseline survey is—
(Joint) A multi-disciplinary site survey conducted prior to or in the initial stage of a joint
operational deployment (JP 3-34).
(Army) An assessment or study done on an area of interest (a property) in order to define the
environmental state or condition of that property prior to use by military forces. Used to
determine the environmental impact of property use by military forces and the level of
environmental restoration needed prior to returning the property upon their departure. (FM 3-
34.5/MCRP 4-11B)
9-21. The EBS documents the original environmental condition of the land. An EBS is required if an area
is to be occupied by U.S. forces for more than 30 days. (See FM 3-34.5/MCRP 4-11B, EP 1105-3-1, and JP
3-34 for additional information on the EBS.)
9-22. General site planning is finding and plotting, to scale, a logical location for every aboveground area,
facility, and infrastructure requirement, along with the portrayal of the various, often invisible, major utility
corridors, safety clearance zones, and various boundaries that influence and support the base camp
development plan (EP 1105-3-1). It requires multidisciplinary expertise in a process that links architecture,
engineering, military operations planning, antiterrorism/force protection, the environment, social science,
and community planning. The result of this process establishes plan-view dimensions, corridors, zones, and
boundaries for the development of a base camp, usually portrayed on overlays to maps of the area. (ATP 3-
37.10/MCRP 3-17.7N and EP 1105-3-1 for additional information.)
9-23. Land use planning is the process of mapping and planning the allocation of land use areas based on
general use categories, mission analysis products, functional requirements and interrelationships, and
criteria and guidelines (ATP 3-37.10/MCRP 3-17.7N). A land use plan is like a jigsaw puzzle, because
each piece of the plan is intended to fit together to form a whole that is greater than the sum of the parts.
The plan is sized and shaped to account for constraints that cannot be overcome, to take advantage of
opportunities that exist, to accommodate existing requirements, and to allow for future expansion.
Compatible land uses are placed close to each other, and incompatible land uses are not. (ATP 3-
37.10/MCRP 3-17.7N and EP 1105-3-1 for more information.)
9-24. The master planning for base camps generally follows the process that is used for permanent
installations, except it has a shortened planning horizon and may not be prepared to the same level of detail.
(See AR 210-20, ATP 3-37.10/MCRP 3-17.7N, and EP 1105-3-1 for additional information on master
planning.)
9-25. Site design (sometimes referred to as site planning) includes the actions taken by a design
professional to draw up and prepare detailed plans, specifications, and cost estimates for the construction or
renovation of facility complexes, individual buildings, infrastructure, and supporting utilities. The term site
design is used to avoid confusion with the terms site planning and general site planning. (ATP 3-
37.10/MCRP 3-17.7N for more information.)
9-26. Base camp cleanup and closure is the process of preparing and executing alternative COAs to vacate
a base camp after a U.S. military mission is complete. An archival record is prepared that includes the
operational history of the base camp, the actions taken to clean up and close the base camp, and a
description of cleanup and closure tasks that could not be completed which may lead to land use, health,
safety, and environmental problems in the future. (ATP 3-37.10/MCRP 3-17.7N and EP 1105-3-1 for more
information.)
BED-DOWN FACILITIES
9-27. Some expeditionary or initial bed-down facilities are located within a base camp after base
development begins. The CCDR may choose to develop some base camps very early in a campaign or
operation so that some bed-down facilities are within base camps from the start. Bases and base camps
support the reception, bed-down, and employment of personnel, equipment, and logistics. Bed-down
facilities are expeditionary or initial operating facilities with construction standards designated by the
CCDR. Force bed-down facilities include billeting, dining halls, religious support facilities, medical clinics,
hygiene facilities motor pools, and aircraft facilities.
9-28. The planning for bed-down is fully integrated with the CCDR basing strategy, since some of these
initial facilities will later be expanded and upgraded. Life cycle planning flows from bed-down, to a
scheme of base camps, to transfer or close. The information generated from master planning facilitates
future cost benefit analyses that enable decisionmaking for other aspects of base camp operations. (See AR
210-20 for additional information on real property master planning for U.S. Army installations for
considerations that can be applied to contingency operations.)
Standardization.
Survivability.
STANDARDS
9-35. Table 9-1 provides an example of CCDR construction standards for various types of construction that
guide GE activities.
9-36. DOD construction agents are the principal organizations to design, award, and manage construction
contracts in support of some semipermanent facilities and permanent facilities.
9-37. Major construction standards are as follows:
Semipermanent. Semipermanent construction standards allow for finishes, materials, and
systems selected for moderate energy efficiency, maintenance, and life cycle cost with a life
expectancy of more than 2 years, but less than 10 years.
Permanent. Permanent construction is designed and constructed with finishes, materials, and
systems selected for high-energy efficiency and low maintenance and life cycle cost. Permanent
construction has a life expectancy of more than 10 years. The CCDR must specifically approve
permanent construction.
used in the event of a deployment (such as in Kuwait or Turkey), or in a friendly nation to support active
combat operations in a nearby country (such as in Qatar).
9-43. USACE initiated base camp development planning to assist military planners and establish a process.
Key considerations in base camp development planning include—
Selecting suitable base camp locations, while coordinating with CCDRs, the U.S. Department of
State, the Federal Emergency Management Agency, other federal agencies (as appropriate), and
the HN.
Planning and documenting the detailed actions needed for a properly located and sized base
camp that consider related land areas, facilities, utilities, and other factors to provide U.S. forces
with the safest, healthiest, and best living and working conditions in the TO.
Planning and executing the cleanup and closure of a base camp in a manner that meets U.S. and
HN standards or those approved by the theater command.
9-44. The base camp development planning process focuses primarily on the engineer-specific areas of
base camp planning, but also requires team effort contributions from many participants. Base camp
planners assist in the location, design, construction, cleanup, and closure of base camps that support
military forces or governmental organizations across the range of military operations.
9-45. Integral to the base camp development planning process is the expectation that base camp
development has a limited time frame and, therefore, will require rapid planning and fast-track
construction. Other factors (such as rapidly changing military and political situations, parallel missions in
the same or neighboring regions, or a reintroduction of combat operations into the target area of the
proposed base camp) may require the steps in the planning process to be altered. Also, the requirement to
serve HN needs and address concerns regarding the establishment of a single base camp or a series of base
camps may change the described steps of the planning process and the options influencing flexibility within
each planning step. The intended life-span of the facilities and infrastructure of a base camp depends on
mission-driven and economic decisions. A likely component of this effort is the FFE support that USACE
will provide to the tactical commanders who determine the need for a base camp.
9-46. The base camp development planning process is a time sensitive and mission driven, cyclical
planning process that determines and documents the physical layout of properly located, sized, and
interrelated land areas, facilities, utilities, and other factors to achieve maximum mission effectiveness,
maintainability, and expansion capability in theater. The base camp development planning process is
depicted in figure 9-1. Planners rarely perform these steps in exact sequence; consequently, numbers are
not assigned to these steps. At times, planners may enter the process when it is well under way, since
planning is iterative and intuitive in nature. (See EP 1105-3-1 for more information on base camp
development planning.)
9-47. The base camp development planning process requires a multidisciplinary, multistaff team approach
to efficiently identify, analyze, and develop workable solutions to the many challenges that will require
addressing. Base camp planning team members may consist of commanders and staffs from the units that
will occupy, or may already be occupying, the base camp; operational planners and protection experts; civil
affairs specialists; technical experts in engineering and other design professions; environmental and
preventive medicine experts; resource managers; range and training experts; program analysts; contracting,
real estate, and other legal specialists; and HN planners. In other words, organizations that have a major
role or will impact the base camp development planning should be included in the team.
9-48. The base camp development planning process is an iterative process that is continuous; it is not
finished until the facilities and land are turned back over to the HN. Base camp development plans must be
shaped to improve base camp living and working conditions. For example—
Tents convert to shelters; shelters convert to buildings.
Field sanitation converts to chemicals; chemicals convert to waterborne systems.
9-49. All levels of command are involved in real property planning and its related facility programming
actions. Therefore, base camp development planning is reviewed and approved by the base camp
commander or designated representative by means of a base camp planning board and by higher echelons
as appropriate. This procedure has the added advantage of serving as a check and balance against hasty or
capricious planning. The additional technical review and approval of development plans for specialized
projects and facilities (such as the planning of munitions storage and handling facilities, ranges and training
areas, and high-security and aviation facilities) are required.
9-50. Base camp development planners should consider the objective end state condition of the base camp
facilities and the land area it occupies from the very start of the planning process. Initial agreements should
address the cleanup, closure, and disposal or turnover of facilities to the HN that were once occupied by
U.S. forces. The objective condition of formerly occupied land must be thoroughly defined, because in
many cases, the original owners want it returned in the same condition that it was in prior to U.S.
occupancy.
9-51. The TCMS is the official U.S. Army tool for base camp development planning and design.
PLANNING FACTORS
9-55. Planning factors can be found in ATP 3-37.10/MCRP 3-17.7N.
9-56. The ASCC engineer staff and subordinate commands rely heavily on FFE, in the form of forward
deployment and reachback, to accomplish base camp design, construction, and management functions. The
facilities engineering team is ideally suited to serve as a directorate of public works for a base camp in a
contingency operation. (See FM 3-34 for a discussion on the teams and resources available.)
9-58. The design must also consider the operational aspects of the base camp and include base camp land
use categories that will support the purpose of the base camp. (ATP 3-37.10/MCRP 3-17.7N for
information on base camp land use categories.)
9-59. To determine the requirements for land, facilities, and infrastructure, base camp development
planners must assess the mission, population, purpose, life-span, construction standards, and commander’s
guidance.
Population
9-60. The base camp population includes tenant and transient units and organizations, which can include
U.S., multinational, and HN personnel, units, and organizations (CAAF and non-CAAF). Transient units
and organizations are those that come to the base camp for specified services and support, which may not
necessarily require overnight stays. Determining the number of transients that a base camp will serve is a
critical factor in accurately identifying requirements for base camp facilities, infrastructure, services, and
support. Sources of population data for a base camp include—
Table of organization and equipment documents.
Table of distribution and allowance documents.
Nonappropriated fund documents and other U.S. government documents that provide data on
segments of the population, such as contractor personnel and local national employees.
The time-phased force and deployment list.
The civilian tracking system, which provides information regarding U.S. civilians present or
scheduled to be present in the TO.
U.S. government contracting documents that authorize U.S. and foreign contractors and HN
employees. This personnel count must be added to the personnel count of the assigned military
units to determine the total planned population of a proposed base camp.
The purpose or reason for using the facility to support the mission.
The projected service life for the use of the facility.
Construction standards as found in Unified Facilities Criteria and local building codes.
Commander’s guidance as outlined in the OPLAN or OPORD.
Fire Protection
9-61. Fire protection must be planned into the design of all base camps. Tent separations, wiring standards,
and Soldier or Marine education are all critical components in reducing or preventing base camp fires and
mitigating their effects on Soldiers, Marines, and equipment. On a historical note, more than 50 tents in
Kuwait were lost due to fires during Operation Enduring Freedom/Operation Iraq Freedom. Most fires were
due to improper electrical wiring connections and involved contractor-supplied tents that lacked the same
flame-retardant material that military-issued tents have. A lack of proper spacing, cleanliness, unit
discipline, fire protection equipment, and training contribute to fire hazard.
Utilities
9-62. Utility system design must be based on current applicable technical manuals and guidance.
Engineering calculations will be used to size the system. Where economically supportable and practicable,
electric grids should be connected to commercial power. Smaller or remote bases should construct central
power plants capable of supporting 125 percent of the camp maximum demand load or use distributed
generators of sufficient capacity to support maximum demand loads. When stand-alone, distributed
generators are the main power source, they will be sized so that no generator set is loaded at less than 50
percent capacity.
9-63. Base camp utilities should be tied into local municipalities if it is economically feasible and if they
meet health and other protection standards. The installation of wells for potable water is authorized. There
should be a minimum of two wells per camp—one primary and one for backup (located within the camp
boundaries). The last choice is to use the Tactical Water Purification System, potable-water trucks, or
bottled water.
Potable Water
Food Service
Maintenance
Ammunition
Solid Waste
Wastewater
Parking Lot
60 kilowatt
Generator
Bulk Fuel
Laundry
Helipad
Shower
Latrine
Roads
Billets
Facility
Latrine 300 300 500 200 200 15 200 50 300 100 200 0 50 300
Food service 300 300 500 300 300 15 200 50 300 50 200 300 300
Potable
300 200 300 300 300 15 200 50 200
water
Roads 15 15 300 15 15
Ammunition 300
Solid waste
CONSTRUCTION
9-69. The CCDR, JFC, and ASCC with Title 10 USC responsibilities identify the minimum-essential
engineering and construction requirements for facilities, including the new construction and repair of war-
damaged facilities. For the ASCC, the theater engineer command is normally responsible for planning,
prioritizing, and tasking subordinate units for project execution. The theater engineer command can provide
construction assistance and restoration support to the other Services when assets are available or as directed
by the ASCC. Support may also be provided to allied forces when they are assisting U.S. operations. The
CCDR or JFC may designate a regional wartime theater construction manager to coordinate and prioritize
engineer construction activities of Services in a geographic area.
Site Selection
9-71. Site selection and layout are shared responsibilities between the engineer and architects and the site
user. The engineer, protection officer, operations officer, and logistician may each have their own ideal site
location, but trade-offs are made based on a priority of criteria or restrictions.
9-72. Emphasis should be placed on the—
Tactical situation.
Capability to defend the site.
Local terrain features.
Distance from population centers.
Availability of suitable existing facilities that may be occupied immediately or modified to
desired specifications.
Environmental restrictions that may limit the size of the required facility. (These may be caused
by weather or HN policies.)
Other environmental considerations that may affect facility locations, designs, or requirements.
Accessibility to projected traffic.
Distance from road networks.
Availability of construction materials and local labor assets.
Local weather conditions and climatic extremes that may demand refrigeration or other climate
control measures.
Potential mission expansion and surge requirements.
Layout
9-73. When locating and positioning each support area facility, the commander evaluates all information
gathered in the planning and reconnaissance phases. Once the commander or designated representative has
finalized a decision on where the installation is to be built, the engineer develops a construction plan that
takes into consideration the location and available resources (military, HN, or contract construction
personnel, materials, and equipment). The layout should be well communicated, coordinated, and organized
in such a way that it can be completed in time to meet the operational priorities and minimize future
controversies.
9-74. Internal operating efficiency must also be considered in the facility layout. The TCMS and AFCS
illustrate typical standardized installation layouts. New construction and use of nonstandard designs must
be held to a minimum. When feasible, facility requirements must be met first by the use of existing
facilities (U.S. and HN), organic unit shelters, and portable or relocatable facility substitutes.
9-75. The standards for new construction (initial or temporary) are dictated by the CCDR or ASCC based
on the expected duration of use, availability of materials, man-hours of construction effort, and material
cost. Locally available materials may dictate design and construction criteria. Plans are provided for many
supply and maintenance facilities in the TCMS. Modification may be required to adapt to local conditions.
Housing Facilities
9-79. The Sand Book and Base Camp Facilities Standards for Contingency Operations (commonly known
as The Red Book) are examples of CCDR guidance that provide very specific recommended minimum
planning factors and construction standards for facilities within base camps. The Southeast Asia hut is a
frequently used solution for bed-down and base camp facilities. (See figure 9-2.)
9-80. Southeast Asia huts, as shown in a cluster configuration in figure 9-2, are 512 square feet (16 feet x
32 feet). A Southeast Asia hut has eight 110- or 220-volt electrical outlets. Normally, there is an
environmental control unit on each end for climate control. A Southeast Asia hut is constructed of wood
with a sheet vinyl floor, 5/8-inch gypsum walls and ceiling, flat latex paint, metal roof, precast concrete
pilings, painted exterior, and a nail board 6 feet above the floor (which allows Soldiers or Marines to put a
nail on the wall to hang things).
9-81. A variation of the Southeast Asia hut is the Davidson Southeast Asia hut, which combines six
Southeast Asia huts to save materials. When in a Davidson configuration, there are five Southeast Asia hut
units, with one 12-foot by 32-foot latrine, for a total of 2,944 square feet of enclosed space. There is a 5-
foot-wide walkway on each side. An administrative configuration has 3,072 square feet, but the latrines
only take up 256 square feet. It has walkways all around the building. The entire footprint is 42 feet by 106
feet, including walkways.
Each SEA hut is 16’ x 32’, same size as a general purpose medium tent.
Legend:
SEA Southeast Asia
Surge Housing
9-84. Base camps should maintain the ability to expand to house an additional 10 percent of the total
population as transients and surges. During surge periods that exceed 10 percent, Tier 2 tents (maximum)
will be used for housing. The definition of construction standards for tents includes—
Tier 1. Tier 1 consists of a general-purpose, medium field tent with plywood floor panels.
Tier 2. Tier 2 consists of a general-purpose, medium field tent with plywood floor panels, two
electrical light outlets, two electrical outlets, and space heaters.
Tier 3. Tier 3 consists of a general-purpose, medium field tent with a full wooden tent frame,
plywood panel sidewalls, raised insulated flooring, four electrical light outlets, eight electrical
outlets, and space heaters.
9-86. Considerations should be given to shower water reuse systems or other water reuse systems.
Adjacent property use. Present and potential future uses are important. Deeds of restriction
may be required for adjacent properties near the ammunition storage areas to reduce premature
detonation caused by outside hazards.
Wet climates. Particularly in the tropics, the maximum effort must be made to combat the
effects of moisture. Adequate shelter, dunnage, and ventilation must be provided.
Very hot and very cold areas. Static electricity is an important consideration.
9-102. The longer the anticipated duration of the conflict, the greater the need to support medical
treatment through fixed facilities. While medical facilities always entail a considerable amount of
environmental considerations in temporary and fixed facilities, the importance of these considerations will
increase over time and they should be applied as early as possible. These facilities must be designed and
built with the capacity and means to adequately treat injuries and other health problems sustained during
the contingency.
9-103. Medical treatment facilities must facilitate rapid, high-quality treatment within the theater to
expedite Soldier or Marine duty return. In addition, U.S. forces are responsible for the well-being of enemy
prisoners of war, DOD employees, contractors, and other nonmilitary personnel who accompany combat
forces, such as the mass media and nongovernmental organizations. The emergency treatment of allied
Soldiers or Marines or the civilian population may also be required.
9-115. Resettlement is conducted by military police to shelter, sustain, guard, protect, and account for
dislocated civilians as a result of military or civil conflict or natural or man-made disasters. Resettlement
operations include dislocated civilians, refugees, migrants, expellees, internally displaced persons,
evacuees, and stateless persons.
9-116. General engineers may be required to support the construction of detention or resettlement
facilities. (See FM 3-63 for additional information on detention facility designs and logistics
considerations.)
9-117. Depending on the duration and extent of the conflict, requirements for the evacuation of internees
may warrant the establishment of internee holding areas within the corps area and semipermanent detainee
facilities within more secure locations. Further evacuation to semipermanent or permanent facilities outside
the AO may also require provisions for total evacuation. The discussion of detainee facilities in this chapter
is limited to the BCT, regimental combat team, division, and theater levels. Generally, internees are
evacuated for their own safety, for interrogation, for medical treatment, or to relieve troops in the capturing
unit.
9-118. Once detainees are gathered at detainee facilities, they may constitute a pool of potential labor
assets. They are, however, subject to special considerations and limitations. Detainees constitute a
significant labor force of skilled and unskilled individuals. These individuals should be employed to the
fullest extent possible in work that is needed to construct, manage, perform administrative functions for,
and maintain the detainee facility. Per AR 190-8, detainees may be employed in other essential work only
when other qualified civilian labor is not available.
9-119. Detainee labor, which is external to the DOD, is regulated through contracts. (See AR 190-8 for a
complete discussion on the employment and compensation of detainees.)
9-120. Exercise caution when contemplating the use of internees for labor, and contact the staff judge
advocate for guidance. The staff judge advocate ensures that the policy complies with all treaties and
conventions. (See Convention [III] relative to the Treatment of Prisoners of War, Geneva; FM 3-63; and JP
3-63.)
Planning Considerations
9-121. The CCDR is responsible for detainee and resettlement operations and provides engineer and
logistics support to the military police commander for the establishment and maintenance of detainee and
resettlement facilities. Planning for the construction of detainee or resettlement facilities must be developed
early in the operation plan. This provides the timely notification of engineers, selection and development of
facility sites, and procurement of construction materials.
9-122. The military police coordinate facility locations with engineers, logistics units, higher
headquarters, and the HN. The failure to properly consider and correctly evaluate all factors may increase
the logistics and personnel efforts required to support operations. If a facility is improperly located, the
entire internee population may require relocation when resources become scarce. (See the planning
considerations in FM 3-63 and JP 3-63 when selecting a site.)
9-123. Engineer participation in managing internee activities includes providing construction support for
building or renovating detainee facilities and employing internee labor in engineer tasks where appropriate.
(See FM 3-63 and JP 3-63.)
Site Selection
9-124. Detainee facilities must be planned early enough during a contingency operation to provide for
timely site selection and development. Construction materials must be procured and construction initiated
promptly. Contingency construction should be planned for a possible expansion capacity if there is a surge
in the acceptance of additional enemy prisoners of war. The site should be located on a topographic high
point with free-draining subgrade soil. This will serve to minimize additional earthmoving requirements for
drainage.
9-125. Greater sanitary precautions must be taken when working in an environment with high water tables
or in a swamp-like environment. Planners should ensure that an adequate potable-water supply, a sewage
system, an electrical power supply, and nearby construction materials are available. If possible, existing
structures should be used to minimize new construction; however, the same basic safety and environmental
considerations and conformity apply. (See FM 3-63 and JP 3-63 for additional information.)
Construction
9-129. Detainee and resettlement facility construction standards, bills of material, and estimates of
construction man-hours are contained in the TCMS and AFCS. The length of time that the facility will
operate must be considered when determining the standard of construction. In addition, engineers must
complete an EBS, in conjunction with an EHSA, for the site. (See FM 3-19.4, FM 3-63, and JP 3-63.)
commander has the overall responsibility for maintenance and repair. Capabilities that extend beyond
tenant units require support by general engineers.
9-138. Units and organizations that occupy facilities are encouraged to establish internal teams that
perform routine maintenance and repair of facilities. Engineers perform maintenance and repair work that
exceeds the capabilities of user units. This support usually requires specialized skills or heavy equipment.
9-139. General engineers can assist the base camp commander by providing routine maintenance and
services on base camp facilities. This can include facility inspections, structural assessments, construction
material orders, and work schedules. Because materials and parts can be in short supply, base camp
commanders, with the assistance of engineer advisors, must be vigilant in establishing a proactive
maintenance program.
9-140. Base camp commanders are responsible for establishing, directing, and controlling 24-hour
emergency response to base camp incidents due to acts of nature, accidents, or enemy activity. (See
ATP 3-37.10/MCRP 3-17.7N) General engineers can also provide rapid response, which includes—
Performing immediate repair required after natural disasters (floods, tornadoes, hurricanes).
Restoring power outages.
Fixing water main leaks that impact key facilities.
Responding to fuel and hazmat spills and leaks.
Fighting fires and dealing with the aftermath of explosions.
Repairing perimeter fencing, barriers, and obstacles to prevent enemy penetration.
Repairing lighting and other security systems to restore observation and monitoring.
Repairing facilities that are deemed mission-critical and -essential to base operations.
CHIEF OF ENGINEERS
10-2. The chief of engineers is the DA staff officer responsible for real estate functions and, as such,
exercises staff supervision over U.S. Army real estate activities of overseas commands. (See AR 405-10.)
The chief of engineers is responsible for carrying out the following duties:
Establish real estate records and reporting systems necessary to administer responsibilities.
Provide technical advice and assistance in handling real estate acquisition, management of lease
actions, and disposition.
Issue instructions to ensure that real estate activities are conducted according to applicable
directives, policies, and regulations.
Review real estate data, including estimates, justifications, records, and reports.
10-5. The real estate teams conduct real estate management within their assigned areas according to the
directives, instructions, and standard operating procedures. A contingency real estate support team is
deployable and can acquire, manage, and dispose of real estate on behalf of the U.S. government. The
contingency real estate support team has the capability to—
Acquire land or facilities, manage lease and use agreements, dispose of land or facilities, and pay
rents and damages for real estate used within the AO.
Investigate, process, and settle real estate claims.
Conduct utilization inspections.
Record, document, and prepare reports on the real estate used, occupied, or held by the U.S.
Army (or joint forces, as appropriate) within their assigned areas.
Coordinate with agencies of the friendly HN to execute joint U.S. and HN real estate functions.
Coordinate with the staff judge advocate for legal issues and claim settlements.
Include an EBS and EHSA, when possible and appropriate, in all real estate actions.
Note. See FM 3-34 and EP 500-1-2 for more information on the organization and roles of the
contingency real estate support team.
COMBATANT COMMANDER
10-11. A CCDR is responsible for all real estate activities within the AO. This responsibility may be
delegated to a designated deputy or to the U.S. Army, U.S. Navy, or U.S. Air Force Service component
commander with the greatest requirements and the appropriate authority and technical real estate staff
expertise. Maintaining a single inter-Service real estate facility use policy consolidates activities, reduces
duplication, and limits the impact on the local economy. The theater commander may establish a central
real estate office to direct and record all real estate activities or direct that the commander assigned real
estate responsibility establish such an office. The CCDR develops the policies and procedures for real
property and base camp transfers as part of the theater basing strategy. Associated guidance on
environmental considerations will be provided in an annex of the OPLAN or OPORD. The commander of
the assigned AO is responsible for the timely identification and mitigation of negative environmental
impacts within the AO. (See FM 3-34.5/MCRP 4-11B for more information on the environmental real
estate considerations.)
OBJECTIVES
10-21. The efficient conduct of real estate activities depends largely on a command-wide understanding of
the objectives of the real estate program in overseas commands. These objectives are to—
Acquire and administer real property that is essential to the mission.
Acquire and use existing facilities to keep new construction to a minimum.
Acquire environmentally safe real property and facilities that promote force health protection
and coordinate for the performance of an EHSA when applicable.
Protect the United States and its allies against unjust and unreasonable claims and charges for
using, renting, or leasing real or personal property. Linking an EBS to the signing of a lease,
when possible, is an excellent method of providing desired financial protection for the
government.
Provide reasonable compensation to individuals or private entities for the use of real property,
except enemy-held property or, possibly, property that is located in a combat zone or enemy
territory.
PLANNING
10-24. These are key terms related to real estate and real property maintenance:
Real estate is interests in real property as referred to as rights or estates, hence real estate is
similar to real property (AR 405-45).
A facility is a real property entity consisting of one or more of the following: a building, a
structure, a utility system, pavement, and underlying land (JP 3-34).
A joint facilities utilization board is a joint board that evaluates and reconciles component
requests for real estate, use of existing facilities, inter-Service support, and construction to
ensure compliance with Joint Civil-Military Engineering Board priorities (JP 3-34).
Maintenance is the routine recurring work required to keep a facility in such condition that it
may be continuously used at its original or designed capacity and efficiency for its intended
purpose (JP 4-0).
Operation and maintenance is the maintenance and repair of real property, operation of utilities,
and provision of other services such as refuse collection and disposal, entomology, snow
removal, and ice alleviation (JP 3-34).
Real property is lands, buildings, structures, utilities systems, improvements, and appurtenances,
thereto that includes equipment attached to and made part of buildings and structures, but not
movable equipment (JP 3-34). AR 405-45 provides additional clarity by stating, “It includes
equipment affixed and built into the facility as an integral part of the facility (such as heating
system), but not movable equipment (such as plant equipment). In many instances, this term is
synonymous with ‘real estate’”.
Solid waste is garbage, refuse, sludge, or other waste material (except those excluded by Federal
regulation) in the form of solid, liquid, semi-solid, or contained gaseous material that has been
discarded or is being accumulated, stored, or treated prior to being discarded as a result of
institutional, industrial, commercial, mining, agricultural, or community operations and
activities. (For purposes related to recycling, infectious waste material is not included in this
category.) (See Section 261.2, Title 40, Code of Federal Regulations for additional information.)
PLANNING GROUP
10-30. A planning group, which includes the combatant command staff and representatives of all Service
commanders, must initiate real estate planning during the preparatory phases of a campaign. The agency
that will execute real estate operations when the campaign begins is organized at this time and should
participate in all planning activities. Real estate support enables force projection and enables logistics
support for theater opening. In addition to plans for real estate operations during hostilities, consideration
should be given to real estate requirements for the occupation period after hostilities cease. This may be
most critical for those requirements that will be met by new construction, such as base camps.
10-31. The site selection process is a joint effort that is conducted by several members. If available, a
USACE contingency real estate support team member should be included as an integral part of the site
selection team, helping to ensure site acquisition through a HN use agreement or lease of private property.
The site selection team should also include engineer, medical, or other required subject matter experts to
conduct an EBS and EHSA and integrate appropriate environmental considerations when possible. (See
ATP 4-45 for more information on on-site selection team and site selection considerations.)
EXISTING FACILITIES
10-32. Facilities are grouped into six broad categories that emphasize the use of existing assets over new
construction, as discussed in JP 3-34. Consolidate and use existing facilities as much as possible to reduce
the need for new construction. To the maximum extent possible, facilities or real estate requirements should
be met from the following categories, in the priority listed:
U.S.-owned, -occupied, or -leased facilities (including captured facilities).
U.S.-owned facility substitutes pre-positioned in theater.
HN and multinational support facilities where an agreement exists for the HN or partner nation
to provide specific types and quantities of facilities at specific times in designated locations.
Facilities available from commercial sources.
U.S.-owned facility substitutes stored in the United States.
Newly constructed facilities identified during an assessment of available existing assets.
10-33. Existing facilities should be used when they are available. The use of existing facilities—
Allows swift occupation by military activities.
Uses existing utilities; existing telephone service; and connecting air, ground, and sea LOC
facilities.
Uses available, on-site administrative and industrial equipment.
Permits less diversion of troops from combat missions.
Uses a smaller outlay of government funds and resources.
Provides some inherent camouflaging of military activity.
Note. The location may be near major government, industrial, transportation, or resource centers.
10-34. The advantages of using existing facilities normally outweigh the disadvantages. However, there
may be some disadvantages that make the facilities strongly undesirable for military use. Planners should
consider alternatives when existing facilities cannot be adapted to the desired mission requirements, such as
when—
Facilities cannot be adapted to desired survivability and force protection standards.
Dispersion is difficult or impossible.
Facilities are inflexible and cannot be tailored to meet military needs.
Environmental considerations and associated force health protection issues make the site
undesirable or questionable for occupation.
FACILITY MODIFICATION
10-42. The situation may require the modification of existing facilities to better serve military needs. This
could be as a result of changing existing mission requirements, accommodating special unit needs,
correcting deficiencies, or conducting upgrades and improvements. Correcting deficiencies should be the
primary focus of GE work. Theater planning should identify deficiencies and required corrective actions.
Theater requirements for antiterrorism and other protection tasks must be considered in the initial planning
stages. Area-of-responsibility real estate principles for property acquisition apply as discussed above. These
changes could require additional compensation to property owners and should be factored into the initial
planning and budget. Draw on the expertise, ingenuity, and innovation of engineers, HN experts, and
civilian contractors to resolve these issues. In addition, use tools such as the TCMS/AFCS to modify
existing facilities for military use and to upgrade according to applicable Unified Facilities Criteria.
RESPONSIBILITIES
10-48. Per AR 405-10, the Chief of Engineers is the DA staff officer responsible for real estate functions
exercising staff supervision over U.S. Army real estate activities in overseas commands. Real property
maintenance is administered by the theater Army area command through its subordinate area support
groups. (See TM 5-300.)
10-49. The Installation Management Command supports the U.S. Army warfighting mission by working
to provide standardized, effective, and efficient services, facilities, and infrastructure to Soldiers, civilians,
and families. Support for real property maintenance is provided on an area basis to all installations, organic
activities, and tenant units. The theater engineer command at the theater Army level provides overall
supervision and technical assistance. The administration of real property maintenance forward of the corps
rear boundary is a corps responsibility. Command relationships in the theater Army are described in ATTP
3-34.23.
PLANNING
10-50. The theater engineer command (or senior engineer brigade) and the responsible engineer staff must
consider current and anticipated real property maintenance requirements for the AO. These include—
Maintaining and repairing the LOC.
Estimating potential requirements for repairing war damage.
Coordinating phase planning and target date requirements.
Reviewing after action reviews and lessons learned from recent operations.
Considering contract support (such as the logistics civil augmentation program [U.S. Army]),
preplacement of contract vehicles, and mechanisms for the management of such contracts in
theater (such as engineer advisory board or Defense Contract Management Command).
Considering other U.S. agencies (such as the Department of State and the U.S. Agency for
International Development) that may be in the area of responsibility concurrently, considering
how the competencies of each might be leveraged, and establishing working relations across the
agencies in peacetime.
Determining the limitations (such as political) on using a cost-effective local work force and
local contractors.
Ensuring that a management system is in place that identifies facilities to support U.S. facility
needs.
Identifying procedures for the accountability, security, maintenance, and training of appropriate
local national facilities personnel if they are to be transferred to local authorities after the ceasing
of hostilities.
Integrating appropriate environmental considerations and related force health protection
concerns.
10-51. Any alteration or renovation work that is planned for existing structures should be designed
according to AFCS guidance and should essentially be nonpermanent in nature. Plans for major repairs,
renovations, or alterations on existing structures must include estimates for labor and materials. Planners
may also use estimating sources, such as the engineer performance standards or a commercial estimating
guide (means estimating guide).
10-52. There may be situations in the theater where the estimated materials or labor resources are
insufficient or unavailable. Local materials, labor, and services should be used to accomplish real property
maintenance when possible. With the approval of the theater Army engineer and support of the theater
engineer command or assigned engineer brigade, the local responsible engineer may change the design or
scope of planned project work to capitalize on locally available personnel, resources, and services.
OPERATION OF UTILITIES
10-53. In the TO, the O&M or upgrade of existing utilities and the construction, operation, and
maintenance of new utilities systems may be an engineer responsibility. Utility systems include electric
power, wastewater collection and treatment, and other systems (cooling and refrigeration, compressed air,
heating). Operating these systems requires specially certified, licensed, or trained personnel. These
personnel may be available through the theater engineer command or assigned engineer brigade, trained
locally, or hired from the local work force.
10-54. Utility systems must be reliable, properly operated, and protected. Appropriate measures should be
implemented to ensure their correct operation and servicing. Measures should be implemented to provide
increased or upgraded physical security if the situation warrants. Such measures include controlled access,
continuous inspection, and adequate security personnel. (See ATP 3-39.32 for more details on facility
physical security.)
10-57. Field sanitation measures (such as pit latrines and grease sumps), portable chemical toilets, and
waste treatment plants may be used temporarily until fixed facilities are completed and in operation. Force
health protection is facilitated through good unit standard operating procedures, leadership enforcement,
and field discipline in conjunction with the conduct of an EHSA and medical monitoring procedures. (See
ATP 4-25.12 and FM 21-10/MCRP 4-11.1D.)
10-58. As with all AFCS designs in the AO, the standard of construction for wastewater systems will
nearly always be nonpermanent and designed to require minimum maintenance during the limited time
anticipated for the period of occupation. Locally available materials may be used if approved by the ASCC
engineer. Engineers will perform real property maintenance and operate the system as directed by the
ASCC engineer. Guidance on environmental considerations will be provided in an annex of the OPORD.
(See the AFCS for standard designs of wastewater systems.)
SOLID-WASTE MANAGEMENT
10-66. Solid-waste management includes collection, recycling, and disposal. Improperly handled solid
waste can be a safety and health hazard. The local commander is usually made responsible for solid-waste
collection and disposal, and engineers accomplish the task. Guidance on solid-waste collection and disposal
is found in AR 420-1 and NAVFAC MO-213/AFR 91-8/TM 5-634.
10-67. Placing in a landfill, burning, and removing are normal means for solid-waste disposal in an AO.
Because of potential surface and groundwater contamination, the explosive hazard associated with
uncontrolled methane gas production, increased vermin activity, and the obvious problems with solid-waste
odors, it is imperative that landfills be properly planned, designed, managed, and maintained. Options
available to lessen the quantity and/or eliminate specific types of solid waste in sanitary landfills include—
Using incineration equipment.
Using recycling programs and services.
Using appropriate compost methods.
Using a combination of several methods.
10-68. Compaction and selective disposal are two alternate methods for reducing the volume of solid
waste:
Compaction. Compaction is accomplished with specialized equipment for collecting and
compacting solid waste prior to it being dumped into a landfill. At the landfill site, special
mobile compaction equipment may be used to reduce the volume of solid waste before it is
buried and covered. Other compaction and solid waste-handling techniques include compacting
and baling solid waste for burial or removal from the area.
Selective disposal. Selective disposal is the separation of certain types of solid waste, such as
wood or metal, from the waste stream. The separated material is then stored or reused.
10-69. Table 10-1 shows an example of estimated solid-waste disposal requirements in tons per day for
supported populations for standard base camp sizes and levels of base camp capabilities (basic, expanded,
and enhanced). The top end of the population range is multiplied by planning factors from ATP 3-
37.10/MCRP 3-17.7N. These estimates can be used for the initial, field-expedient planning of the total
daily, solid-waste disposal requirements for base camps when no other information is available.
Table 10-1. Example of base camp estimated solid-waste disposal in tons per day
Basic Water Expanded Water Enhanced Water
Size Population Requirements (4 Requirements (6 Requirements (10
p/per/day)/2,000 p/per/day)/2,000 p/per/day)/2,000
Extra small 299 0.6 0.9 1.5
Small 1,999 4.0 6.0 10.0
Medium 5,999 12.0 18.0 30.0
Estimate waste disposal requirements based on the planned population
Large >6,000
and planning factors.
LEGEND:
p/per/day pounds per person per day
10-70. The waste management principles of reduce, reuse, and recycle can reduce the generated waste
amounts and reduce the required capacities of disposal facilities or other waste management options. TM 3-
34.56/MCIP 4-11.01 provides information on developing more detailed waste generation rates that are
tailored to a specific situation and waste management options.
10-71. Solid-waste collection and disposal techniques depend on the volume of waste generated, the
duration of facility occupation, existing collection facilities, the resources available to perform the work,
the facility location, the situation, and the environmental aspects of the area. In some cases, selected
recycling may be enacted.
10-72. Special consideration should be given to hazardous waste, especially waste products generated by
medical facilities and maintenance operations. Hazardous waste should be disposed of according to
regulations, laws, treaties, and agreements. Specific guidance should be contained in an annex of the
OPORD. The improper disposal of hazardous waste may cause serious illness or death to those who operate
landfills or cause irreversible environmental damage. Specialized medical expertise exists to support the
engineer and the commander when dealing with hazardous waste. (See TM 5-814-7 for more information
on hazardous-waste disposal in land treatment facilities.)
Responsibilities
11-4. General engineers have the capability to plan, design, construct, operate, and maintain basic power
generation and secondary distribution systems. U.S. Army engineer prime power assets can reach back to
USACE and provide power planning beyond the capability of assigned engineers.
11-5. There is a division of labor among the specialized U.S. Army electricians who handle interior,
distribution, and power plant systems. This includes the following:
Interior system electricians. Interior electricians are trained and equipped to perform electrical
work within the interior of the building, up to the circuit box. This includes reading electrical
system blueprints; installing wiring, transformers, circuit breakers, service panels, switches,
electrical boxes, and lighting systems; and inspecting, testing, repairing, and replacing electrical
systems within facilities.
Distribution system electricians. Power distribution specialists are trained and equipped to
perform tasks associated with electrical distribution. They connect service drops and conduits on
deenergized systems. Their duties also include installing—
Electrical prime power distribution systems.
Exterior services.
Utility poles.
Guys.
Anchors.
Crossarms.
Conductors.
Insulators.
Transformers.
Other electrical hardware.
Power plant system electricians. Prime power production specialists are trained and equipped
to perform electrical assessments and facility power system maintenance. They can perform
quality assurance or quality control operations and supervision. They can operate, install, and
perform direct support/general support level maintenance on electric power plants. They can
work on prime power generator sets of 500-kilowatt capacity and higher and associated auxiliary
systems and equipment. Other duties include the liaison officer and technical advisor to the
Federal Emergency Management Agency and other federal organizations as necessary.
11-6. Every U.S. Army element that is authorized power system components (such as generators and
electrical distribution equipment) on their modified table of organization equipment is required to have a
unit power manager who is trained and licensed to operate the unit tactical power system. The tactical
power system will typically be a plug-and-play power system that provides power to the unit tactical
operations center, communication facility, or maintenance facility.
BASE CAMPS
11-13. Base camps may provide power from generators, a central power plant, or commercial utility
power sources to meet operational and life support requirements. Base camps can connect a variety of
power sources to the base camp distribution system to create a self-contained microgrid. A microgrid is a
localized grouping of electricity generation, energy storage, and loads that normally operate connected to a
traditional, commercial centralized grid (microgrid).
11-14. A microgrid may provide more efficient distribution and use of electrical power. Base camp power
generation and distribution systems may also include power storage capabilities into their grid for
supporting mission-essential facilities or equipment. The installation, operation, and maintenance of power
storage capabilities may be performed by units, interior electricians, prime power personnel, or contractors.
OTHER SOURCES
11-15. The HN may operate regional or national power systems or have commercial utility power systems
that are capable of supporting U.S. military operations. However, HN power may not be sufficient, reliable,
or compatible with U.S. military equipment or facilities. Exercise caution when considering HN power, as
it may undermine counterinsurgency goals and actions.
11-16. Contracted power support may be available through local military contracts, the USACE
worldwide power contract, or the logistics civil augmentation program. Contract support may range from
simple O&M of military power systems to the construction and leasing of large power systems to support
large base camps. (ATP 3-37.10/MCRP 3-17.7N for additional information.)
POWER CONTINUUM
11-18. The power continuum illustrates a well-planned, designed, and implemented electrical-power
system progression from initial combat operations through long-term peacetime military engagements and,
ultimately, to base camp closure. (See figure 11-1.) The power systems are constructed to be compatible
building blocks from one system to another, ensuring that all users have sufficient electrical power in a
scalable system that will support the changing electrical power demands of the theater.
11-19. Typically, a contingency power system will begin with a unit-owned tactical power system,
transition to a deployable prime power system and, ultimately, progress to the civilian- or contractor-
managed sustained power system for long-term engagements. However, the phases of the power continuum
do not have to occur consecutively and several or all phases can occur concurrently. The goal is to employ
power systems that support and build on one another.
11-20. The following power systems are depicted in the power continuum in figure 11-1:
Tactical power system. This is a highly mobile contingency power system that produces and
distributes electrical power at user voltage and is installed, operated, and maintained by Soldiers.
Initial tactical power systems are composed of modified table of organization equipment-
authorized, U.S. Army standard generators and power distribution equipment; but they may
include commercial, off-the-shelf power equipment as missions dictate. User voltage is typically
120/208 volts at 60 hertz, but may also be 230/400 volts at 50 hertz, depending on the TO.
Tactical power is generated by a mobile, electrical-power unit that is dedicated to supporting the
missions of units engaged in combat operations. Tactical power uses two classes of generators:
precise and utility. These standard military generators are highly mobile, produce low voltages,
and do not require the use of transformers. They have an output capacity that ranges from 0.5 to
200 kilowatts. These generators are in the unit table of organization and equipment and are
referred to as tactical generators. Distribution systems for tactical power are usually very simple.
They often consist of standard components, such as field wiring, distribution illumination sets,
and electrical sets. The installation, operation, and maintenance of tactical generators and
distribution equipment are the responsibility of the using unit.
Deployable prime power system. This is a deployable contingency power system that produces
and distributes electrical power at medium voltage; uses transformers to produce user voltage;
and is installed, operated, and maintained by Soldiers. Medium-voltage is typically a 2400- to
13,800-volt power system that is capable of distributing power.
Sustained power system. This is a contingency power system that is site-specific and may be
composed of low- or medium-voltage power equipment, fixed generators, and commercial
electrical equipment. It is installed, operated, and maintained by contracted civilian personnel.
11-21. See TM 3-34.45 for additional information on power systems.
POWER SYSTEMS
11-22. There are many sources of electrical power. Each source varies in complexity, efficiency, and
reliability. Routine power sources are tactical generators, prime power generators, and commercial power.
Engineers estimate power requirements; plan for sources over time; and design and construct basic power
generation systems, secondary distribution systems, and fixed-site storage systems. As the TO matures,
power requirements grow significantly and engineers conduct detailed planning to forecast and estimate
future power demands to ensure that demands do not exceed supply over time.
Utility corridors/utility space. A utility corridor is a linear strip of land, normally running
parallel with roads, that is identified for present or future locations of utility lines. Locate power
cables in dedicated utility corridors out of main traffic patterns to minimize damage and to
ensure access for repair or expansion/modification of the power system. Do not locate power
cables under facilities, T-shaped walls, sandbags, or other obstructions to access. Provide a
dedicated space for generators and other power system components out of main traffic patterns
to prevent physical damage, but allow access for maintenance or replacement.
Equipment standards. Use only commercial power system components that have been
approved by one of the nationally recognized testing laboratories or that have been inspected and
approved by the authority with jurisdiction. Military power system components must meet
military standards or adhere to military specifications. Do not use nonlisted components of
existing facilities. Replace discovered nonlisted parts. (See DA Pamphlet 385-26.)
11-24. Power system planners should be integrated into the planning committee or working group to
coordinate with facility master planners, communications personnel, force protection personnel, and
logistics personnel. This is needed to ensure that the power system will best meet the needs of all supported
and minimize conflicts with other mission requirements.
11-25. Always consider personnel and system safety with respect to locating overhead power lines in
close proximity to facilities or in areas that frequently use tall combat vehicles with tactical radio antennas,
high-lift forklifts, or cranes. Work on energized circuits during system installation or maintenance requires
an energized work permit. A complete power system design will require a short-circuit analysis of potential
fault currents to aid in determining proper circuit breaker and component sizing and ratings. The data from
the short-circuit analysis is used in an arc flash hazard analysis to determine arc flash protection
boundaries, incident energy at the working distance, minimum requirements of arc-rated protective
clothing, and potential risks to personnel performing system maintenance and to develop risk mitigation
strategies.
11-26. Automated planning and design tools, such as the TCMS, are available to provide baseline
standard designs and produce a construction bill of materials. The Auto Distribution Illumination System,
Electrical, is a computer model developed to simulate the use of the Distribution Illumination System,
Electrical, or the Power Distribution Illumination Systems, Electrical. The Distribution Illumination
System, Electrical, refers to the military family of power distribution equipment (military customized
electrical breaker boxes). These tools can aid in proper system configuration and component selection.
11-27. Additional references are as follows:
See TM 3-34.46/MCRP 3-17.7K for detailed design, layout, installation, and maintenance of
electrical systems.
See the AFCS program guidelines for standard electrical designs.
See UFC 3-500 series for commercial power system guidance, and UFC 3-501-01 for details of
electrical engineering.
See TM 3-34.45 for deployable power systems.
See TM 5-683/NAVFAC MO-116/AFJMAN 32-1083 for guidance on the facilities maintenance
of interior electrical systems.
See TM 5-684/NAVFAC MO-200/AFJMAN 32-1082 for the maintenance and repair of exterior
electrical distribution systems.
See DA Pamphlet 385-26, TM 5-682, and UFC 3-560-01 for details on safe electrical practices.
Will there be large logistics, transportation, and maintenance facilities or water purification
and ice production equipment?
Will there be a large consolidated laundry facility?
What power system assets are available, and are they sustainable? An initial assessment
includes a listing of serviceable power system equipment on-site or readily available. Decisions
to utilize or purchase nonstandard, commercial equipment must carefully consider whether the
power system is sustainable with readily available service and repair parts and whether trained
technicians are available to operate and maintain the equipment.
Note. An effective planning rule of thumb is that, for standard 120/208-volt power systems, the
total distance from the power source to the point of consumption should not exceed 300 feet.
(See TM 3-34.45 for additional information.)
Notes.
8. See DA Pamphlet 385-26, TM 5-682, and UFC 3-560-01 for electrical safety practices.
11-33. GE units may also assist in writing the scope of work for power system construction contracts.
11-34. The proper power system grounding and bonding of electrical components are essential to ensure
reliable system operation and protective device operation. This will also ensure that personnel are protected
from electrocution due to equipment malfunction. The IEEE Standard 142-2007 (commonly referred to as
the Green Book) provides guidelines for electrical system grounding and bonding. Additional standards
govern power system construction and safe electrical work practices.
11-35. Power systems that operate or will operate at the U.S. military standard 120/208 volts at 60 hertz
must be constructed to meet the standards outlined in NFPA 70: National Electrical Code; the IEEE
Standard 142-2007; the National Electrical Safety Code; and applicable military standards and directives.
Power systems that operate at different voltages or frequencies must be constructed to meet HN electrical
construction and safety standards. If the HN electrical code is inadequate, then use the TCMS to plan
electrical system construction.
operational responsibility has been transferred to a contractor. (See TM 3-34.45 for additional information
on power system configurations.)
operation of permanent and semipermanent water facilities. This includes water supply and distribution
systems within base camps, facilities, or buildings. Plumbing is a system of piping, apparatus, and fixtures
for water distribution and waste disposal within a facility or building. The facility engineer manages water
utilities on an installation or base camp.
12-13. Water testing is normally conducted at the lowest level through local medical teams. See the
Center for Disease Control and Prevention Web site for further assistance. As a reachback resource, the
center has comprehensive water-testing capabilities that exceed those of local medical teams and a staff of
subject matter experts beyond local medical teams.
WATER WELLS
12-19. Water wells are engineer construction projects and must be planned, designed, managed, and
reported in the same manner as other projects. The detailed planning, designing, and drilling of wells is
discussed in NTRP 4-04.2.13/TM 3-34.469/AFMAN 32-1072. The U.S. Navy and U.S. Air Force maintain
well-drilling capabilities, which are also addressed in this manual. Wells should be drilled in a secure area
within the AO and, if possible, within base camps or other facilities for which the water will be used. The
well-drilling team is inherently modular and deploys to the AO with the organic equipment for well
drilling.
12-20. Well-drilling teams are a theater engineer command asset and should be deployed, and employed
by, an engineer brigade or battalion capable of providing expertise and logistics support. Because the well-
drilling team has limited personnel, the engineer headquarters must plan security at the work site.
12-22. Water may be required for human consumption, agriculture, livestock, or industrial use or to
support sanitary measures. The U.S. military may have to temporarily take over the repair and operation of
a municipal water system until the local capability is restored. See the USACE Web site to obtain
information on water resources, including dams, irrigation systems, and transmission systems (aqueducts
and tunnels).
12-23. When drilling a water well, avoid drilling into the same aquifer that the local populace is using.
This will eliminate the perception that the U.S. military is taking water from the local water supply.
WATER PRODUCTION
12-29. Sustainment and engineer units contribute to water production to meet operational requirements.
Water supply units produce potable water. Water distribution units distribute potable water. Preventive
medicine personnel analyze, test, and certify water supplies. Together, these units ensure that there is
enough quality water production and distribution to continuously support the forces.
12-30. Engineer units support water production by conducting GE support, which includes—
Building combat roads and trails to establish traffic control patterns at the distribution site.
Connecting existing roads.
Clearing, preparing, and maintaining the site.
WATER DETECTION
12-32. The effective detection of groundwater sources is critical for successful well-drilling operations.
Without proper analysis, the potential for finding an adequate source is less likely. Determining the most
suitable sites to drill for groundwater falls primarily on geospatial teams and water detection response
teams.
12-33. Geospatial teams use data from the worldwide water resources database, terrain products, field
reconnaissance, geophysical surveys, and other geospatial products to recommend the best sites to conduct
well-drilling operations. They also have the reachback capability to access experts at the U.S. Army
Geospatial Center to obtain data and analysis from historical records and subject matter expertise to
identify areas with a high potential for developing water supply sources. Geospatial teams are not equipped
or trained for actual detection, only predictive analysis. The U.S. Army Geospatial Center provides water
resources information to the military community under the authority of DODD 4705.1. (See the USACE
Web site.)
12-34. In unfamiliar terrain, well-drilling teams may drill exploratory test holes to detect groundwater, but
this method is costly and time-consuming. It is only recommended if other water detection methods are not
available or have been proven to be unsuccessful.
WELL-DRILLING OPERATIONS
12-35. Wells provide water to deployed forces. Well-drilling projects should be managed the same as any
construction project. The well-drilling team commander must coordinate closely with the construction or
operations officer of the higher headquarters unit to ensure timely reporting. Because well-drilling
equipment is inherently large and heavy, engineers must ensure its mobility in areas with poor trafficability.
As the team moves from project to project, the operations officer arranges the transfer of completed work
to the user, movement to the new project site, and additional logistics and security arrangements.
12-36. Well-drilling operations include auxiliary activities that consist of exploratory drilling, soil and
rock sampling, well installation monitoring, and construction and demolition support.
12-37. Drilling rigs are truck- or semitrailer-mounted. Current well-drilling and well completion
equipment consists of a 600-foot, well-drilling system (referred to as the LP-12) that includes—
A truck-mounted drilling machine.
A truck-mounted tender vehicle.
A lightweight, well completion kit (including accessories, supplies, and tools required for
drilling a well).
12-38. The U.S. Army also uses the CF-15-S trailer-mounted, 1,500-foot, well-drilling machine and the
1,500-foot well completion kit. The LP-12 replaced the CF-15-S and 1,500-foot well completion kit, but
the CF-15-S may still be forward-deployed for contingency operations.
12-39. The LP-12 can be deployed to anywhere in the world with minimal preparation and support
equipment. With the completion kit, drillers can construct a well to a depth of 600 feet using mud, air, or a
down-hole hammer equipped with or without foam injection. With the augmentation of an auxiliary 250-
cubic-feet-per-minute air compressor, a drill pipe, and 400 feet of drilling stem, the LP-12 can drill to
depths of 1,500 feet in a variety of soil conditions, using mud or drilling foam. Additional equipment
includes casing elevators and slips, larger drill bits, and an additional drill stem. Well-drilling teams should
ensure that they have the rig accessory kit for the LP-12 to be fully mission-capable. Although well-drilling
systems can be deployed rapidly, they are thin-skinned vehicles and need protection when moving around
the battlefield.
12-40. The LP-12 is—
Air-transportable by a C-130, C-141, C-5, or C-17.
Equipped for tie-down and lift operations during transport.
Equipped for air percussion drilling and for rotary drilling with mud or air.
Equipped to drill wells up to a depth of 600 feet.
Adaptable for drilling to a depth of 1,500 feet.
Truck-mounted for mobility.
A three-mode, water transfer pumping system.
DISTRIBUTION
12-41. Sustainment and GE units conduct water distribution tasks. Sustainment units deliver water in
packages, by line haul distribution in trucks, or by hose and pipelines. They distribute water to units,
storage tanks, bulk distribution areas, and hoses or pipelines that connect to plumbing supplies.
12-42. The tactical water purification system provides the military with mobile, tactical water purification
for a broad range of water sources to meet water requirements. The U.S. Army tactical water purification
system configuration is mounted on a load handling system-compatible flat rack, while the Marine version
is skid-mounted. The tactical water purification system platform can be efficiently transported by truck,
marine vessel, or fixed-wing aircraft. Although the system is intended for use by the U.S. Army and
Marines, it can also be used to provide potable water to civilian agencies or HNs during emergencies,
disaster relief efforts, humanitarian efforts, and peacekeeping missions.
12-43. The tactical water purification system uses state-of-the-art reverse osmosis technology to produce
1,500 gallons of potable water per hour from any source, including freshwater, seawater, brackish water,
and contaminated freshwater that contains nuclear, biological, and chemical agents. The tactical water
purification system can be operated by a small crew and includes a pretreatment system, a chemical
injection kit, a high-pressure pump, reserve osmosis elements, valves, piping, a wastewater collection
system, an ocean intake system, and a storage tank system. (See TM 10-4610-309-10 (Army)/TM 10802A-
OI/1A Vol 1 (Marine Corps) for more information on the tactical water purification system.)
12-44. GE units plan, design, construct, operate, and maintain the water distribution systems that are
internal to base camps and facilities. They also support sustainment/combat service support unit water
distribution by planning, designing, constructing, and maintaining fixed distribution facilities, such as rigid
storage tanks and pipelines. The water supply may come from existing sources, existing distribution
systems, sustainment/combat service support units, or base camp water sources or wells. On a facility or
installation, water is also called a utility. Distribution pipelines enter a building and become plumbing to
the point of use; then they become waste collection systems to the point of storage, treatment, or recycling.
GE water distribution tasks include support to sustainment/combat service support units installing—
Pipelines.
Plumbing supplies.
Pipe fittings.
Sewage matter.
Size, Man-Hours
Facility Basis Qty
in feet Hor Ver Gen Total
Shop, motor repair 48x48x14 1/100 veh 1 55 1,185 287 1,527
Storehouse 20x50x8 2 sq ft/man 1 32 461 136 629
Dispensary 20x60x8 1/500 men 1 33 1,290 115 1,438
Headquarters/unit supply 20x40x8 1/200 men 3 84 1,293 240 1,617
Barracks, 50-man 20x100x8 40 sq ft/man 10 450 7,510 1,860 9,820
Kitchen Varies 1/250 men 2 154 10,352 3,788 14,294
1 shower/10
Bathhouse/latrine 20x30x8 1 24 941 61 1,026
men
1 shower/24
Bathhouse/latrine 20x80x8 1 39 1,754 150 1,943
men
Quarters (office) 20x100x8 80 sq ft/office 1 45 869 186 1,100
Guardhouse 20x60x8 1–250 men 1 33 626 115 774
Dayroom 40x60x8 5 sq ft/man 1 43 868 178 1,089
Power system 500 man light/power 1 56 460 192 708
1/2 dining/1/2
Boiler plant Varies 1 208 4,112 1,200 5,520
sleeping
Drainage 500 man 17.5 gpd 1 205 384 490 1,079
Water supply well Varies As required 1 396 45 230 671
Water tank 200 gal As required 1 105 4 109
Water distribution 500 man 25 gpd/man 1 352 812 416 1,580
effective radius,
Sump fire 10,000 gal 1 16 108 16 240
500 feet
Legend:
gal gallon(s)
gen general
gpd gallons per day
HOR horizontal
qty quantity
sq ft square foot (feet)
veh vehicle
VER vertical
Population
Facility Criteria
500 1,500 3,000 10,000
Dining sq ft/person varies by unit size NA NA NA NA
Fire station 2.6 x size of vehicle + 90 sq ft NA NA NA NA
Detainee 250 sq ft/MP + 50 sq ft/confinee NA NA NA NA
Bakery 0.6 sq ft/person supported 300 900 1800 6000
Laundry sq ft/person varies by unit size 4.4 4.4 3.3 3.0
Dry cleaning sq ft/person varies by unit size 4.4 4.4 1.75 1.0
Chapel 1.785 sq ft/person 893 2,678 5,55 17,850
Craft/hobby 1 sq ft/person 500 1,500 3,000 10,000
Gymnasium 3.3 sq ft/person 1650 4,950 9,900 33,000
Library 0.75 sq ft/person 375 1,125 2,250 7,500
Service club 7.5 sq ft/NCO; 9.5 sq ft/officer NA NA NA NA
Post exchange 1.2 sq ft/person 600 1,800 3,600 12,000
Post office sq ft/person varies by unit size NA NA 0.5 0.5
Theater sq ft/person varies by unit size NA NA 5.5 5.5
Legend:
NA not applicable
B-5. Table B-7, table B-8, and table B-9 provide examples of selected storage requirements planning
factors for base camps.
Table B-7. Covered/open storage requirements for 14 days of stockage
Base Camp Population Covered Storage, in Square Feet Open Storage, in Square Yards
500 44 1,330
1,500 132 3,990
3,000 265 7,980
10,000 882 26,600
SUMMARY
B-8. The preliminary estimate performed when planning for base camp construction should contain the
following:
Real estate required, in square feet or meters.
Equipment hours required for construction.
Man-hours required for construction, by construction skill.
Materiel requirements, in short tons.
Detailed cost estimate to allow a cost comparison of one or more base camp concept designs.
SECTION II – TERMS
None.
RELATED PUBLICATIONS
These documents contain relevant supplemental information.
AIR FORCE
Most Air Force doctrinal publications are available online at <http://www.e-publishing.af.mil/>.
AFMAN 91-201. Explosives Safety Standards. 12 January 2011.
AFPAM 10-219 V5. Bare Base Conceptual Planning. 30 March 2012.
AFPAM 10-1403. Air Mobility Planning Factors. 12 December 2011.
Air Force Doctrine Annex 3-34. Engineer Operations. 19 September 2011.
<https://doctrine.af.mil/DTM/dtmengineerops.htm>, accessed on 14 August 2014.
ARMY
Most Army doctrinal publications are available online at <www.apd.army.mil>.
AD-A243 233. U.S. Army Engineer Studies Center. Army Directorate of Public Works Reference
Guide. September 1991. <http://oai.dtic.mil/oai/oai?verb=getRecord&metadataPrefix
=html&identifier=ADA243233>, accessed on 21 August 2014.
ADP 3-0. Unified Land Operations. 10 October 2011.
ADP 3-28. Defense Support of Civil Authorities. 26 July 2012.
ADP 3-37. Protection. 31 August 2012.
ADP 5-0. The Operations Process. 17 May 2012.
ADP 6-0. Mission Command. 17 May 2012.
ADRP 3-0. Unified Land Operations. 16 May 2012.
ADRP 3-07. Stability. 31 August 2012.
ADRP 3-28. Defense Support of Civil Authorities. 14 June 2013.
ADRP 3-37. Protection. 31 August 2012.
ADRP 3-90. Offense and Defense. 31 August 2012.
ADRP 4-0. Sustainment. 31 July 2012.
ADRP 5-0. The Operations Process. 17 May 2012.
ADRP 6-0. Mission Command. 17 May 2012.
AR 25-30. The Army Publishing Program. 27 March 2006.
AR 190-8. Enemy Prisoners of War, Retained Personnel, Civilian Internees and Other Detainees.
1 October 1997.
AR 210-20. Real Property Master Planning for Army Installations. 16 May 2005.
AR 385-10. The Army Safety Program. 27 November 2013.
AR 405-10. Acquisition of Real Property and Interests Therein. 14 May 1970.
AR 405-45. Real Property Inventory Management. 1 November 2004.
FM 10-602. Headquarters and Headquarters Units, Petroleum and Water Distribution Organization.
12 September 1996.
FM 27-10. The Law of Land Warfare. 18 July 1956.
GTA 90-01-011. Joint Forward Operations Base (JFOB) Protection Handbook.
1 October 2011.
TC 5-340. Air Base Damage Repair (Pavement Repair). 27 December 1988.
TM 3-34.23. M2 Bailey Bridge. 13 August 2013.
TM 3-34.45. Engineer Prime Power Operations. 13 August 2013.
TM 3-34.51. Construction Drafting. 15 June 2012.
TM 3-34.55. Construction Surveying. 3 August 2012.
TM 3-34.61. Geology. 12 February 2013.
TM 3-34.63. Paving and Surfacing Operations. 13 August 2013.
TM 3-34.72. Pile Construction. 15 November 2013.
TM 3-34.73. Port Construction and Repair. 4 January 2013.
TM 3-34.83. Engineer Diving Operations. 2 August 2013.
TM 5-300. Real Estate Operations in Oversea Commands. 10 December 1958.
TM 5-301-1. Army Facilities Components System–Planning (Temperate). 27 June 1986.
TM 5-301-2. Army Facilities Components System–Planning (Tropical). 27 June 1986.
TM 5-301-3. Army Facilities Components System–Planning (Frigid). 27 June 1986.
TM 5-301-4. Army Facilities Components System–Planning (Desert). 27 June 1986.
TM 5-302-1. Army Facilities Components System: Design. 28 September 1973.
TM 5-303. Army Facilities Components System–Logistic Data and Bills of Materiel. 1 June 1986.
TM 5-304. Army Facilities Components System User Guide. 1 October 1990.
TM 5-315. Firefighting and Rescue Procedures in Theaters of Operations. 20 April 1971.
TM 5-610. Preventive Maintenance Facilities Engineering Buildings and Structures.
1 November 1979.
TM 5-626. Unsurfaced Road Maintenance Management. 16 January 1995.
TM 5-682. Facilities Engineering Electrical Facilities Safety. 8 November 1999.
TM 5-803-1. Installation Master Planning. 13 June 1986.
TM 5-811-6. Electric Power Plant Supply. 20 January 1984.
TM 5-814-7. Hazardous Waste Land Disposal/Land Treatment Facilities. 29 November 1984.
TM 5-818-7. Foundations in Expansive Soils. 1 September 1983.
TM 5-840-2. Storage Depots. 7 October 1994.
TM 5-850-1. Engineering and Design of Military Ports. 15 February 1983.
TM 5-852-3. Arctic and Subarctic Construction for Runway and Road Design. 29 October 1954.
TM 5-5420-278-10. Operator’s Manual for Improved Ribbon Bridge (IRB). 8 April 2003.
TM 5-5420-279-10. Operator’s Manual for Dry Support Bridge (DSB). 10 May 2004.
DEPARTMENT OF DEFENSE
Most Department of Defense doctrinal publications are available online at <http://www.dtic.mil
/whs/directives/corres/dir.html>.
Defense Contingency Contracting Handbook. October 2012. < http://www.acq.osd.mil/dpap/ccap/
cc/jcchb/HTML/read_the_handbook.html>, accessed on 21 August 2014.
DODD 3025.18. Defense Support of Civil Authorities (DSCA). 29 December 2010.
DODD 4165.06. Real Property. 13 October 2004.
DODD 4270.5. Military Construction. 12 February 2005.
FACILITIES CRITERIA
Most Facilities Criteria documents are available online at <www.wbdg.org/ccb/browse_cat.php?c=4>.
FC 1-300-09N. Navy and Marine Corps Design Procedures. 1 May 2014.
UFC 1-200-01. General Building Requirements. 1 July 2013.
UFC 1-200-02. High Performance and Sustainable Building Requirements. 1 March 2013.
UFC 1-201-01. Non-Permanent DOD Facilities in Support of Military Operations. 1 January 2013.
UFC 1-300-07A. Design Build Technical Requirements. 1 March 2005.
UFC 1-300-08. Criteria for Transfer and Acceptance of DoD Real Property. 16 April 2009.
UFC 2-000-05N. Facility Planning for Navy and Marine Corps Shore Installations.
23 January 2012.
UFC 2-100-01. Installation Master Planning. 15 May 2012.
UFC 3-230-01. Water Storage, Distribution, and Transmission. 1 November 2012.
UFC 3-230-02. Operation and Maintenance: Water Supply Systems. 10 July 2001.
UFC 3-230-03. Water Treatment. 1 November 2012.
UFC 3-240-01. Wastewater Collection. 1 November 2012.
UFC 3-240-02. Domestic Wastewater Treatment. 1 November 2012.
UFC 3-240-03N. Wastewater Treatment Systems Augmenting Handbook Operation and Maintenance.
16 January 2004.
UFC 3-240-10A. Sanitary Landfill. 16 January 2004.
UFC 3-240-13FN. Industrial Water Treatment Operation and Maintenance. 25 May 2005.
UFC 3-250-01FA. Pavement Design for Roads, Streets, Walks, and Open Storage Areas.
16 January 2004.
UFC 3-250-03. Standard Practice Manual for Flexible Pavements. 15 May 2001.
UFC 3-250-04. Standard Practice for Concrete Pavements. 16 January 2004.
UFC 3-250-06. Repair of Rigid Pavements Using Epoxy Resin Grouts, Mortars, and Concretes.
16 January 2004.
UFC 3-250-08FA. Standard Practice for Sealing Joints and Cracks in Rigid and Flexible Pavements.
16 January 2004.
UFC 3-250-09FA. Aggregate Surfaced Roads and Airfields Areas. 16 January 2004.
UFC 3-250-11. Soil Stabilization for Pavements. 16 January 2004.
UFC 3-260-01. Airfield and Heliport Planning and Design. 17 November 2008.
UFC 3-260-02. Pavement Design for Airfields. 30 June 2001.
UFC 3-260-03. Airfield Pavement Evaluation. 15 April 2001.
UFC 3-260-17. Dust Control for Roads, Airfields, and Adjacent Areas. 16 January 2004.
UFC 3-270-01. Asphalt Maintenance and Repair. 15 March 2001.
UFC 3-270-02. Asphalt Crack Repair. 15 March 2001.
UFC 3-270-03. Concrete Crack and Partial-Depth Spall Repair. 15 March 2001.
UFC 3-270-04. Concrete Repair. 15 March 2001.
UFC 3-270-07. O&M: Airfield Damage Repair. 12 August 2002.
UFC 3-270-08. Pavement Maintenance Management. 16 January 2004.
UFC 3-501-01. Electrical Engineering. 3 February 2010.
UFC 3-520-01. Interior Electrical Systems. 3 February 2010.
JOINT
Most Joint doctrinal publications are available online at <http://www.dtic.mil/doctrine/>.
CJCSM 3122.05. Operating Procedures for Joint Operation Planning and Execution System
(JOPES)–Information Systems (IS) Governance. 15 December 2011.
CJCSM 3500.04F. Universal Joint Task Manual. 1 June 2011.
JP 1. Doctrine for the Armed Forces of the United States. 25 March 2013.
JP 2-0. Joint Intelligence. 22 October 2013.
JP 3-0. Joint Operations. 11 August 2011.
JP 3-05. Special Operations. 16 July 2014.
JP 3-07. Stability Operations. 29 September 2011.
JP 3-15. Barriers, Obstacles, and Mine Warfare for Joint Operations. 17 June 2011.
JP 3-18. Joint Forcible Entry Operations. 27 November 2012.
JP 3-26. Counterterrorism. 24 October 2014.
JP 3-27. Homeland Defense. 29 July 2013.
JP 3-28. Defense Support of Civil Authorities. 31 July 2013.
JP 3-34. Joint Engineer Operations. 30 June 2011.
JP 3-63. Detainee Operations. 13 November 2014.
JP 4-0. Joint Logistics. 16 October 2013.
JP 4-01.2. Sealift Support to Joint Operations. 22 June 2012.
JP 4-01.5. Joint Terminal Operations. 6 April 2012.
JP 4-01.6. Joint Logistics Over-the-Shore. 27 November 2012.
JP 4-09. Distribution Operations. 19 December 2013.
JP 4-10. Operational Contract Support. 16 July 2014.
JP 5-0. Joint Operation Planning. 11 August 2011.
MARINE CORPS
Most Marine Corps doctrinal publications are available online at
<http://www.marines.mil/News/Publications/ELECTRONICLIBRARY/tabid/13081/Default.aspx?Custompubt
ype=Doctrine+Pubs>.
MCWP 3-17. Engineering Operations. 14 February 2000.
MCWP 5-1. Marine Corps Planning Process. 24 August 2010.
MULTI-SERVICE
ATP 3-28.1/MCWP 3-36.2/NTTP 3-57.2/AFTTP 3-2.67. Multi-Service Tactics, Techniques, and
Procedures for Defense Support of Civil Authorities and Integrating With National Guard
Civil Support. 11 February 2013.
ATP 3-37.10/MCRP 3-17.7N. Base Camps. 26 April 2013.
ATP 3-37.34/MCWP 3-17.6. Survivability Operations. 28 June 2013.
ATP 3-90.8/MCWP 3-17.5. Combined Arms Countermobility Operations. 17 September 2014.
ATTP 3-34.84/MCRP 3-35.9A/NTTP 3-07.7/AFTTP 3-2.75/CG COMDTINST 3150.1C.
Multi-Service Tactics, Techniques, and Procedures for Military Diving Operations.
12 January 2011.
ATTP 3-90.4/MCWP 3-17.8. Combined Arms Mobility Operations. 10 August 2011.
FM 3-34.5/MCRP 4-11B. Environmental Considerations. 16 February 2010.
FM 3-34.170/MCWP 3-17.4. Engineer Reconnaissance. 25 March 2008.
FM 5-430-00-1/AFJPAM 32-8013, Volume I, Planning and Design of Roads, Airfields, and Heliports
in the Theater of Operations–Road Design. 26 August 1994.
FM 5-430-00-2/AFJPAM 32-8013, Volume II. Planning and Design of Roads, Airfields, and Heliports
in the Theater of Operations–Airfield and Heliport Design. 29 September 1994.
FM 5-472/NAVFAC MO 330/AFJMAN 32-1221(I). Materials Testing. 27 October 1999.
FM 21-10/MCRP 4-11.1D. Field Hygiene and Sanitation. 21 June 2000.
MCIP 3-33.02/NWP 3-07/COMDTINST M3120.11. Maritime Stability Operations. 25 May 2012.
NAVFAC MO-213/AFR 91-8/TM 5-634. Solid Waste Management. 1 May 1990.
NTRP 4-04.2.3/TM 3-34.41/AFPAM 32-1000/MCRP 3-17.7M. Construction Estimating.
1 December 2010.
NTRP 4-04.2.5/TM 3-34.42/AFPAM 32-1020/MCRP 3-17.7F. Construction Project Management.
December 2012.
NTRP 4-04.2.13/TM 3-34.469/AFMAN 32-1072. Water-Well Drilling Operations. 1 December 2008.
NTTP 3-02.1M/MCWP 3-31.5. Ship-to-Shore Movement. May 2007.
NTTP 4-04.1M/MCWP 4-11.5. Seabee Operations in the MAGTF. February 2008.
NWP 4-0M/MCWP 4-2. Naval Logistics. July 2011.
OPNAVINST 3500.38B/MCO 3500.26A/USCG COMDTINST 3500.1B. Universal Naval Task List.
30 January 2007.
TB MED 577/NAVMED P-5010-10/AFMAN 48-138_IP. Sanitary Control and Surveillance of Field
Water Supplies. 1 May 2010.
TM 3-34.21/MCRP 3-17.1A. Medium Girder Bridge. 10 November 2010.
TM 3-34.22/MCRP 3-17.1B. Military Nonstandard Fixed Bridging. 17 October 2013.
TM 3-34.44/MCRP 3-17.7D. Concrete and Masonry. 23 July 2012.
TM 3-34.46/MCRP 3-17.7K. Theater of Operations Electrical Systems. 3 May 2013.
TM 3-34.47/MCRP 3-17.7C. Carpentry. 20 September 2013.
TM 3-34.56/MCIP 4-11.01. Waste Management for Deployed Forces. 19 July 2013.
TM 3-34.62/MCRP 3-17.7I. Earthmoving Operations. 29 June 2012.
TM 3-34.65/NTRP 4-04.2.12/AFMAN 10-903. Quarry Operations. 30 October 2013.
TM 3-34.70/MCRP 3-17.7E. Plumbing, Pipe Fitting, and Sewerage. 23 July 2012.
TM 3-34.85/MCRP 3-17A. Engineer Field Data. 17 October 2013.
TM 5-600/AFJPAM 32-1088. Bridge Inspection, Maintenance, and Repair. 6 December 1994.
TM 5-622/NAVY MO-104/AFM 91-34. Maintenance of Waterfront Facilities. 1 June 1978.
TM 5-628/AFR 91-44. Railroad Track Standards. 8 April 1991.
TM 5-683/NAVFAC MO-116/AFJMAN 32-1083. Facilities Engineering Electrical Interior Facilities.
30 November 1995.
TM 5-684/NAVFAC MO-200/AFJMAN 32-1082. Facilities Engineering Electrical Exterior
Facilities. 29 November 1996.
TM 5-803-5/NAVFAC P-960/AFM 88-43. Installation Design. 1 March 1981.
TM 5-818-1/AFM 88-3, chapter 7. Soils and Geology Procedures for Foundation Design of Buildings
and Other Structures (Except Hydraulic Structures). 21 October 1983.
TM 5-818-8/AFJMAN 32-1030. Engineering Use of Geotextiles. 20 July 1995.
TM 5-820-1/AFM 88-5, chapter 1. Surface Drainage Facilities for Airfields and Heliports.
20 August 1987.
TM 5-822-14/AFJMAN 32-1019. Soil Stabilization for Pavements. 25 October 1994.
TM 5-852-1/AFR 88-19, Volume 1. Arctic and Subarctic Construction General Provisions.
4 September 1987.
TM 5-852-2/AFR 88-19, Volume 2. Arctic and Subarctic Construction Site Selection and
Development. 21 May 1990.
TM 5-852-4/AFM 88-19, chapter 4. Arctic and Subarctic Construction Foundations for Structures.
15 October 1983.
TM 5-852-5/AFR 88-19, Volume 5. Arctic and Subarctic Construction Utilities. 31 August 1987.
TM 5-852-6/AFR 88-19, Volume 6. Arctic and Subarctic Construction Calculation Methods for
Determination of Depths of Freeze and Thaw in Soils. 25 January 1988.
TM 5-5420-212-10-1(Army)/TM 08676A-10/1-1 (Marine Corps). Operator’s Manual for Medium
Girder Bridge. 16 February 1993.
TM 10-4610-309-10 (Army)/TM 10802A-OI/1A Vol 1 (Marine Corps). Operator Manual for Tactical
Water Purification System (TWPS). 15 May 2008.
NAVY
Most Navy doctrinal publications are available online at <http://doni.daps.dla.mil/default.aspx> and at
<https://ndls.nwdc.navy.mil/default.aspx> (registration is required).
NTTP 4-04.3. Naval Contingency Engineering Operations. December 2008.
NWP 4-04. Naval Civil Engineering Operations. December 2007.
OPNAVINST 11010.20H. Navy Facilities Projects. 16 May 2014.
SECNAVINST 11011.47C. Acquisition, Management, and Disposal of Real Property and Real
Property Interests by the Department of the Navy. 26 August 2013.
SS521-AG-PRO-010. U.S. Navy Diving Manual. 15 April 2008.
<http://www.supsalv.org/pdf/Dive%20Manual%20Rev%206%20with%20Chg%20A.pdf>.
OTHER
10 USC. Armed Forces. <http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title10
-front&num=0&edition=prelim>, accessed on 14 August 2014.
10 USC 2801. Armed Forces, General Military Law.
<http://uscode.house.gov/view.xhtml?req=(title:10 section:2801 edition:prelim)>, accessed
on 14 August 2014.
32 USC. National Guard. <http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title32
-front&num=0&edition=prelim>, accessed on 14 August 2014.
49 USC 10901. Transportation, Interstate Transportation.
<http://uscode.house.gov/view.xhtml?req=(title:49 section:10901 edition:prelim)>, accessed
on 14 August 2014.
Base Camp Facilities Standards for Contingency Operations.
<http://www.eur.army.mil/pdf/Red_Book.pdf>, accessed on 14 August 2014.
40 CFR 261.2. Protection of the Environment. <http://www.ecfr.gov/cgi-bin/text-
idx?SID=06350259669347fcd740addc950ae27f&node=pt40.26.261&rgn=div5#se40.26.261_
12>. accessed on 3 February 2015.
Convention for the Protection of Cultural Property in the Event of Armed Conflict. The Hague.
<http://www.icrc.org/ihl/INTRO/400>, accessed on 14 August 2014.
Convention (III) relative to the Treatment of Prisoners of War. Geneva.
<http://www.icrc.org/ihl/INTRO/375?OpenDocument>, accessed on 14 August 2014.
Convention (IV) relative to the Protection of Civilian Persons in Time of War. Geneva.
<http://www.icrc.org/applic/ihl/ihl.nsf/385ec082b509e76c41256739003e636d/6756482d8614
6898c125641e004aa3c5>, accessed on 14 August 2014.
Convention (IV) respecting the Laws and Customs of War on Land and its annex: Regulations
concerning the Laws and Customs of War on Land. The Hague.
<http://www.icrc.org/applic/ihl/ihl.nsf/385ec082b509e76c41256739003e636d/1d1726425f69
55aec125641e0038bfd6>, accessed on 14 August 2014.
PRESCRIBED FORMS
None.
REFERENCED FORMS
Unless otherwise indicated, DA forms are available on the Army Publishing Directorate Web site at
<www.apd.army.mil>. DD forms are available on the Office of the Secretary of Defense Web site at
<www.dtic.mil/whs/directives/infomgt/forms/formsprogram.htm>.
DA Form 2028. Recommended Changes to Publications and Blank Forms.
DD Form 1354. Transfer and Acceptance of DOD Real Property.
DD Form 1391. FY____ Military Construction Project Data.
WEB SITES
Base Engineering Survey Tool Web site,
<http://proceedings.esri.com/library/userconf/proc02/pap0315/p0315.htm>, accessed on
14 August 2014.
Center for Disease Control and Prevention Web site, < http://www.cdc.gov/>, accessed on 14 August
2014.
Construction Criteria Base Index, National Institute of Building Sciences Web site,
<http://www.wbdg.org/ccb/ccb.php>, accessed on 14 August 2014.
Health Facility Planning Agency Web site,
<http://www.armyhealthfacilities.amedd.army.mil/index.html>, accessed on 14 August 2014.
NAVFAC Engineering Criteria and Programs Office, National Institute of Building Sciences Web site,
<http://www.wbdg.org/references/pa_dod_cieng.php>, accessed on 14 August 2014.
TCMS Web site, <https://redi.usace.army.mil/Pages/index.htm>, accessed on 28 January 2015.
Transportation Systems Center Web site, < https://transportation.erdc.dren.mil/tsmcx/>, accessed on
14 August 2014.
Unified Facilities Criteria Index, National Institute of Building Sciences Web site,
<http://www.wbdg.org/ccb/browse_cat.php?c=4>, accessed on 14 August 2014.
U.S. Army Combined Arms Center, Center for Army Lesson’s Learned Web site, <
http://usacac.army.mil/cac2/call/ll-links.asp>, accessed on 14 August 2014.
U.S. Army Public Health Command Web site, < http://phc.amedd.army.mil/Pages/default.aspx>,
accessed on 14 August 2014.
U.S. Army Safety Center Web site, < https://safety.army.mil/>, accessed on 14 August 2014.
U.S. Air Force Civil Engineer Center Web site, <http://www.afcec.af.mil/>, accessed on 14 August
2014.
U.S. Department of Labor Occupational Safety and Health Administration Web site,
<https://www.osha.gov/pls/oshaweb/owastand.display_standard_group?p_part_number=1926
&p_toc_level=1>, accessed on 14 August 2014.
U.S. Marine Corps Engineer School Training and Education Command Web site,
<http://www.mces.marines.mil/>, accessed on 14 August 2014.
USACE Engineer Pamphlets Web site, <
http://www.publications.usace.army.mil/USACEPublications/EngineerPamphlets.aspx? >,
accessed on 23 January 2015.
USACE Hydrology Web site, < http://www.agc.army.mil/Missions/Hydrology/AboutHyDRA.aspx>,
accessed on 14 August 2014.
USACE Publications Web site, < http://www.publications.usace.army.mil/>, accessed on
14 August 2014.
USACE Reachback Operations Center Web site, <https://uroc.usace.army.mil>, accessed on
14 August 2014.
USACE Technical Information Web site, <http://www.hnc.usace.army.mil/Missions/Engineering
/TECHINFO.aspx>, accessed on 14 August 2014.
RECOMMENDED READINGS
These documents contain relevant supplemental information.
ADRP 2-0. Intelligence. 31 August 2012.
AR 415-18. Military Construction Responsibilities. 1 December 1982.
AR 415-28. Real Property Category Codes. 15 April 2014.
AR 415-32. Engineer Troop Unit Construction in Connection With Training Activities. 15 April 1998.
ATP 2-01.3/MCRP 2-3A. Intelligence Preparation of the Battlefield/Battlespace. 10 November 2014.
ATTP 3-97.11/MCRP 3-35.1D. Cold Region Operations. 28 January 2011.
DA Pamphlet 405-45. Real Property Inventory Management. 15 September 2000.
FM 3-05.70. Survival. 17 May 2002.
FM 3-57. Civil Affairs Operations. 31 October 2011.
FM 3-90-2. Reconnaissance, Security, and Tactical Enabling Tasks, Volume 2. 22 March 2013.
FM 3-97.6. Mountain Operations. 28 November 2000.
FM 90-3/FMFM 7-27. Desert Operations. 24 August 1993.
FM 90-5. Jungle Operations. 16 August 1982.
JP 3-57. Civil-Military Operations. 11 September 2013.
JP 4-01. The Defense Transportation System. 6 June 2013.
JP 4-03. Joint Bulk Petroleum and Water Doctrine. 09 December 2010.
MCDP 5. Planning. 21 July 1997.
STANAG 2238. Allied Joint Doctrine for Military Engineering–AJP-3.12, Edition B. 20 June 2014.
<https://nso.nato.int/protected/,> accessed on 18 November 2014.
STANAG 2394. Land Force Combat Engineer Doctrine–ATP-52(B). 18 December 2008.
<https://nso.nato.int/protected/,> accessed on 18 November 2014.
TM 3-34.64/MCRP 3-17.7G. Military Soils Engineering. 25 September 2012.
TM 5-627/NAVY MO-103/AFM 91-33. Maintenance of Trackage. 1 January 1980.
TM 5-698-1. Reliability/Availability of Electrical & Mechanical Systems for Command, Control,
Communications, Computer, Intelligence, Surveillance and Reconnaissance (C4ISR)
Facilities. 19 January 2007.
TM 5-814-3/AFM 88-11. Domestic Wastewater Treatment. 31 August 1988.
TM 5-822-9/AFM 88-6, chapter 10. Repair of Rigid Pavements, Using Epoxy Resin Grouts, Mortars,
and Concretes. 20 January 1989.
TM 5-822-11/AFP 88-6, chapter 7. Standard Practice for Sealing Joints and Cracks in Rigid and
Flexible Pavements. 11 June 1993.
TM 5-830-3/AFM 88-17, chapter 3. Dust Control for Roads, Airfields, and Adjacent Areas.
30 September 1987.
UFC 3-510-01. Foreign Voltages and Frequencies Guide. 1 March 2005.
UFC 3-520-05. Stationary Battery Areas. 14 April 2008.
A P
AFCS, 4-2 engineering life cycle, 1-1 partner capacity, 1-5
air traffic control and landing environmental baseline survey. power generation and distribution,
systems, 6-11 See EBS 11-3
airbase damage repair, 6-14 explosive hazards, 10-12 electrical, 11-3
aircraft, 11-3 F Prime Base Engineer Emergency
airfield, 3-20 Force. See Prime BEEF
force projection, 2-1
ammunition storage, 9-15 Prime BEEF, 11-3
G project management, 4-3
armored vehicle launched bridge,
8-3 general engineer, 2-10 protection, 10-5, 10-8, 12-5
Army Facilities Components general engineer unit, 2-3 cultural, 10-5
System. See AFCS geospatial financial, 10-5
teams, 12-5 fire protection, 3-20
Army Geospatial Center, 12-5
protection design, 6-9
assured mobility, 2-3 H
hazmat, 3-20 R
B
Hydrologic Data Resources railroad bridging, 7-9
Bailey bridge, 8-4
Application, 12-2 Rapid Engineer Deployable Heavy
base Operational Repair Squadron
air, 11-3 I Engineer. See RED HORSE
base camp, 10-7, 10-8, 10-9, 12-3 improved ribbon bridge, 8-4 rapidly employed bridge system,
shore facility, 11-3 8-3
J
bed down, 12-5 reachback, 12-5
job site safety, 4-4
C job site security, 4-4 reachback capacity, 3-25
civil engineer, 11-3 joint assault bridge, 8-3 real estate, 10-3, 10-4, 10-5, 10-6
combat engineer, 11-3 acquisition, 10-1, 10-5, 10-8
L activities, 10-3, 10-4
combat engineering, 2-3 Army service component staff
labor
construction, 10-7 estimates, 10-10 engineer, 10-4
new, 10-9 resources, 10-10 contingency real estate
contingency operation, 10-1, 11-3, support team, 10-1
line of communications. See LOC functions, 10-1, 10-2
12-6
LOC, 10-7 guidance, 10-4
D logistics over-the-shore, 5-8 intercommand, 10-3
decontamination laws and customs, 10-5
logistics support bridge, 8-4
CBRN, 12-1 modification, 10-8
M operations, 10-5
defense support of civil
planning, 10-6
authorities. See DSCA Mabey Johnson bridge, 8-4
policies, 10-4
detainee labor, 9-20 master planning, 3-8 program, 10-4, 10-5
detention, 9-20 MDMP, 3-10 team, 10-3
drainage medium girder bridge, 8-4 transfer, 10-13
improving, 12-5 military decisionmaking process. rear area, 10-3
DSCA, 2-9 See MDMP RED HORSE, 11-3
mobility, 12-6 resettlement, 9-20
E
EBS, 10-2, 10-7, 10-8 O S
engineer reconnaissance, 3-7 obstacle, 12-7 Seabees, 5-2
Southeast Asia hut, 9-14 requirements, 10-8 water detection response team,
special forces, 2-8 theater Army area command, 12-2
10-9 water supply, 12-3
standard ribbon bridge, 8-4
Theater Construction sources, 12-5
survivability, 10-7 Management System. See units, 12-7
T TCMS water testing, 12-3
TCMS, 4-2, 10-9 threat, 11-3 well drilling, 12-1, 12-5, 12-6
theater, 10-6, 10-10 U equipment, 12-5
commander, 10-3 machine, 12-6
Unified Facilities Criteria, 3-23 operations, 12-3, 12-5
directives, 10-8
engineer command, 10-9, 10- unified land operations, 2-1 project, 12-5
11, 12-3 universal joint task list, 1-6 system, 12-6
forces, 10-11 team, 12-3, 12-6
overseas, 10-5 W Wolverine, 8-3
planning, 10-8 Warfare, Law-of-land, 10-4
real estate, 10-4 water detection, 12-5
RAYMOND T. ODIERNO
General, United States Army
Chief of Staff
Official:
GERALD B. O’KEEFE
Administrative Assistant to the
Secretary of the Army
1504401
DISTRIBUTION:
Active Army, Army National Guard, and U.S. Army Reserve: Not to be distributed; electronic
media only (EMO).
PCN 143 000164 00 PIN 105043−000