CONDUCTOR PILE INSTALLATION
OFFSHORE WEST MALAYSIA (2007)
Talisman Malaysia Ltd used a Dawson
Construction Plant hammer to drive 4off 36
conductor piles at there Global Industries, DB
Seminole Rig.
A Dawsons HPH9000 hydraulic piling hammer
was used to drive 140m piles, 74m below the
mud line.
Talisman Energy Inc. is a global, diversied,
upstream oil and gas company, headquartered
in Canada. Talismans three main operating
areas are North America, the North Sea
and Southeast Asia. The Company also
has a portfolio of international exploration
opportunities.
Talisman Malaysia had used Dawson piling
hammers successfully on numerous wells /
leases around the offshore West Malaysia
region.
DATE
06-04-2002
29-04-2002
01-05-2002
16-04-2003
02-09-2003
11-11-2003
21-12-2003
13-07-2004
LOCATION
Offshore West Malaysia
Offshore West Malaysia
Offshore West Malaysia
Offshore West Malaysia
Offshore West Malaysia
Offshore West Malaysia
Offshore West Malaysia
Offshore West Malaysia
LEASE / WELL
West Bunga Raya - 1
South Bunga Seroja - 1
North Bunga Cengkeh - 1
North Bunga Pakma - 2
North Bunga Orkid - 1
Bunga Tanjung - 1
Bunga Tulip - 1
North-West Besar - 1
Click
Pg.2
TEC. SPEC
Pg.1
Technical Specications
Click
PILE SIZE - 36 , 1 WT
PILE LENGTH - SEE BELOW
--------------------------------------HAMMER TYPE - HPH9000
RAM WEIGHT - 4,750kg
IMPACT VELOCITY - 6.0m/s
MAXIMUM PILE ENERGY - 35KNm
MINIMUM PILE ENERGY - 35KNm
BLOW RATE - 60-90bpm
BODY DIAMETER - 750mm
TOTAL WEIGHT - 13,500mm
Work Platform
P4
10.90m
52.50m
P3
Mud Line
P2
TIME
DESCRIPTION
Conductor self penetrate seabed on its own weight to 68.83m.
(5.43m. Below mud line)
74.17m
P1
137.57m
02:49
02:51 Feb 13th. Drive conductor (P2) from 68.83m to 104.43m
09:39
10:37 Feb 15th. Drive conductor (P3) from 71.64m to 104.43m
16:17
20:05 Feb 15th. Drive conductor (P4) from 104.43m to 137.57m
Remarks: All depth measured from rigging work platform. Completed A31d driving at 20:05hrs feb 15th: 2007, with 1.63m stick-up on P4 pile. 36
Conductor shoe set at 137.57m. (74.17m below Mud Line)